GAO-25-106963: IT Modernization: SBA Urgently Needs to Address Risks on Newly Deployed System

Summary

GAO-25-106963, IT Modernization: SBA Urgently Needs to Address Risks on Newly Deployed System, a November 2024 Government Accountability Office report to the Ranking Member, Committee on Small Business, House of Representatives. It reviews SBA's Unified Certification Platform project, started in 2023 to let small businesses apply for and maintain certifications for SBA's contracting assistance programs. It states that SBA paused accepting new certification applications effective August 1, 2024 and deployed the UCP system on October 18, 2024 after a delay. GAO rates risk management and cost minimally met, cybersecurity partially met and schedule not met. GAO makes fourteen recommendations; SBA concurred with three, partially concurred with three and did not concur with eight.

Summary drafted by a model from the document's text below and checked by script against that text before publication. It is a navigation aid, not a reading of what the document proves. Where AI is used

Cite this document

“GAO-25-106963: IT Modernization: SBA Urgently Needs to Address Risks on Newly Deployed System.” Original at www.gao.gov. Archived at Pandemic Darlings, https://pandemicdarlings.com/source-documents/gao-25-106963-it-modernization-sba-urgently-needs-to-address-risks-on-0759545990/, SHA-256 50c674273ed35a080d84c029ee63052ff5e836a12b46b557fccfc550e0821f07.

Full text

                United States Government Accountability Office
                Report to the Ranking Member,
                Committee on Small Business, House of
                Representatives



                IT MODERNIZATION
November 2024




                SBA Urgently Needs
                to Address Risks on
                Newly Deployed
                System




GAO-25-106963
                                               November 2024

                                               IT MODERNIZATION
                                               SBA Urgently Needs to Address Risks on Newly
                                               Deployed System
Highlights of GAO-25-106963, a report to the
Ranking Member, Committee on Small
Business, House of Representatives




Why GAO Did This Study                         What GAO Found
In fiscal year 2023, the federal               In 2023, the Small Business Administration (SBA) started the Unified Certification
government awarded $178.6 billion in           Platform project. This project is intended to allow small businesses to more
contracts to small businesses. SBA             efficiently apply for and maintain certifications to SBA’s contracting assistance
promotes small business participation          programs, compared to legacy certification systems.
in federal contracting through a variety
of contracting assistance programs.            SBA originally anticipated deploying the system in September 2024. In June
These programs rely on multiple IT             2024, SBA announced a pause, effective August 1, 2024, in accepting new
systems. However, SBA’s past                   applications for certification. GAO expressed concerns regarding the agency’s
attempts to modernize its IT systems           pause in accepting new applications until the certification system is deployed.
experienced challenges and did not             GAO also noted that SBA triggered questions about risks and available mitigation
deliver expected results.                      strategies if full deployment did not occur in September or if there were system
GAO was asked to review SBA’s                  performance issues after deployment. The risk of a deployment delay was
Unified Certification Platform project.        eventually realized, as SBA delayed UCP deployment to address system issues
This report (1) describes the project’s        identified during testing. SBA subsequently deployed the UCP system on
plans and status, and (2) evaluates the        October 18, 2024, but work remains to develop additional, more complex
extent SBA has adopted leading                 functionality, secure the system, and migrate data.
practices for risk management,                 GAO’s analyses of SBA’s efforts show that leading practices for risk
cybersecurity, and schedule and cost
                                               management, cybersecurity, and schedule and cost estimation have not been
estimation for the project. To do so,
                                               fully implemented. Accordingly, SBA faces an increased risk of additional delays
GAO summarized and analyzed
relevant documentation and compared
                                               as it completes remaining work and may face challenges with addressing system
SBA’s risk management, cybersecurity,          issues that arise.
and schedule and cost estimation               Extent to Which the Small Business Administration (SBA) Met Selected IT Management Areas
efforts to leading practices. GAO also         for the Unified Certification Platform Modernization
interviewed SBA officials.                      IT management area                                   Overall assessment
What GAO Recommends                             Risk Management                                      ◔ Minimally met
                                                Cybersecurity                                        ◑ Partially met
GAO is making fourteen
recommendations to SBA, including               Schedule                                             ○ Not met
that it should (1) expeditiously address        Cost                                                 ◔ Minimally met
critical risk management issues, (2)           Source: GAO analysis of SBA data. | GAO-25-106963
expeditiously address critical
cybersecurity issues, and (3) consider         GAO identified critical management gaps:
the probability and impact of accepted         •     SBA did not have a project level risk management strategy, a risk mitigation
risks if deciding to issue a final                   plan, and did not fully identify and document risks.
authorization to operate the system.           •     SBA did not document plans for managing cybersecurity risks or conduct a
SBA concurred with three, partially
                                                     traceability analysis to ensure project security requirements had been met.
concurred with three, and did not
                                                     This increases the likelihood of a successful cyberattack.
concur with eight recommendations.
GAO maintains that the                         Further, the project’s schedule and cost estimates were unreliable. SBA did not
recommendations are warranted.                 create an integrated master schedule; instead, it used a “road map” that did not
                                               meet the characteristics of a reliable schedule. SBA’s cost estimate largely relied
                                               on subject matter expertise instead of supporting data or methodologies.
                                               SBA issued an interim authority to operate for the system in August 2024 while it
View GAO-25-106963. For more information,
                                               continues to implement IT security controls. Under schedule pressure, SBA could
contact Carol C. Harris at (202) 512-4456 or   decide to accept known risks and issue a final authorization to operate with
HarrisCC@gao.gov, or Courtney LaFountain       issues not being fully resolved. If taking such an action, consideration of the
at (202) 512-5463 or LaFountainC@gao.gov.      probability and resulting impact of accepted risks is essential.
                                                                                                   United States Government Accountability Office
Contents


Letter                                                                                     1
               Background                                                                  3
               SBA Unified Certification Platform to Address Shortcomings with
                 Certification Systems; Work is Ongoing Post-Deployment                  12
               SBA Has Not Fully Implemented Selected Leading IT
                 Management Practices and Faces Increased Risks                          17
               Conclusions                                                               34
               Recommendations for Executive Action                                      35
               Agency Comments and Our Evaluation                                        37

Appendix I     Objectives, Scope, and Methodology                                        42



Appendix II    SBA UCP Project Cost Estimate Compared to Leading Practices               46



Appendix III   Comments from the Small Business Administration                           48



Appendix IV    GAO Contacts and Staff Acknowledgments                                    57


Tables
               Table 1: Examples of Small Business Administration (SBA)
                       Contracting Assistance Program Reporting                            6
               Table 2: Unified Certification Platform (UCP) Planned Cost, as of
                       October 2024                                                      15
               Table 3: Implementation Status of the Small Business
                       Administration’s (SBA) Unified Certification Platform
                       Project, as of October 2024                                       16
               Table 4: Analysis of the Small Business Administration’s (SBA)
                       Implementation of Selected Leading Risk Management
                       Practices for the Unified Certification Platform (UCP)
                       Project, as of October 2024                                       19
               Table 5: Extent to Which the Small Business Administration (SBA)
                       Adopted Selected Leading Cybersecurity Practices for the
                       Unified Certification Platform (UCP) Project, as of October
                       2024                                                              24




               Page i                                      GAO-25-106963 SBA IT Modernization
          Table 6: Assessment of Small Business Administration (SBA)
                  Unified Certification Platform (UCP) May 2023 Cost
                  Estimate Compared to Cost Estimating Leading Practices,
                  as of October 2024                                                                31
          Table 7: Assessment of the Unified Certification Platform (UCP)
                  Cost Estimate Compared to Leading Practices, as of
                  October 2024                                                                      46

Figures
          Figure 1: Simplified Overview of the Small Business
                   Administration’s (SBA) Contracting Assistance Program
                   Certification Process                                                             5
          Figure 2: Examples of Intended Functions of the Small Business
                   Administration’s (SBA) Unified Certification Platform
                   (UCP)                                                                            14




           Abbreviations

           BTIC                      Business Technology Investment Council
           CMMI                      Capability Maturity Model Integration
           HUBZone                   Historically Underutilized Business Zone
           NIST                      National Institute of Standards and Technology
           CIO                       Chief Information Officer
           OIG                       Office of Inspector General
           SBA                       Small Business Administration
           UCP                       Unified Certification Platform
           VetCert                   Veteran Small Business Certification Program
           WOSB                      Women-Owned Small Business
           WBS                       work breakdown structure


          This is a work of the U.S. government and is not subject to copyright protection in the
          United States. The published product may be reproduced and distributed in its entirety
          without further permission from GAO. However, because this work may contain
          copyrighted images or other material, permission from the copyright holder may be
          necessary if you wish to reproduce this material separately.




          Page ii                                               GAO-25-106963 SBA IT Modernization
                       Letter




441 G St. N.W.
Washington, DC 20548




                       November 6, 2024

                       The Honorable Nydia Velázquez
                       Ranking Member
                       Committee on Small Business
                       House of Representatives

                       Dear Ms. Velázquez,

                       The Small Business Administration (SBA) administers contracting
                       assistance programs and promotes small business participation in federal
                       contracting through a variety of programs. In fiscal year 2023, the federal
                       government awarded $178.6 billion in federal procurement opportunities
                       to small businesses. Approximately $156.5 billion of those contracting
                       dollars was awarded to small businesses that were disadvantaged,
                       women-owned, service-disabled veteran-owned, or located in historically
                       underutilized business zones.1

                       To certify small businesses for eligibility in its contracting assistance
                       programs, SBA relies on multiple IT systems. We and SBA’s Office of
                       Inspector General (OIG) have previously reported that these systems
                       have shortcomings, including issues with reconciling data between
                       systems and limitations in promised functionality.2

                       To help address these shortcomings, in 2023, SBA initiated the Unified
                       Certification Platform (UCP) modernization project. The UCP project is
                       intended to deploy a new system to allow small businesses to more
                       efficiently apply for and maintain certifications to SBA’s contracting
                       assistance programs.

                       You asked us to review SBA’s UCP project. Our specific objectives were
                       to (1) describe SBA’s plans for the UCP project and the status of its
                       efforts; and (2) determine to what extent the UCP project has adopted


                       1Government-Wide Performance FY2023 Small Business Procurement Scorecard,
                       available at
                       https://www.sba.gov/agency-scorecards/scorecard.html?agency=GW&year=2023.
                       2GAO, Small Business Administration: Recent Changes to the 8(a) Program’s Financial
                       Thresholds Need Evaluation, GAO-22-104512. (Washington, D.C.: Aug 30, 2022); Small
                       Business Administration, Office of Inspector General, Evaluation of Certify.SBA.Gov, 20-
                       17 (Washington, D.C.: Jul. 30, 2020).



                       Page 1                                               GAO-25-106963 SBA IT Modernization
leading IT management practices for risk management, cybersecurity,
and schedule and cost estimation.

To address our first objective, we reviewed and summarized relevant
UCP project information, such as acquisition plans, solicitation
documents, monthly meeting minutes, and schedule and cost
documentation. We also interviewed agency officials to verify SBA’s plans
for its modernization effort and its current status.

To address our second objective, we assessed the UCP project’s
practices for managing risks, cybersecurity, and schedule and cost
estimation against selected leading practices. Specifically,

•   We selected seven leading practices associated with risk
    management in ISACA’s Capability Maturity Model Integration
    (CMMI).3 We then evaluated the UCP project’s documentation, such
    as risk registers and quality assurance plans, and SBA policies
    against the selected practices.
•   We selected five leading practices that represented key elements for
    addressing cybersecurity requirements and needs in an acquisition
    from the National Institute of Standards and Technology’s (NIST)
    guidance on Engineering Trustworthy Secure Systems.4 We then
    evaluated the UCP project’s documentation, such as the UCP
    acquisition plan and performance work statement, against the
    selected NIST guidance.
•   We reviewed documentation supporting SBA’s schedule and cost
    estimates for the UCP project. Specifically, we assessed SBA’s efforts
    to establish a project schedule against leading practices for
    developing a comprehensive, well-constructed, credible, and
    controlled schedule, as identified in GAO’s Schedule Assessment
    Guide.5 In addition, we evaluated documentation supporting the
    project’s cost estimate against the leading practices for developing a



3ISACA, CMMI Model V3.0 (Pittsburgh, PA: Apr. 6, 2023). CMMI Model and ISACA©
[2021] All rights reserved. Used with permission.
4National Institute of Standards and Technology, Engineering Trustworthy Secure
Systems, Special Publication 800-160, Volume 1, Revision 1 (Gaithersburg, Md.: Nov. 16,
2022).
5GAO, Schedule Assessment Guide: Best Practices for Project Schedules, GAO-16-89G
(Washington, D.C.: Dec. 22, 2015).




Page 2                                              GAO-25-106963 SBA IT Modernization
                 comprehensive, accurate, well documented, and credible cost
                 estimate identified in GAO’s Cost Estimating and Assessment Guide.6
             For both objectives, we interviewed cognizant agency officials in SBA’s
             Office of Government Contracting and Business Development, as well as
             SBA’s Office of the Chief Information Officer to obtain their views and
             verify the information provided. Additional details on our objectives,
             scope, and methodology are provided in appendix I.

             We conducted this performance audit from July 2023 to November 2024
             in accordance with generally accepted government auditing standards.
             Those standards require that we plan and perform the audit to obtain
             sufficient, appropriate evidence to provide a reasonable basis for our
             findings and conclusions based on our audit objectives. We believe that
             the evidence obtained provides a reasonable basis for our findings and
             conclusions based on our audit objectives.

             SBA was created in 1953 as an independent agency of the federal
Background   government with a mission to aid small businesses, preserve free and
             competitive enterprise, and maintain and strengthen the overall economy
             of our nation. The agency’s Office of Government Contracting and
             Business Development is responsible for promoting small business
             participation in federal contracting. The office administers several
             contracting assistance programs that, among other things, facilitate
             contract set-asides (i.e. government contracts with competition limited to
             small businesses in general or those that meet specific eligibility
             requirements), including the following programs:

             •   8(a) Business Development assists small businesses owned and
                 controlled by socially and economically disadvantaged individuals and
                 entities. The program provides up to 9 years of developmental
                 support, such as business counseling and mentoring, contracting
                 guidance, and access to capital. The program also sets aside federal
                 contracting opportunities for program participants.
             •   Women-Owned Small Business (WOSB) provides greater access to
                 federal contracting opportunities for women-owned small businesses.
                 Through this program, contracting officers can set aside contracts for
                 eligible WOSBs and economically-disadvantaged women-owned
                 businesses.


             6GAO, Cost Estimating and Assessment Guide: Best Practices for Developing and
             Managing Program Costs, GAO-20-195G (Washington, D.C.: Mar. 12, 2020).




             Page 3                                            GAO-25-106963 SBA IT Modernization
                          •   Historically Underutilized Business Zone (HUBZone) provides
                              small businesses located in economically distressed areas access to
                              federal contracting set-aside opportunities to promote economic
                              development.
                          •   Veteran Small Business Certification Program (VetCert) allows
                              veteran-owned and service-disabled veteran-owned small businesses
                              to compete for federal set-aside contracts.7
SBA’s Certification       According to SBA, the general initial certification process for the 8(a),
Process and Systems for   WOSB, HUBZone and VetCert programs include a pre-application phase
                          where the applicant registers and uploads required documents to an
Contracting Assistance
                          online portal. During this phase, SBA may provide assistance or answers
Programs                  to questions from prospective applicants. Subsequent phases are;

                          •   an application screening step where SBA staff or contractor support
                              staff check submitted applications for completeness before full review;
                          •   a document processing, application evaluation, and fact review step to
                              confirm eligibility and other program requirements;
                          •   a certification decision recommendation by individuals responsible for
                              the primary review; and
                          •   a final certification review/approval.
                          Figure 1 provides an overview of SBA’s contracting assistance program
                          certification process.




                          7The National Defense Authorization Act for Fiscal Year 2021 provided for the transfer to
                          SBA of the veteran-owned and service-disabled veteran owned small business
                          certification process from the Department of Veterans Affairs. Pub. L. No. 116-283, § 862,
                          134 Stat. 3388, 3776-3784. In January 2023, SBA began accepting applications to certify
                          new veteran-owned small businesses through its VetCert program. Existing veteran-
                          owned small businesses that were already certified by the Department of Veterans Affairs
                          as of January 1, 2023, were granted a one-time, one-year extension by SBA. Prior to the
                          2021 act, veteran-owned small businesses would self-certify using the VetCert portal at
                          veterans.certify.sba.gov. The portal allows participants to check their eligibility, apply for
                          certification or re-certify their businesses, access checklists and guides, and search for
                          certified veteran-owned firms.




                          Page 4                                                  GAO-25-106963 SBA IT Modernization
Figure 1: Simplified Overview of the Small Business Administration’s (SBA) Contracting Assistance Program Certification
Process




                                         Note: The certification process for some of the contracting assistance programs differ from the
                                         general approach depicted above. For example, the Women-Owned Small Business program allows
                                         approved third-party certifiers to review applications and make eligibility determinations, subject to
                                         SBA oversight. See, e.g., 13 C.F.R. §§ 127.350-356. The 8(a) program also includes a secondary
                                         review of the certification decision for applicants.


                                         SBA also produces various reports associated with its contracting
                                         assistance programs. Table 1 provides a description of each program’s
                                         reporting.


                                         Page 5                                                       GAO-25-106963 SBA IT Modernization
Table 1: Examples of Small Business Administration (SBA) Contracting Assistance Program Reporting

Program                                       Reporting summary
8(a) Business Development                     Section 408 of the Business Opportunity Development Reform Act of 1988 requires SBA to develop
                                              and implement a process for the systematic collection of data on the 8(a) program.a The act also
                                              requires SBA to submit an annual report to Congress with information on the program’s costs and
                                              benefits, the dollar amount of contracts awarded, and the status of businesses exiting the program,
                                              among other things. In addition to this annual report, SBA reports metrics for this program as part of
                                              its agencywide annual performance report.
Women-Owned Small Business                    SBA reports metrics for this program as part of its agencywide annual performance report.
Historically-Underutilized                    Section 31 of the Small Business Act as amended requires SBA to annually report performance
Business Zone                                 metrics and program data.b In addition, SBA reports metrics for this program as part of its
                                              agencywide annual performance report.
Veteran Small Business                        SBA reports metrics for this program as part of its agencywide annual performance report.
Certification
Source: GAO analysis of SBA documentation. | GAO-25-106963

                                                             Pub. L. No. 100-656, § 408, 102 Stat. 3853, 3877-78 (codified at 15 U.S.C. § 636j(16)).
                                                             a


                                                             15 U.S.C. § 657a(e).
                                                             b




                                                             Each of SBA’s contracting assistance programs are supported by
                                                             different IT systems. These IT systems use different computer languages,
                                                             are located on various platforms, and are hosted in cloud computing
                                                             environments using various technology providers.8 According to SBA, in
                                                             fiscal year 2023, the agency reported spending approximately $10.86
                                                             million to operate and maintain the IT systems environment supporting its
                                                             contracting assistance programs.

Overview of Leading                                          We, ISACA, and NIST have identified leading practices and guidance to
Practices for IT                                             assist in ensuring the effective management of IT modernization
                                                             initiatives. These include the following:
Modernization
                                                             •   Risk management. ISACA’s CMMI provides guidance for improving
                                                                 an organization’s capabilities and performance when developing or
                                                                 acquiring solutions, including hardware and software, and their related
                                                                 components. ISACA’s CMMI Model Version 3.0, published in April
                                                                 2023, includes practices to help organizations manage potential risks
                                                                 and reduce the chance of adverse impacts on meeting objectives,
                                                                 among other areas.


                                                             8According to the National Institute of Standards and Technology (NIST), cloud computing
                                                             is a means for enabling on-demand access to shared pools of configurable computing
                                                             resources (e.g., networks, servers, storage applications, and services) that can be rapidly
                                                             provisioned and released.




                                                             Page 6                                                     GAO-25-106963 SBA IT Modernization
•   Cybersecurity. NIST has issued a suite of information security
    standards and guidelines that, collectively, provide comprehensive
    guidance on managing cybersecurity risk to agencies. For example,
    NIST’s guidance on engineering trustworthy secure systems
    establishes leading practices for agencies to follow in developing new
    systems or updating legacy systems.9 The guidance is intended to
    address security issues from a perspective of stakeholder
    requirements and protection needs and to use established processes
    to ensure that such requirements and needs are addressed with the
    appropriate rigor across the life cycle of the system. By following the
    guidelines, agencies can better ensure that the security requirements
    of the system are defined, among other things.
•   Schedule estimation. GAO’s Schedule Assessment Guide presents
    10 leading practices for scheduling.10 Leading practices within this
    guide show that a well-planned schedule is a fundamental
    management tool that can help government programs use public
    funds effectively by specifying when to perform work in the future and
    measuring program performance against an approved plan. An
    integrated and reliable schedule can show when major events are
    expected as well as the completion dates for all activities leading up to
    them, which can help determine if the program’s parameters are
    realistic and achievable.
•   Cost estimation. GAO’s Cost Estimating and Assessment Guide
    establishes a consistent methodology based on 18 leading practices
    that can be used across the federal government for developing,
    managing, and evaluating program cost estimates for acquisitions and
    development efforts.11 GAO grouped leading practices into the four
    characteristics of a reliable cost estimate—comprehensive, well-
    documented, accurate, and credible. The guidance considers an
    estimate reliable if it substantially or fully meets each of the
    characteristics of a reliable cost estimate.




9National Institute of Standards and Technology, Engineering Trustworthy Secure
Systems, Special Publication 800-160, Volume 1, Revision 1 (Gaithersburg, Md.: Nov. 16,
2022).
10GAO-16-89G.

11GAO-20-195G.




Page 7                                              GAO-25-106963 SBA IT Modernization
GAO and OIG Reports
Found Longstanding
Challenges with SBA’s
Prior IT Systems
Modernizations,
Reporting, and IT
Management

Prior IT System                  From 2011 through 2019, SBA initiated several projects to modernize the
Modernizations for Contracting   IT systems used for its contracting assistance programs but has faced
Assistance Programs              longstanding challenges.

                                 •   OneTrack. In 2011, SBA began a $1.9 million contract to develop an
                                     IT system, OneTrack, which was intended to improve, streamline,
                                     automate, and unify business processes for the 8(a) and HUBZone
                                     programs. The intent was to create one portal for businesses to use
                                     for the programs, and to provide SBA staff with a shared database of
                                     program data to improve productivity and enhance monitoring and
                                     reporting capabilities. However, the SBA OIG found in 2014 that the
                                     system did not achieve the intended capabilities because the
                                     development process did not complete the necessary market
                                     research for the project, did not use modular contracting principles,
                                     did not maintain contract documentation, and did not monitor or
                                     mitigate project risks.12
                                     In 2015 we also reported that SBA experienced problems
                                     implementing the OneTrack system.13 SBA ultimately decided not to
                                     deploy the system and instead began development of another
                                     replacement IT system.
                                 •   Certify.sba.gov. In 2015, SBA approved a contract for
                                     Certify.sba.gov, which—like OneTrack—was intended to improve the
                                     8(a), HUBZone, and WOSB programs by creating a single gateway
                                     for participating businesses. Certify.sba.gov would also increase
                                     efficiency for processing and reviewing applications and enable SBA
                                 12Small Business Administration, Office of Inspector General, The SBA Did Not Follow
                                 Federal Regulations and Guidance in the Acquisition of the OneTrack System, 14-10
                                 (Washington, D.C.: Feb. 12, 2014).
                                 13GAO, Small Business Administration: Leadership Attention Needed to Overcome
                                 Management Challenges, GAO-15-347 (Washington, D.C.: Sept. 22, 2015). The report
                                 made eight recommendations designed, among other things, to improve SBA’s oversight
                                 of IT investments. SBA implemented all of our recommendations.




                                 Page 8                                              GAO-25-106963 SBA IT Modernization
                                   to report on and analyze the agency’s impact on small businesses.
                                   However, from 2015 through 2019, the SBA OIG found that the
                                   system’s technical architecture would not meet the needs of 8(a) and
                                   HUBZone program processes.14 In addition, the system was missing
                                   critical features such as the ability to prescreen applications and key
                                   analytical tools to improve review capabilities. These issues created
                                   delays, backlogs, and reliance on manual workarounds.
                                   SBA ultimately stopped development of Certify.sba.gov in 2019 when
                                   it was determined that the platform was unsustainable in the long-term
                                   due to maintenance and updates required for the open-source
                                   platform, and security vulnerabilities were difficult to address. The
                                   agency reported to the Office of Management and Budget that the
                                   cost for the Certify.sba.gov system between 2015 and 2019 exceeded
                                   $30 million.
                               •   Beta.Certify.sba.gov. In 2019, SBA approved plans to redesign
                                   Certify.sba.gov on a new platform, called beta.Certify.sba.gov, at a
                                   cost of $3.5 million. Like the original Certify.sba.gov platform, the
                                   initial intent of beta.Certify.sba.gov was to unify 8(a), WOSB, and
                                   HUBZone under one system and to facilitate improved user
                                   experience for applicants as well as to enhance electronic reviews
                                   and tracking by SBA staff. Additionally, the platform was intended as a
                                   replacement for other obsolete tools, such as business search tools,
                                   among other things. According to SBA, the scope of the effort was
                                   reduced to provide a platform solely for the WOSB program, and 8(a)
                                   and HUBZone remained in their legacy systems. Beta.Certify.sba.gov
                                   was launched in 2020 as the WOSB system of record. Subsequently,
                                   in a September 2022 report, the SBA OIG found that
                                   beta.Certify.sba.gov did not contain accurate WOSB information and
                                   was undergoing fixes as program officials discovered issues.15
Challenges with Contract       SBA has also faced challenges in meeting the contracting program
Assistance Program Reporting   reporting requirements previously discussed. These challenges were due,

                               14Small Business Administration, Office of Inspector General, Evaluation of
                               Certify.SBA.Gov, 20-17 (Washington, D.C.: Jul. 30, 2020).
                               15Small Business Administration, Office of Inspector General, SBA’s Implementation of the
                               Women-Owned Small Business Certification Program, 22-20 (Washington, D.C.: Sept. 29,
                               2022). In the September 2022 report the OIG recommended that SBA mitigate or remedy
                               the beta.Certify.sba.gov issues affecting data accuracy. SBA disagreed with the
                               recommendation, stating that SBA already had procedures and guidance in place to
                               identify and address system issues. The OIG noted that those procedures and guidance
                               did not catch the data issues uncovered in the OIG report and that SBA did not provide
                               any information that improvements had been made to address the issues the OIG
                               identified.




                               Page 9                                               GAO-25-106963 SBA IT Modernization
                     in part, to shortcomings in its IT systems. Specifically, we reported in
                     2022 that SBA identified a number of challenges that led to a delay in
                     required 8(a) program reporting, including

                     •   manual data collection and aggregation processes, such as data on
                         firm owners saved in individual spreadsheets maintained by different
                         analysts;
                     •   IT issues, such as reconciling data between prior IT systems and new
                         systems; and
                     •   limited functionality of the current Certify.sba.gov system, such as the
                         inability to monitoring the business development of 8(a) participants.16
                     We recommended that, among other things, SBA assess the process to
                     systematically collect data and develop a report on the 8(a) program in
                     light of delay-causing challenges. We recommended that the agency
                     identify potential operational efficiencies and develop a plan to assess
                     report delays, such as revising procedures or developing time frames as
                     needed. SBA agreed with this recommendation and has taken steps to
                     address it. In March 2024, SBA stated that the agency had assessed the
                     8(a) program reporting process to develop revisions that reduce or
                     eliminate reporting delays. As of July 2024, SBA had published the 2023
                     fiscal year 8(a) program report, however, the agency has not yet
                     published program reports for fiscal years 2019-2022. We will continue to
                     monitor SBA’s progress in implementing this recommendation.

Challenges with IT   We and the SBA OIG have previously reported on SBA’s IT management
Management           issues. These included, among other things, a governance board that did
                     not meet to oversee IT investments, not reporting investment
                     performance against established baselines, and not taking corrective
                     actions for underperforming investments.

                     •   In 2015, we reported that, although SBA had taken steps to
                         implement aspects of several key IT management initiatives for
                         managing its IT acquisitions and operations, the agency had not fully
                         completed all of them.17 For example, the agency had not developed
                         a policy for conducting regular operational analyses of all of its IT
                         investments. We made eight recommendations to SBA, including to
                         improve its IT investment oversight by ensuring that investments are
                         continuing to meet business and customer needs and agency

                     16GAO-22-104512.

                     17GAO-15-347.




                     Page 10                                      GAO-25-106963 SBA IT Modernization
    strategic goals. SBA took action to implement all eight of our
    recommendations.
•   In 2017 the OIG found that although SBA had made significant
    progress improving its oversight of IT investments, the agency had not
    fully implemented OMB guidance. For example, SBA had not
    conducted regular reviews of its IT investments and there were IT
    control issues with SBA’s handling of several projects, including
    Certify.sba.gov.18 The OIG made six recommendations to SBA,
    including that SBA ensure that its Business Technology Investment
    Council (BTIC) sessions review and track all IT investment
    baselines.19 The OIG also recommended that the SBA Chief
    Information Officer (CIO) measure and report on IT project
    performance against baselines and use updated system development
    policies that address cloud and agile development, among others.
    SBA agreed with the recommendations and took actions to address
    them. For example, in November 2017, SBA’s OIG reported that the
    CIO incorporated all performance baselines for IT investments into
    BTIC session agendas and ensured that any changes to those
    performance baselines followed an agency established review
    process.
•   In 2024, the SBA OIG reported that SBA had significant IT investment
    internal control issues as a result of not having an effective IT
    governance framework in place.20 For example, SBA’s BTIC did not
    meet regularly to review and evaluate IT investments through their
    business cases and baselines which consider cost, performance
    goals, scope, and schedule. In addition, those investments did not
    have an independent cost and performance assessment with
    approvals from the architecture review board and the BTIC.21 Further,
    the OIG also found that business cases were not completed for the
    investments they sampled. The OIG recommended that SBA ensure
18Small Business Administration, Office of Inspector General, Review of SBA’s
Implementation of the Federal Information Technology Acquisition Reform Act, 18-06
(Washington, D.C.: Nov. 28, 2017).
19The Business Technology Investment Council (BTIC) is the agency’s principal
governance body that oversees the selection, control, and evaluation of SBA’s major IT
investments.
20Small Business Administration, Office of Inspector General, SBA’s IT Investment
Governance Framework, 24-10 (Washington, D.C.: Mar. 29, 2024).
21SBA’s architecture review board supports the process of researching, investing,
architecting, and implementing IT capabilities and services. The board establishes
adequate governance to ensure SBA investments conform to an overarching SBA IT
system design.




Page 11                                              GAO-25-106963 SBA IT Modernization
                             that (1) it reviews new investments to confirm compatibility with
                             existing systems, (2) the BTIC approves new investments prior to
                             purchase, and (3) program offices create business cases prior to
                             approval of the investment, as required by SBA policies. SBA agreed
                             with these recommendations.
                             The OIG also found that SBA did not effectively monitor major IT
                             investments as the projects were being developed to ensure that they
                             continued to meet mission needs at the expected levels of cost and
                             risk and take corrective action if needed. SBA policy requires earned
                             value principles to be used to plan and manage the development
                             activities for major IT investments.22 According to that policy earned
                             value methods should at a minimum, track schedules, incurred costs,
                             and estimates to complete the project. The OIG recommended that
                             the agency update procedures to provide specific guidance on how to
                             use earned value principles to measure investment progress against
                             the approved performance measurement baseline23 and the original
                             performance measurement baseline24 for all major investments. SBA
                             partially agreed with the recommendation and noted that agency
                             investment managers plan to use earned business value principles to
                             measure investment progress and the agency plans to update its
                             procedures.
                         SBA initiated the UCP modernization project to help address
SBA Unified              shortcomings with the systems supporting the certification of small
Certification Platform   businesses for its contracting assistance programs. According to SBA
                         officials and a 2022 third-party evaluation by the MITRE Corporation,
to Address               these systems have shortcomings that have led to inefficiencies.25 For
Shortcomings with        example, MITRE’s evaluation noted that SBA’s certification systems do
                         not interface with each other and the manual process of extracting firm
Certification Systems;   data from multiple databases and storing it in spreadsheets for analysis is
Work is Ongoing          time-consuming, inefficient, and inconsistent.
Post-Deployment
                         22Earned Value Management is a technique to measure program and project
                         performance, allowing PMs and investment managers to reduce program or project risk.
                         23A documented baseline approved by the BTIC, along with any approved changes to
                         cost, schedule, or scope from the original baseline.
                         24The original baseline is the baseline approved by the BTIC prior to the addition of the
                         investment to SBA’s IT portfolio and submission within the official budget. This baseline
                         includes a cost, schedule, and scope baseline.
                         25The MITRE Corporation is a not-for-profit organization chartered to work in the public
                         interest with expertise in system engineering, IT, and enterprise modernization.




                         Page 12                                                GAO-25-106963 SBA IT Modernization
Further, a business applying to multiple programs must have a login for
each program and repeatedly upload the same documents to each
system. According to SBA officials, an estimated 40 percent of certified
small businesses are eligible for multiple certifications; however, many
forego additional certifications because the different application
processes are administratively burdensome and complicated.
Additionally, SBA staff sometimes rely on manual processes and
spreadsheets for accessing data from these systems. As a result, it can
be difficult for SBA staff to leverage data and documents in or across the
different systems for analysis.

According to SBA, the UCP project is intended to develop an IT system to
streamline and enhance the administration of the 8(a), HUBZone,
VetCert, and WOSB programs. With UCP, SBA plans to improve the
certification and recertification process for firms by providing a single
software solution for all of SBA’s contracting assistance programs. The
UCP project was approved by SBA’s BTIC in March 2024. SBA’s Office of
Government Contracting and Business Development, in conjunction with
the Office of the CIO, is managing the project. Figure 2 describes the
functions SBA plans to provide with the UCP system.




Page 13                                     GAO-25-106963 SBA IT Modernization
Figure 2: Examples of Intended Functions of the Small Business Administration’s (SBA) Unified Certification Platform (UCP)




                                         Page 14                                          GAO-25-106963 SBA IT Modernization
                                                              To develop the UCP system, SBA issued two contracts that, in total,
                                                              include a 12-month base period beginning in September 2023 followed by
                                                              two 3-month option periods beginning in September 2024 and December
                                                              2024, respectively, and a final 12 -month option period beginning in
                                                              March 2025.26

                                                              According to SBA, the UCP system is expected to cost $19.14 million for
                                                              the entire 30-month period. This cost figure includes $13.5 million for the
                                                              contract base period, and $5.64 million for the option periods. However,
                                                              SBA did not provide the total lifecycle costs of the UCP system. This
                                                              issue is discussed later in the report. As of October 2024, SBA stated that
                                                              it had spent approximately $14.2 million on UCP. See table 2 for an
                                                              overview of the planned costs for UCP.

Table 2: Unified Certification Platform (UCP) Planned Cost, as of October 2024

Contract period                                                                        Dates                                           Cost (in millions)
Base period (12 months)                                                                September 2023 – September 2024                             $13.50
Additional development and operations and maintenance                                  September 2024 – December 2024                               $1.09
contract option (3 months)
Additional development and operations and maintenance                                  December 2024 – March 2025                                   $1.09
contract option (3 months)
Operation and maintenance contract option (12 months)                                  March 2025 – March 2026                                      $3.46
Total                                                                                                                                              $19.14
Source: GAO analysis of Small Business Administration documentation. | GAO-25-106963



                                                              SBA is implementing UCP using an Agile incremental development
                                                              approach with two-week development cycles that are intended to result in




                                                              26The development, implementation, and operations and maintenance for UCP were split
                                                              into two concurrent contracts, UCP I and UCP II. The UCP I contract is for the
                                                              development, implementation, and post-deployment operations and maintenance of
                                                              technology solutions for the HUBZone, WOSB and the VetCert programs, including
                                                              certification decisions, certification servicing, oversight, and re-certification functions,
                                                              associated reporting, websites, and training. The second contract for UCP II is for the
                                                              development, implementation, and post-deployment operations and maintenance of
                                                              technology solutions for the 8(a) field functions, including certification servicing and
                                                              oversight functions, associated reporting, websites, and training, among other things. The
                                                              8(a) field functions are SBA’s 68 field offices who oversee and engage with 8A firms.




                                                              Page 15                                                GAO-25-106963 SBA IT Modernization
                                          deployable working software.27 The program manager holds planning
                                          sessions with stakeholders prior to the start of the development of the
                                          next system release or sprint, as well as review sessions at the end of
                                          each release or sprint to evaluate the work produced.

                                          SBA faced a delay in deploying the UCP system. Based on SBA’s July
                                          2024 product road map, the agency initially planned to deploy the UCP
                                          system in September 2024.28 According to SBA officials, the agency
                                          delayed the deployment of UCP to address system issues identified
                                          during testing.

                                          SBA subsequently deployed the UCP system on October 18, 2024, but
                                          work remains to develop additional, more complex functionality.29 For
                                          example, although small businesses starting new certification applications
                                          can use the UCP system, those businesses that are managing existing
                                          certifications still need to use other systems. As of October 2024, SBA
                                          was in the process of performing data migration from prior systems, which
                                          is a necessary step to allow the new system to manage existing
                                          certifications. SBA was also working to develop additional functionality to
                                          enable small businesses to manage existing certifications using the new
                                          UCP system. Lastly, SBA was still implementing system security controls,
                                          as discussed later in this report. See table 3 for a description of the UCP
                                          project activities and their statuses.

Table 3: Implementation Status of the Small Business Administration’s (SBA) Unified Certification Platform Project, as of
October 2024

                                                                                              Original estimated
Activity                                                                    Start date        completion date           Status
Initiate contract                                                           9/2023            9/2023                    Completed
Develop user, business, and system requirements                             11/2023           12/2023                   Completed
Create a product road mapa for the system development                       12/2023           1/2024                    Completed


                                          27Agile software development approach emphasizes early and continuous software
                                          delivery, with development broken into iterations called sprints. Each set of sprints is
                                          compiled into deployable working software, referred to as a release. Agile uses
                                          collaborative teams, and measures progress with working software. GAO, GAO Agile
                                          Assessment Guide: Best Practices for Adoption and Implementation, GAO-24-105506
                                          (Washington, D.C.: Dec. 15, 2023).
                                          28According to GAO’s Agile Assessment Guide, a product road map is a management
                                          plan where capabilities or features for development are laid out in a timeline and planned
                                          for future iterations. GAO-24-105506.
                                          29We did not evaluate the performance of the UCP system.




                                          Page 16                                                GAO-25-106963 SBA IT Modernization
                                                                                                                          Original estimated
Activity                                                                                            Start date            completion date               Status
System Development                                                                                  3/2024                8/2024                        In progress
Data migration                                                                                      4/2024                3/2025                        In progressb
System deployment                                                                                   9/2024                9/2024                        Delayed,
                                                                                                                                                        then
                                                                                                                                                        completedc
Additional development, operations, and maintenance (3-month contract                               9/2024                12/2024                       In progress
option)
Additional development, operations, and maintenance (additional 3-month                             12/2024               3/2025                        Not started
contract option)
Operations and maintenance (12 months)                                                              3/2025                4/2026                        Not started
Source: GAO analysis of SBA documentation. | GAO-25-106963
                                                             a
                                                              According to GAO’s Agile Assessment Guide, a product road map is a management plan where
                                                             capabilities or features for development are laid out in a timeline and planned for future iterations.
                                                             GAO, GAO Agile Assessment Guide: Best Practices for Adoption and Implementation,
                                                             GAO-24-105506 (Washington, D.C.: Dec. 15, 2023).
                                                             b
                                                              SBA officials reported that data essential to the system’s functionality will be migrated first and that
                                                             data migration is expected to continue after deployment.
                                                             c
                                                               SBA deployed the UCP system on October 18, 2024, but additional work remains to develop
                                                             additional functionality, secure the system, and migrate data.




                                                             SBA has not fully implemented leading IT management practices in the
SBA Has Not Fully                                            planning and implementation of the UCP modernization project.
Implemented                                                  Specifically, SBA partially implemented leading practices related to
                                                             identifying and managing risks, and cybersecurity. In addition, SBA did
Selected Leading IT                                          not develop an integrated master schedule for the project, and the
Management                                                   agency’s cost estimate for UCP was unreliable.
Practices and Faces                                          As mentioned previously, SBA deployed the UCP system, but work
Increased Risks                                              remains to develop additional, more complex functionality, secure the
                                                             system, and migrate data. Critical management gaps, including a lack of
                                                             project-level risk management strategy, risk mitigation plan, and
                                                             cybersecurity risk management plan increase the risk of additional delays.
                                                             As SBA completes remaining work, it will increasingly be more difficult to
                                                             quickly or effectively deal with issues that arise.

SBA Did Not Fully                                            According to the CMMI model, an effective risk management process
Implement Selected                                           identifies potential problems before they occur, so that risk-handling
                                                             activities may be planned and invoked, as needed, across the life of the
Leading Practices for
Identifying and Managing
Risks


                                                             Page 17                                                        GAO-25-106963 SBA IT Modernization
project to mitigate adverse impacts on achieving objectives.30 In addition,
the model also indicates that risk identification should consider topics
such as work tasks, objectives or requirements, technology, staffing,
funding, performance, and regulatory constraints, among other things.

Specifically, effective risk management practices at both the
organizational and project levels include seven selected leading
practices.

1. Determine risk sources and categories such as work activities,
   resources, regulations and laws, and management or technical
   uncertainties).
2. Define parameters to analyze and categorize risks such as the
   severity of risk, likelihood of occurrence, and impact or consequences.
3. Establish and maintain a risk management strategy. That includes
   potential mitigation techniques and defining when a risk becomes
   unacceptable to trigger the execution of a mitigation plan. It also
   includes consideration of the costs and benefits of implementing risk
   mitigation plans for key risks.
4. Identify and document risks throughout all phases of the development
   lifecycle, for example, a document that identifies and records risks,
   including details about context, conditions, and consequences.
5. Evaluate and categorize each identified risk using defined risk
   categories and parameters and determine its relative priority.
6. Develop a risk mitigation plan in accordance with the risk
   management strategy. That includes a determination of the thresholds
   that define when a risk becomes unacceptable and triggers the
   execution of a risk mitigation plan. It also includes the costs and
   benefits of implementing the risk mitigation plan for key risks.
7. Monitor the status of each risk periodically and implement the risk
   mitigation plan as appropriate, to include resource commitments and
   the schedules for each risk-handling activity.
SBA partially met five and did not meet two of seven selected leading
practices for risk management. Table 4 lists these practices and provides
our assessment of the UCP project’s implementation of the practices, as
of October 2024.


30ISACA, Capability Maturity Model Integration, Version 3.0 (Schaumburg, IL: April 2023).
CMMI Model and ISACA© [2021] All rights reserved. Used with permission.




Page 18                                              GAO-25-106963 SBA IT Modernization
Table 4: Analysis of the Small Business Administration’s (SBA) Implementation of Selected Leading Risk Management
Practices for the Unified Certification Platform (UCP) Project, as of October 2024

Leading practice                Assessment         Description of assessment
Determine risk sources and           ◐             SBA’s enterprise risk management framework, which describes SBA’s high-
categories                                         level approach to risk across the agency, includes information on the different
                                                   risk categories and descriptions, for use in risk management at various levels.
                                                   The UCP business requirements document, which lays out the goals and
                                                   requirements for the UCP project, includes a section that identifies various
                                                   categories of risks along with short descriptions.
                                                   As part of the risk determination process, SBA’s IT program manager meets
                                                   weekly with developers, SBA stakeholders, and SBA management.
                                                   Additionally, project leadership meets monthly to discuss risks to project
                                                   objectives, among other things like resources, backlog, and quality assurance
                                                   metrics.
                                                   SBA identifies and tracks risks to the UCP development process using a risk
                                                   register. The UCP risk register includes columns that describe and categorize
                                                   risks. As of February 2024, SBA identified and categorized eight risks, such
                                                   as potential communication issues between product teams or managers,
                                                   contractor staff access to technology tools, delay in policy decisions, and the
                                                   possibility of government-wide shutdown, among other things.
                                                   However, the risk register does not include a column for risk sources and
                                                   does not explicitly state risk sources in the other columns.
Define parameters to                 ◐             As described above, SBA’s enterprise risk management framework includes
analyze and categorize                             categories and descriptions for use in categorizing risks.
risks                                              Additionally, the framework includes descriptors and definitions for assigning
                                                   a likelihood rating and impact rating to a risk based on the likelihood of
                                                   occurrence and potential severity of impact. The framework also includes
                                                   instructions for calculating an overall risk rating based on the likelihood and
                                                   impact scores.
                                                   However, the UCP risk register does not define or describe the parameters to
                                                   categorize or analyze risks, nor does the document include instructions for
                                                   how to identify, analyze, and add risks. The IT Program Manager said that
                                                   the process to add risks to the UCP risk register does not have defined
                                                   parameters.
Establish and maintain risk          ○             SBA does not have a project level risk management strategy for UCP.
management strategy
Identify and document risks          ◐             Risks are identified at the various meetings attended by the IT program
throughout development                             manager and are documented in the UCP risk register, as described above.
lifecycle                                          Additionally, the UCP contracts require the contractor to create monthly
                                                   status reports that include discussion of risks, among other things such as
                                                   project progress and mitigation actions.
                                                   However, the identified risks do not include risks associated with critical
                                                   phases of development, such as system deployment.




                                         Page 19                                             GAO-25-106963 SBA IT Modernization
Leading practice                                Assessment             Description of assessment
Evaluate, categorize, and                              ◐               SBA evaluated and categorized risks at the various meetings attended by the
prioritize risks using defined                                         IT program manager and documented in the UCP risk register. The risk
risk categories and                                                    register also provides the capability to prioritize risks using a series of
parameters                                                             columns that assign likelihood, impact, and total scores for the potential
                                                                       severity of each risk. For example, the risk with the highest total score is
                                                                       delay in policy decisions validated by management, while two other technical
                                                                       risks related to IT infrastructure used in development have the highest
                                                                       individual assigned likelihood and impact scores out of all the identified risks.
                                                                       However, risks were not evaluated, categorized, or prioritized using defined
                                                                       categories or parameters, and officials confirmed there are no procedures or
                                                                       guidance for the process in the context of UCP.
Develop a risk mitigation                              ○               SBA does not have a risk mitigation plan for UCP. Other SBA guidance, such
plan in accordance with risk                                           as a standard operating procedure on IT performance management, notes
management strategy                                                    the importance of having a project risk strategy or mitigation plan in addition
                                                                       to the agencywide risk management strategy.
Monitor risks and                                      ◐               SBA monitors risks through the various meetings attended by the IT program
implement the risk                                                     manager and documents the risks, status, and mitigation actions in the UCP
mitigation plan as                                                     risk register. The risk register has a section for noting mitigation actions
appropriate                                                            connected to each risk, but the information in that section is a mix of
                                                                       mitigation steps already taken, mitigation steps being taken, and mitigation
                                                                       steps to potentially take. For example, the risk register entry for the risk of
                                                                       delay in policy decisions validated by management notes that the concern
                                                                       has been elevated to management and an alternative development approach
                                                                       devised.
                                                                       However, each entry in the mitigation column of the risk register is only one
                                                                       sentence long, and acts as a record of mitigation actions. The mitigations are
                                                                       not connected to any risk mitigation plan or risk strategy. For example, the
                                                                       risk register does not note when the alternative development approach
                                                                       should be implemented, what it entails, or how it relates to other activities or
                                                                       stakeholders.

● Fully met: SBA provided evidence that addressed the entire practice.
◐ Partially met: SBA provided evidence that addressed one or more of the practice activities, but not all the activities.
○ Not met: SBA did not provide evidence that addressed the practice.
Source: GAO analysis of SBA documentation. | GAO-25-106963



                                                             The weaknesses in SBA’s implementation of risk management practices
                                                             are due, in part to a lack of policies and procedures requiring their use.
                                                             According to SBA’s IT program manager, there are no SBA policies and
                                                             procedures requiring the use of specific risk management practices on
                                                             the UCP project. Although SBA has an enterprise-wide risk management
                                                             strategy, the detailed procedures it lays out are applied at the agency
                                                             level.

                                                             Further, the manager noted that these practices have not been fully
                                                             implemented at the project level because they consider the UCP risk
                                                             register to be sufficient for the project’s needs. According to the manager,
                                                             developing additional documents such as a project-level risk



                                                             Page 20                                              GAO-25-106963 SBA IT Modernization
management strategy and project-level risk mitigation plan has been a
lower priority compared to other UCP development tasks. Until SBA
establishes and implements policies and procedures requiring the use of
leading risk management practices on its IT modernization projects, the
agency will be limited in its ability to identify potential problems on its
projects before they occur and mitigate adverse impacts on achieving
objectives.

As previously discussed, SBA originally anticipated deploying the UCP
system in September 2024. In June 2024, SBA announced a pause,
effective August 1, 2024, in accepting new applications for certification.
The agency stated that it would not be accepting new applications until
the new system was deployed. In our draft report provided to SBA for
comment, we expressed concerns regarding the agency’s pause in
accepting new applications. We noted that SBA triggered questions about
risks and available mitigation strategies if full deployment did not occur in
September or if there were system performance issues after deployment.
These questions included:

•   If deployment of the certification system was delayed or there are
    performance issues after deployment, how long does SBA wait until
    lifting the pause on accepting certification applications?
•   If the pause is lifted due to a delayed deployment or there are
    performance issues after deployment, can SBA temporarily return to
    its processes that were in place before August 1, 2024?
This risk of a deployment delay was eventually realized, as SBA delayed
UCP deployment to address system issues identified during testing.
Although SBA subsequently deployed the system in October 2024 and
lifted the pause in accepting new applications, risks remain with SBA’s
efforts to develop additional, more complex functionality, secure the
system, and migrate data.

As mentioned previously, SBA did not provide risk documentation that
addressed risks associated with the deployment of the UCP. The most
recent version of the UCP risk register—SBA’s primary risk assessment
and documentation tool—provided to us in February 2024 included eight
risks associated with various human and technical risks.31 These risks
included coordination issues (disconnection between product managers

31We provided SBA with the opportunity to produce a more recent risk register and other
documentation of the meetings where risks are discussed and documented; however, the
agency has not yet provided us with any such documents.




Page 21                                             GAO-25-106963 SBA IT Modernization
or among product team roles), agency policy issues, developer staff
access to digital infrastructure, delays from use of new enterprise tools or
services, government shutdown risk, and dependency on legacy
technology.

Further, while the UCP risk register included a column for mitigation
actions, it did not include the type of detail found in a risk mitigation plan.
Specifically, none of the described mitigation actions explained the
responsible parties, a breakdown of individual tasks required for the
mitigation, resources required for a mitigation, or a timeline for when a
mitigation can be considered sufficiently implemented. For example, one
mitigation entry in its totality was “elevated concern to leadership, devised
alternate development strategy.” The entry did not describe what level of
leadership the risk was elevated to or by whom, what the alternate
development strategy entailed, or what would trigger the alternate
strategy.

We have previously reported that federal IT investments too frequently fail
to deliver intended capabilities, due in part to lack of effective
management in project planning, oversight, and governance.32 In
addition, we have previously reported that planning for testing, conducting
testing, and resolving software issues discovered during testing is key to
avoiding risks of system problems in general.33

Without a project level risk management plan or risk mitigation plan, SBA
is at risk of not being able to quickly or effectively deal with issues that
arise that could affect the ability of applicants to submit certification
applications. Further, none of SBA’s identified risks were related to
common software testing or deployment issues (e.g., technical failures,
data integrity or availability issues, integration or compatibility issues),
including the potential for delays which—as previously mentioned—SBA
experienced. Lastly, SBA did not develop mitigation strategies to account
for possible delays in deployment or system performance issues.



32GAO, High Risk Series: Efforts Made to Achieve Progress Need to Be Maintained and
Expanded to Fully Address All Areas, GAO-23-106203 (Washington, D.C.: Apr. 20, 2023).
We designated the management of IT acquisitions and operations to be a high risk area
across the federal government in 2015, a designation that remains.
33GAO, Electronic Health Records: VA Has Made Progress in Preparing for New System,
but Subsequent Test Findings Will Need to Be Addressed, GAO-21-224 (Washington,
D.C.: Feb. 11, 2021).




Page 22                                           GAO-25-106963 SBA IT Modernization
                        SBA also needs to obtain a final authorization to operate for the system
                        and consider the risks of the system to agency operations.34 SBA issued
                        an interim authority to operate for the UCP system on August 28, 2024,
                        while it continues to implement system security controls. Under schedule
                        pressure, SBA could decide to accept known risks and issue a final
                        authorization to operate with issues not being fully resolved. If taking such
                        an action, consideration of the probability and resulting impact of
                        accepted deployment risks is essential. Without doing so, SBA will have
                        difficulty assessing the potential consequences on the agency’s ability to
                        provide certification services. Later in this report, we discuss additional
                        cybersecurity and schedule risks facing SBA.

SBA Did Not Fully       NIST guidance on engineering trustworthy secure systems establishes
Implement Selected      leading practices for agencies to follow in developing new systems or
                        updating legacy systems.35 The guidance is intended to address security
Leading Cybersecurity
                        issues from a perspective of stakeholder requirements and protection
Practices               needs and to use established processes to ensure that such
                        requirements and needs are addressed with the appropriate rigor across
                        the life cycle of the system.

                        The NIST guidelines include the following selected cybersecurity leading
                        practices: (1) define security aspects for conducting the acquisition; (2)
                        include security requirements as part of system requirements; (3) select
                        one or more suppliers that meet the security criteria; (4) develop an
                        agreement that includes security requirements that will be supplied; and
                        (5) identify, acquire, and maintain skilled systems and cybersecurity
                        personnel to staff ongoing projects.

                        For the five selected leading cybersecurity practices, SBA fully met two,
                        partially met two, and did not meet one. Table 5 provides a summary of
                        the selected leading practices and an assessment of the extent to which
                        SBA adopted them, as of October 2024.




                        34NIST defines authorization to operate as the official management decision given by a
                        senior Federal official or officials to authorize operation of an information system and to
                        explicitly accept the risk to agency operations (including mission, functions, image, or
                        reputation), agency assets, individuals, other organizations, and the nation based on the
                        implementation of an agreed-upon set of security and privacy controls.
                        35National Institute of Standards and Technology, Engineering Trustworthy Secure
                        Systems, Special Publication 800-160, Volume 1, Revision 1 (Gaithersburg, Md.: Nov. 16,
                        2022).




                        Page 23                                                GAO-25-106963 SBA IT Modernization
Table 5: Extent to Which the Small Business Administration (SBA) Adopted Selected Leading Cybersecurity Practices for the
Unified Certification Platform (UCP) Project, as of October 2024

Leading practice and
corresponding activities                 Assessment      Description of assessment
Define security aspects for                  ◐           SBA’s system acquisition plan includes general information on
conducting the acquisition.                              acquisition needs and a list of evaluation criteria, including subfactors
•   The acquisition strategy should                      like the technical solution and resource plan. Further, SBA’s UCP
    define security aspects, such as                     contract solicitation documentation requires that the contractor offer
    how security risks will be                           include a detailed description of how the system solution will adhere to
    mitigated, the schedule of                           SBA’s cybersecurity requirements for IT acquisitions.
    security-relevant milestones,                        These cybersecurity requirements detail the security-relevant criteria
    how assets will be protected,                        that the contractors must comply with, such as risk mitigation, security
    and the security-relevant criteria                   milestones, and asset protection. Additionally, the cybersecurity
    for selecting suppliers.                             requirements detail key areas that must be included in the contractor’s
                                                         technical proposal.
                                                         However, the acquisition plan does not include key details on how
                                                         SBA plans to manage security risks, security milestones, and asset
                                                         protection at a project level. The plan also does not include specifics
                                                         on how the contractors will be rated against the security criteria. In
                                                         June 2024, SBA officials noted that the ongoing cybersecurity risks are
                                                         managed by the Office of the Chief Information Security Officer at the
                                                         agency level, however, SBA has not provided any documentation
                                                         describing how the security risks are managed at the project level.
Include security requirements as             ◐           SBA’s performance work statement, included in the solicitation orders
part of system requirements.                             for the UCP contracts, states that the contractor shall comply with all
•    The security requirements                           aspects of SBA’s cybersecurity requirements provided in the
     should be integrated with and                       solicitation package. Further, the UCP systems requirements
     provided as part of the                             document includes the system security requirements for the system.
     stakeholder requirements or                         However, SBA did not document the traceability between the security
     system requirements.                                requirements and how the proposed IT system solution is expected to
                                                         satisfy the requirements.
•    A traceability analysis should be
     documented to ensure that all
     security requirements are
     reflected in the design of the IT
     system.
Select one or more suppliers that            ○           As mentioned before, SBA did not specify how suppliers will be rated
meet the security criteria.                              against the security criteria. In addition, the agency has not provided
•   Subject matters experts should                       documentation demonstrating involvement from security-related
    be involved in the selection                         subject matter experts in the contractor selection process.
    process.




                                         Page 24                                            GAO-25-106963 SBA IT Modernization
Leading practice and
corresponding activities                                   Assessment        Description of assessment
Develop an agreement that includes                                 ●         SBA’s cybersecurity requirements for IT acquisitions detail key areas
security requirements that will be                                           that must be included in contractor’s technical proposals. These areas
supplied.                                                                    are:
•   The agreement with the supplier                                          Response to cybersecurity incidents
    should satisfy the security                                              Availability of service
    requirements, including the
    cybersecurity that will be                                               Data retention
    supplied.                                                                Encryption of data at rest
                                                                             Telecommunication service redundancy
                                                                             Logical and physical data access limited to continental United States.
                                                                             According to SBA, UCP systems requirements document is intended
                                                                             to be the official documentation of service requirements that the
                                                                             contractor has agreed to provide for the project. Among other things,
                                                                             the requirements document lists the services that will be provided by
                                                                             the contractor for system security and data privacy.


Identify, acquire, and maintain                                    ●         SBA provided documentation of their methods to maintain and
skilled systems and cybersecurity                                            manage a skilled pool of cybersecurity and systems engineering
personnel to staff ongoing projects.                                         personnel including:
•     The organization should identify                                       A strategic workforce and succession plan to track metrics for gains
      personnel with security relevant                                       and losses from mission critical occupations, including IT management
      expertise involved in the                                              positions.
      modernization project.                                                 The Fiscal Year 2021-2024 IT Strategic Workforce Plan that
•     The organization should                                                establishes the agency approach to ensuring they have the relevant IT
      maintain and manage a pool of                                          workforce for agency needs.
      skilled cybersecurity and                                              A voluntary bi-annual competency assessment for IT staff that
      systems engineering personnel.                                         assesses foundation, technical, and leadership competencies.
                                                                             A National Recruitment Plan that outlines targeted talent pools.
                                                                             Additionally, SBA reports developing a tech talent recruitment plan to
                                                                             target the cyber workforce.
                                                                             Additionally, SBA identified key security personnel who are involved in
                                                                             the UCP project, including the senior information system security
                                                                             officer.

● Fully met: SBA provided evidence that addressed the entire practice.
◐ Partially met: SBA provided evidence that addressed one or more of the practice activities, but not all the activities.
○ Not met: SBA did not provide evidence that addressed the practice.
Source: GAO analysis of SBA’s documentation. | GAO-25-106963



                                                               The weaknesses in SBA’s implementation of cybersecurity practices are
                                                               due to, among other things, a lack of policies and procedures requiring
                                                               their use. SBA project documentation also lacked specific details to
                                                               address the gaps. For example, SBA stated that a requirements
                                                               traceability matrix was not developed because the business requirements
                                                               document achieves the same outcome, however, this document did not
                                                               provide any detail as to how the contractor had satisfied security
                                                               requirements during the course of development.


                                                               Page 25                                            GAO-25-106963 SBA IT Modernization
                           SBA’s planning documentation for UCP did not include details for how it
                           plans to manage cybersecurity risks at the project level. Specifically, SBA
                           utilizes a cybersecurity appendix for all acquisition contracts that includes
                           general cybersecurity requirements; however, these requirements were
                           not specifically tailored to the needs of the UCP. Further, SBA did not
                           document traceability between security requirements and how the
                           developed system satisfies those requirements.

                           Each of these gaps pose significant risks for the UCP system during or
                           after deployment. For example, without tailored security requirements, or
                           traceability between security requirements and the design of the system,
                           SBA cannot ensure that critical cybersecurity safeguards are fully
                           implemented. This increases the risk of a successful cyberattack where
                           malicious actors gain access to confidential information or disrupt the
                           availability of the system.

                           In addition, for future IT modernization projects, until SBA establishes and
                           implements policies and procedures to require specific plans for how to
                           manage security risks and documents the involvement of security-related
                           subject matter experts in contract selection, SBA will be at risk for
                           expending resources on projects that may not meet the security needs of
                           the agency. Further, until SBA establishes and implements policies and
                           procedures to ensure that a traceability analysis between the security
                           requirements and the proposed IT solution is performed, it faces an
                           increased risk that adequate cybersecurity will not be built into the new
                           system, resulting in a potentially insecure system.

SBA Did Not Develop a      According to GAO’s Schedule Assessment Guide, the success of a
Schedule for Its Unified   project depends in part on having an integrated and reliable master
                           schedule that defines when and how long work will occur and how each
Certification Platform     activity is related to the others.36 The schedule integrates the planned
                           work, the resources necessary to accomplish that work, and the
                           associated budget. This can help determine if the program’s parameters
                           are realistic and achievable.

                           GAO’s research has found that a reliable integrated master schedule is
                           one that is comprehensive, well-constructed, credible, and controlled.
                           Management minimizes the risk of schedule overruns and unmet




                           36GAO-16-89G.




                           Page 26                                       GAO-25-106963 SBA IT Modernization
performance targets by ensuring the integrated master schedule reflects
the following four characteristics.

•   Comprehensive. A comprehensive schedule includes all activities for
    both the government and its contractors necessary to accomplish a
    program’s objectives as defined in the program’s work breakdown
    structure (WBS). The schedule includes the labor, materials, travel,
    facilities, equipment, and the like needed to do the work and depicts
    when those resources are needed and when they will be available. It
    realistically reflects how long each activity will take and allows for
    discrete progress measurement.
•   Well-constructed. A schedule is well-constructed if all its activities
    are logically sequenced with the most straightforward logic possible.
    Unusual or complicated logic techniques are used judiciously and
    justified in the schedule documentation. The schedule’s critical path
    represents a true model of the activities that drive the program’s
    earliest completion date, and total float accurately depicts schedule
    flexibility.
•   Credible. A schedule is credible if it reflects the order of events
    necessary to achieve products or outcomes. It should also reflect
    activities in varying levels of the schedule that relate to one another.
•   Controlled. A schedule is controlled if it is updated regularly to reflect
    actual progress and changes. Updates to the schedule are
    accompanied by a schedule narrative that describes salient changes
    to the work. The current schedule is compared against a designated
    baseline schedule to measure, monitor, and report the program’s
    progress. The baseline schedule is accompanied by a basis
    document that explains the overall approach to the program, defines
    ground rules and assumptions, and describes the unique features of
    the schedule. The baseline schedule and current schedule are
    subjected to configuration management control.
Instead of an integrated master schedule, the project relied on a “product
road map” that is not a schedule. According to SBA officials, the agency
created a UCP product road map as part of their Agile development
framework and aligned it with the two-week sprint cycle process the
product teams follow.

The UCP road map covers calendar year 2024 and contains a section for
certain milestones, such as data migration from the prior systems to UCP
and the deployment of an internal user dashboard. These milestones are
overlaid on time-bounded tasks for the various product teams. However,
the road map does not include milestones for important system


Page 27                                       GAO-25-106963 SBA IT Modernization
cybersecurity tasks, such as when the security requirements will be
finalized and when security testing will be complete. The lack of security
milestones is also discussed later in this report. In addition, the road map
does not include relationships or dependencies between the tasks, nor
does it identify resources for any given activity. Lastly, although SBA
officials stated that they meet with staff to ensure communication between
product teams, they do not rely on an integrated master schedule to track
and plan tasks.

The lack of an integrated master schedule is due, in part, to shortcomings
in SBA’s policies and procedures. Although SBA policy requires a
schedule for new acquisitions, it does not provide procedures and
guidance on how to develop reliable schedule estimates.

According to SBA, its guidance on system development methodology lays
out requirements for project scheduling. However, the guidance only
states that a project management plan should have a road map as part of
the project management plan. It does not describe specific requirements
for what the road map should include, such as how each activity is related
to others or required resources.

Further, SBA officials stated that the Agile methodology does not require
a project schedule equivalent to an integrated master schedule, because
the process results in specific software features being released during
specific time blocks (i.e., individual sprints). According to program
officials, critical path milestones are plotted on the road map, and very
few milestones are truly critical. Officials said the product road map is
sufficient to get the work done in lieu of a master schedule.

However, as explained in GAO’s Agile Assessment Guide, Agile
methodologies still require planning, documentation, and a schedule
baseline.37 Specifically, the guide notes that the adaptive and iterative
nature does not preclude the need for planning and documentation for the
phases of Agile development, how those phases relate to each other, and
updates over the life of the development as new information becomes
available. Additionally, the guide states that the Agile goal of delivering
features at defined intervals still requires the development of a schedule
baseline. According to the guide, the baseline should contain enough
detail to enable collaborative agreement between product owners and
developers. It should be updated with actual data and revisions as

37GAO-24-105506.




Page 28                                      GAO-25-106963 SBA IT Modernization
                            progress is made. It should also provide a record of trends and deviations
                            from the baseline to understand whether program execution is on track or
                            requires changes.

                            The road map provided by SBA does not convey the information available
                            in a reliable integrated master schedule. As a result, it cannot be used to
                            forecast completion dates, help teams plan work based on knowledge of
                            receivables and deliverables, or identify problems that may occur and
                            their effects on downstream work.

                            Until SBA establishes and implements policies and procedures to require
                            the use of an integrated master schedule that reflects GAO’s schedule
                            estimation guidance, the agency faces an increased risk of uncertainty in
                            determining the duration on future IT modernization projects. Such
                            uncertainty can cause schedule slippages, increased project costs, and
                            hinder the ability of agency leadership to make informed decisions.

SBA Cost Estimate for the   According to GAO’s Cost Estimating and Assessment Guide, reliable cost
Unified Certification       estimates are critical for successfully delivering IT programs.38 Such
Platform Was Unreliable     estimates provide the basis for informed decision making, realistic budget
                            formulation, meaningful progress measurement, and accountability for
                            results.

                            GAO’s research has found that a reliable cost estimate is one that is
                            comprehensive, well-documented, accurate, and credible. Management
                            minimizes the risk of cost overruns and unmet performance targets by
                            ensuring cost estimates reflect these four characteristics.

                            •   Comprehensive. Cost estimates completely define the program and
                                reflect the current schedule and technical baseline. They are
                                structured with sufficient detail to ensure that cost elements are
                                neither omitted nor double-counted. Where information is limited and
                                judgments must be made, assumptions and exclusions on which the
                                estimate is based are reasonable, clearly identified, explained, and
                                documented.
                            •   Well-documented. Cost estimates can easily be repeated or updated
                                and can be traced to original sources through auditing. Thorough
                                documentation explicitly identifies the primary methods, calculations,
                                results, rationales or assumptions, and sources of the data used to
                                generate each cost element’s estimate.

                            38GAO-20-195G.




                            Page 29                                     GAO-25-106963 SBA IT Modernization
•   Accurate. Cost estimates are developed by estimating each cost
    element using the best methodology from the data collected. Accurate
    estimates are based on appropriate adjustments for inflation. Their
    underlying mathematical formulas, databases, and inputs are
    validated, and the resulting estimates contain few, if any, minor
    mathematical mistakes. Accurate estimates are based on a historical
    record of cost estimating and actual experiences from comparable
    programs. Finally, they are updated regularly to reflect significant
    changes in the program. Any variances between estimated and actual
    costs are documented, explained, and reviewed.
•   Credible. Cost estimates discuss and document any limitations of the
    analysis, including uncertainty or bias surrounding source data and
    assumptions. The estimate’s major assumptions are varied to
    determine how sensitive it is to changes. Credible cost estimates
    include a risk and uncertainty analysis that determines the level of
    confidence associated with the estimate. In addition, high-value cost
    elements are cross-checked with alternative estimating methodologies
    to validate results. Finally, the estimate is compared with an
    independent cost estimate conducted by a group outside the acquiring
    organization.
The May 2023 SBA cost estimate of approximately $19 million for its UCP
project was unreliable. This was reflected primarily by a lack of evidence
supporting the methodology used to develop the estimate. Although the
estimate was mathematically sound and followed a logical structure, we
could not trace it back to requirements and had no insight into the validity
of the approach used to create the estimate. Our findings below
summarize the analysis of the cost estimate.

Specifically, SBA’s cost estimate partially met two (comprehensive,
accurate), minimally met one (well-documented), and did not meet one of
the four characteristics (credible). Table 6 summarizes our assessment of
SBA’s UCP project cost estimate compared to these characteristics, as of
October 2024. Appendix II provides additional information on our cost
assessment.




Page 30                                      GAO-25-106963 SBA IT Modernization
Table 6: Assessment of Small Business Administration (SBA) Unified Certification Platform (UCP) May 2023 Cost Estimate
Compared to Cost Estimating Leading Practices, as of October 2024

Characteristic         Assessment       Leading practice                    Description of assessment
Comprehensive               ◑           The cost estimate includes all      The cost estimate considers work identified in the
                                        life cycle costs.                   contractor’s performance work statements, for
                                                                            development and one year of operations and
                                                                            maintenance, but it does not include government and
                                                                            system operations costs. When a cost estimate is
                                                                            missing cost elements, the total cost will be
                                                                            underestimated.
                                        The cost estimate is based on       The estimate is the product of estimated hours and rates
                                        a technical baseline description    of pay across various categories. However, it fails to
                                        that completely defines the         show how SBA traced the estimate to a technical
                                        program, reflects the current       baseline description. Without explicit documentation of
                                        schedule, and is technically        the technical baseline of a program’s estimates, it will be
                                        reasonable.                         difficult to update the cost estimate and provide a
                                                                            verifiable trace to a new cost baseline as key
                                                                            assumptions change during the project’s life.
                                        The cost estimate is based on       The estimate relies on a work breakdown structure for
                                        a work breakdown structure          the work identified in the contractor’s performance work
                                        that is product-oriented,           statements.
                                        traceable to the statement of
                                        work, and at an appropriate
                                        level of detail to ensure that
                                        cost elements are neither
                                        omitted nor double-counted.
                                        The cost estimate documents         Although it includes general scope assumptions for the
                                        all cost-influencing ground         contract, the cost estimate does not consider how
                                        rules and assumptions.              ground rules (agreed-upon standards that minimize
                                                                            conflicts in definitions) and assumptions impact the
                                                                            estimate. Without analyzing the effects of changing
                                                                            ground rules and assumptions on the estimated cost and
                                                                            schedule of a program, cost estimators and management
                                                                            will not have a full understanding of their effect and of
                                                                            any limits to their validity.
Well documented             ◔           The cost estimate                   The cost estimate relies on expert judgment and does
                                        documentation shows the             not include supporting documentation that explains the
                                        source data used, the reliability   estimate. Unless the estimate is fully documented, it will
                                        of the data, and the estimating     not support an effective independent review, hindering
                                        methodology used to derive          the understanding of any differences between the
                                        each element’s cost.                proposed estimate and the review. This in turn limits the
                                                                            ability of decision-makers to make informed decisions.
                                        The cost estimate                   The estimate does not discuss how the contractor’s
                                        documentation describes how         performance work statements were used to create the
                                        the estimate was developed so       estimate or whether risk and uncertainty were
                                        that a cost analyst unfamiliar      considered. Unless thoroughly documented, the cost
                                        with the program could              estimate may not be defensible. That is, the
                                        understand what was done and        documentation may not present a convincing argument
                                        replicate it.                       of an estimate’s validity or help answer decision-makers’
                                                                            and oversight groups’ probing questions.




                                        Page 31                                                   GAO-25-106963 SBA IT Modernization
Characteristic   Assessment   Leading practice                  Description of assessment
                              The cost estimate                The estimate cannot be reconstructed from the
                              documentation discusses the      information provided because SBA did not document a
                              technical baseline description   technical baseline description. Because the technical
                              and the data in the technical    baseline is intended to serve as the basis for developing
                              baseline are consistent with the a cost estimate, it should be discussed in the cost
                              cost estimate.                   estimate documentation. Without a technical baseline,
                                                               the cost estimate will not be based on a comprehensive
                                                               program description and will lack specific information
                                                               regarding technical and program risks.
                              The cost estimate                 Although SBA’s Office of the Chief Information Officer
                              documentation provides            and the contracting officer signed off on the cost
                              evidence that the cost estimate   estimate, it lacked information such as an analysis of
                              was reviewed and accepted by      risks, benefits, and the methodology used to estimate
                              management.                       costs. When management is not presented with sufficient
                                                                information about how the estimate was constructed—
                                                                including the specific details about the program’s
                                                                technical characteristics, assumptions, data, cost
                                                                estimating methodologies, sensitivity, and risk and
                                                                uncertainty—management will not know that the
                                                                estimate is complete and high in quality.
Accurate             ◑        The cost estimate is based on     The estimate was developed using expert judgment and
                              a model developed by              does not include supporting data or methodologies.
                              estimating each work              Expert opinion should be used sparingly, and the
                              breakdown structure (WBS)         estimate should account for the possibility that bias
                              element using the best            influenced the results.
                              methodology from the data
                              collected.
                              The cost estimate is adjusted     The estimate was developed using approved inflation-
                              properly for inflation.           adjusted rates but does not include an estimate in base-
                                                                year dollars. Therefore, we were not able to validate
                                                                inflation rates. When adjusting for inflation, if the index
                                                                used is not correct, the resulting estimate could overstate
                                                                or understate the cost of the program.
                              The cost estimate contains      The cost estimate appears mathematically correct.
                              few, if any, minor mathematical
                              mistakes.
                              The cost estimate is based on     According to program officials, documentation does not
                              a historical record of cost       exist to support the estimate, but it is based on the
                              estimating and actual             project manager’s past experience of over 10 years
                              experiences from other            estimating similar programs. A lack of historical data will
                              comparable programs.              leave the cost estimator without insight into actual costs
                                                                of similar programs, including any cost growth since the
                                                                original estimate.
Credible             ○        The cost estimate includes a      SBA did not perform a sensitivity analysis for the UCP
                              sensitivity analysis that         cost estimate. An agency that fails to conduct a
                              identifies a range of possible    sensitivity analysis to identify the effect of uncertainties
                              costs based on varying major      associated with different assumptions increases the
                              assumptions, parameters, and      chances that decisions will be made without a clear
                              data inputs.                      understanding of these impacts on costs.




                              Page 32                                                  GAO-25-106963 SBA IT Modernization
 Characteristic                     Assessment               Leading practice                      Description of assessment
                                                             The cost estimate includes a          SBA did not perform a risk and uncertainty analysis.
                                                             risk and uncertainty analysis         When lacking a risk and uncertainty analysis,
                                                             that quantifies the imperfectly       management cannot determine a defensible level of
                                                             understood risks and identifies       contingency that is necessary to cover increased costs
                                                             the effects of changing key           resulting from unexpected design complexity, incomplete
                                                             cost driver assumptions and           requirements, technology uncertainty, and other
                                                             factors.                              uncertainties.
                                                             The cost estimate employs             The estimate does not indicate that major cost elements
                                                             cross-checks—or alternate             were cross-checked to see whether similar results arise
                                                             methodologies—on major cost           from the use of different methodologies. Unless an
                                                             elements to validate results.         estimate employs cross-checks, the estimate will have
                                                                                                   less credibility because stakeholders will have no
                                                                                                   assurance that alternative estimating methodologies
                                                                                                   produce similar results.

● = Fully met: SBA provided complete evidence that satisfies the entire criterion.
◕ = Substantially met: SBA provided evidence that satisfies a large portion of the criterion.
◑ = Partially met: SBA provided evidence that satisfies about half the criterion.
◔ = Minimally met: SBA provided evidence that satisfies a small portion of the criterion.
○ = Not met: SBA provided no evidence that satisfied any of the criterion.
Source: GAO analysis of UCP project cost estimate and supporting documentation. | GAO-25-106963

                                                              Note: Some criteria for the accurate and credible characteristics were not applicable to the UCP
                                                              project. In particular, the criteria that the cost estimate is regularly updated to ensure it reflects
                                                              program changes and actual costs; the cost estimate documents, explains, and reviews variances
                                                              between planned and actual costs; and the cost estimate is compared to an independent cost
                                                              estimate that is conducted by a group outside the acquiring organization to determine whether other
                                                              estimating methods produce similar results. These criteria did not apply to the UCP project and were
                                                              excluded from the assessment.


                                                              The weaknesses in SBA’s use of cost estimating practices on the UCP
                                                              project are due, in part, to shortcomings in SBA’s policies and
                                                              procedures. Although SBA policies require a cost estimate for new
                                                              acquisitions, it does not provide procedures and guidance on how to
                                                              develop reliable cost estimates. SBA policies also encourage but do not
                                                              require projects to implement leading practices identified in GAO’s cost
                                                              guide. Further, SBA has not provided additional procedures or guidance
                                                              regarding applying the cost estimating leading practices.

                                                              According to the SBA IT program manager, the UCP cost estimate was
                                                              developed based on her own past experience producing similar estimates
                                                              and over a decade of experience in IT contract management. Additionally,
                                                              SBA officials noted that technology acquisitions are overseen by SBA’s
                                                              Office of the Chief Information Officer, which reviews and cross-checks
                                                              cost estimates and serves as a safeguard to the process.

                                                              However, as discussed earlier, subject matter expertise by itself should
                                                              be used sparingly. Given SBA’s multiple attempts at modernizing its


                                                              Page 33                                                      GAO-25-106963 SBA IT Modernization
              certification systems, there should be actual data from those efforts that
              could be used to inform the UCP cost estimate. Furthermore, since SBA
              chose to solely rely on expert opinion, the estimate should have explicitly
              accounted for the possibility of bias since expert opinion is subjective and
              requires objective analyses to supplement it. The agency, however, did
              not perform such analyses (as discussed under the credibility practice).

              Until SBA establishes and implements policies and procedures that
              require the implementation of leading practices identified in the GAO cost
              guide, the agency is less likely to develop reliable cost estimates for its IT
              modernization efforts that can serve as the basis for informed investment
              decision making. In addition, the agency risks being unable to effectively
              estimate funding needs for its IT modernization efforts and using
              unreliable data to make budgetary decisions.

              SBA’s contracting assistance programs rely on IT systems to deliver vital
Conclusions   support services to entrepreneurs. To improve its ability to provide these
              services, SBA planned to deploy UCP to replace existing systems in
              September 2024, but was forced to extend planned deployment into
              October 2024 due to ongoing system development, testing, and issue
              resolution. SBA subsequently deployed the system, but work remains to
              develop additional, more complex functionality, secure the system, and
              migrate data from legacy systems.

              SBA has critical gaps in its risk management implementation for the UCP
              project—notably, the lack of a project-level risk management plan and
              mitigation plan. Due to these gaps, SBA deployed the UCP system
              without a full understanding of the associated risks. Until SBA develops a
              mitigation plan for ongoing risks, the agency will not be able to quickly or
              effectively deal with issues that arise as they simultaneously operate the
              system and develop the more complex functionality that will be added to
              it. Further, it will be important for SBA to fully consider the probability and
              impact of any accepted risks related to issuing a final authorization to
              operate to better ensure that such risks do not affect certification services.

              Shortcomings in SBA’s implementation of leading cybersecurity practices
              also increase the likelihood of a deployed system that includes security
              vulnerabilities. Until it addresses critical cybersecurity weaknesses—
              notably, the lack of a plan for managing project cybersecurity risks and
              documenting traceability between the security requirements and system
              design—it will likely not be prepared for and able to address the impacts
              of a cybersecurity incident.



              Page 34                                       GAO-25-106963 SBA IT Modernization
                      Going forward, it will also be important for SBA to establish policies and
                      procedures to address the gaps we identified in risk management,
                      cybersecurity, and schedule and cost estimation. Until it does so, the
                      agency will be hindered in its ability to effectively manage future IT
                      modernization project risks, ensure that its systems meet the security
                      needs of the agency, and effectively manage the schedules and costs for
                      its projects.

                      We are making fourteen recommendations to SBA:
Recommendations for
Executive Action      The Administrator of SBA should direct the Associate Administrator of
                      SBA’s Office of Government Contracting and Business Development to
                      expeditiously address critical UCP project risk management issues,
                      including developing a project risk management strategy and risk
                      mitigation plan. (Recommendation 1)

                      The Administrator of SBA should direct the Associate Administrator of
                      SBA’s Office of Government Contracting and Business Development to
                      expeditiously address critical UCP project cybersecurity issues, including
                      developing a plan for managing project cybersecurity risks and
                      documenting a traceability analysis for project security requirements.
                      (Recommendation 2)

                      The Administrator of SBA should direct the Chief Information Officer to
                      consider the probability and impact of accepted UCP deployment risks if
                      deciding to issue a final authorization to operate for the system.
                      (Recommendation 3)

                      The Administrator of SBA should direct the Chief Information Officer to
                      establish and implement policies and procedures to ensure that risk
                      registers or equivalent risk documentation explicitly state risk sources for
                      IT modernization projects. (Recommendation 4)

                      The Administrator of SBA should direct the Chief Information Officer to
                      establish and implement policies and procedures to ensure that
                      parameters to categorize or analyze risks are clearly defined at the
                      project level for IT modernization projects. (Recommendation 5)

                      The Administrator of SBA should direct the Chief Information Officer to
                      establish and implement policies and procedures to ensure that project
                      risk management strategies are established and maintained for IT
                      modernization projects. (Recommendation 6)



                      Page 35                                       GAO-25-106963 SBA IT Modernization
The Administrator of SBA should direct the Chief Information Officer to
establish and implement policies and procedures to ensure that risks are
identified and documented for IT modernization projects for all phases of
the development lifecycle, including deployment. (Recommendation 7)

The Administrator of SBA should direct the Chief Information Officer to
establish and implement policies and procedures to ensure that risks are
evaluated, categorized and prioritized using defined parameters, and also
to ensure that project risk mitigation plans are developed for IT
modernization projects. (Recommendation 8)

The Administrator of SBA should direct the Chief Information Officer to
establish and implement policies and procedures to ensure that identified
risk mitigations are connected to a project risk mitigation plan for IT
modernization projects. (Recommendation 9)

The Administrator of SBA should direct the Chief Information Officer to
establish and implement policies and procedures to ensure that IT system
acquisition plans and strategic plans for IT modernization projects contain
all the information needed to manage cybersecurity risks, including how
such risks will be managed, security milestones, how assets will be
protected at a program or project level, and security-relevant criteria for
selecting suppliers. (Recommendation 10)

The Administrator of SBA should direct the Chief Information Officer to
establish and implement policies and procedures to ensure that a
traceability analysis is performed and documented for IT modernization
projects to show the traceability of the security requirements to the design
of the proposed IT system solution. (Recommendation 11)

The Administrator of SBA should direct the Chief Information Officer to
establish and implement policies and procedures to ensure that security-
related subject matter experts are involved in the contractor selection
process for IT modernization projects. (Recommendation 12)

The Administrator of SBA should direct the Chief Information Officer to
establish and implement policies and procedures to ensure that
integrated master schedules are developed for IT modernization projects
using leading practices described in GAO’s Schedule Assessment Guide.
(Recommendation 13)

The Administrator of SBA should direct the Chief Information Officer to
establish and implement policies and procedures to ensure that cost


Page 36                                      GAO-25-106963 SBA IT Modernization
                     estimates for IT modernization projects are developed using leading
                     practices described in GAO’s Cost Estimating and Assessment Guide.
                     (Recommendation 14)



                     We provided a draft of this report to SBA for review and comment. In
Agency Comments      written comments provided by SBA (reproduced in appendix III), the
and Our Evaluation   agency concurred with three recommendations, partially concurred with
                     three recommendations, and did not concur with eight recommendations.

                     The draft report included an additional recommendation that SBA identify
                     UCP deployment delay as a risk and identify mitigation strategies (draft
                     report Recommendation 3). SBA deployed the UCP system on October
                     18, 2024. Therefore, we removed the recommendation and modified our
                     report accordingly.

                     SBA concurred with recommendations 11, 12, and 13 to establish and
                     implement policies and procedures to ensure traceability analyses are
                     documented, security-related subject matter experts are involved in the
                     contractor selection process, and integrated master schedules are
                     developed for IT modernization projects in accordance with the GAO
                     Schedule Guide. SBA stated it intends to initiate activities in line with the
                     recommendations.

                     In addition, SBA partially concurred with our first, second, and third
                     recommendations. Specifically:

                     •   For our first recommendation, SBA noted that it intends to document a
                         UCP project level risk management strategy and risk management
                         plan, expand the risk register to ensure risks are appropriately
                         categorized, prioritized, and evaluated, and determine appropriate
                         mitigation strategies for the risks. These actions are line with our
                         recommendation; however, as noted in our report, we reiterate the
                         need for a risk mitigation plan that includes relevant information such
                         as responsible parties, required tasks, resources, and timelines. As a
                         result, we believe that our recommendation is warranted.
                     •   For our second recommendation, SBA outlined its planned process
                         for assessing the security of the UCP through testing and addressing
                         critical findings during the beta period. SBA also plans to document
                         traceability between security requirements in line with our
                         recommendation. However, as stated in our report, the agency did not




                     Page 37                                       GAO-25-106963 SBA IT Modernization
    document a plan for managing UCP project cybersecurity risks. As
    such, we believe that our recommendation is warranted.
•   For our third recommendation, SBA outlined its procedures for
    approving an authorization to operate for IT systems and agreed that
    additional security measures would enhance the deployment risk
    assessment and validation for the UCP system. As noted in our
    report, it will be important for SBA to fully consider the impact of
    deployment risks when fully authorizing the system, and SBA has yet
    to provide documentation to that effect. As a result, we believe that
    our recommendation is warranted.
SBA did not concur with eight recommendations. Specifically:
•   For recommendations four through nine, SBA outlined its current
    processes and guidance for reviewing and approving major IT
    investments. SBA also reiterated that it has an enterprise risk
    management strategy and cybersecurity and privacy policies that
    reference federally mandated requirements. However, as noted in our
    report, SBA did not provide a UCP project-level risk management
    plan. Additionally, SBA did not provide documentation of the various
    meetings where risks are discussed, and risk management decisions
    made. Further, SBA’s policies and procedures did not require the
    explicit statement of risk sources for IT modernization projects
    (recommendation 4), parameters that define how to categorize or
    analyze risks (recommendation 5), and ensure that project level risk
    management strategies are established (recommendation 6). SBA’s
    policies and procedures also did not require that risks are identified
    and documented at all phases of the development lifecycle
    (recommendation 7), ensure that risks are evaluated, categorized,
    and prioritized using defined parameters and that risk mitigation plans
    are developed (recommendation 8), and that identified risk mitigations
    are connected to project risk mitigation plans (recommendation 9). As
    a result, we maintain that our recommendations on these leading
    practices are warranted.
•   For recommendation 10, SBA stated that its cybersecurity and privacy
    policy and procedures are in-line with federal requirements. SBA also
    noted that its IT-related acquisitions, instructions to potential vendors
    are required to include an appendix that details general cybersecurity
    requirements. However, as noted in our report, the acquisition
    documentation we received for the UCP did not include key project
    level details for how SBA planned to manage risks, protect assets, or
    define security-relevant criteria for selecting the suppliers. As a result,
    we believe our recommendation is warranted.




Page 38                                        GAO-25-106963 SBA IT Modernization
•   For recommendation 14, SBA noted that its current policy references
    the leading practices in GAO’s Cost Estimating and Assessment
    Guide, and that all IT modernization projects are required to follow
    SBA policies. However, as noted in our report, SBA guidance only
    suggests, and does not require, that investments implement leading
    practices identified in GAO’s cost guide. Additionally, we identified
    gaps in the implementation of the leading practices for the UCP. As a
    result, we believe that our recommendation is warranted.
In SBA’s preamble to the recommendation responses, the agency stated
that it believes we mischaracterized its risk management practices in the
report. Specifically, the agency stated that we implied that SBA had no
project risk management in place. However, our report does not state that
SBA had no project risk management. Our report gives credit to SBA for
areas where its efforts aligned with leading practices, such as monitoring
risks through the various meetings attended by the IT program manager
and documenting them in a project level risk register.

However, our report also describes specific instances where SBA’s risk
management documentation and practices do not fully align with leading
practices. For example, we note that SBA does not have a project level
risk management strategy or a project level risk mitigation plan. Further,
in its agencywide risk management guidance and project risk
management tools, SBA does not include explicit risk sources or use
defined parameters when evaluating, categorizing, and prioritizing risks,
among other weaknesses.

SBA also stated that we mischaracterized the agency’s cybersecurity
practices, and that we implied that the UCP project was managed without
any cybersecurity plan or oversight. However, our report does not state
that SBA has no cybersecurity plan or oversight. Our report gives SBA
credit for the areas where its practices and documentation align with
leading cybersecurity practices. For example, we noted that SBA included
security-related aspects in the UCP contract solicitation documentation,
UCP performance work statement, cybersecurity appendix attached to
the UCP contract, and UCP systems requirements document. We also
detailed SBA’s effective methods for maintaining and managing a skilled
pool of cybersecurity and systems engineering personnel.

However, our report also provides instances where SBA’s cybersecurity
documentation and practices do not fully align with leading cybersecurity
practices. For example, as noted in the report, SBA did not include key
details in the UCP acquisition plan for how SBA plans to manage security



Page 39                                     GAO-25-106963 SBA IT Modernization
risks, security milestones, and asset protection at the project level. It also
did not document traceability between security requirements and how the
UCP system is expected to satisfy the requirements; specify how
suppliers would be rated against security criteria; or document how to
involve agency subject matter experts in the contractor selection process.
Additionally, while we note the Office of the Chief Information Security
Officer managed security risks at the agency level, SBA did not provide
documentation of how security risks are managed at the project level.

At the time that we sent our draft report to SBA for comment, the agency
planned to deploy the UCP in September 2024. SBA announced in June
2024 a pause, effective August 1, 2024, in accepting new applications for
certification. According to SBA, it planned to lift the pause when the new
system was deployed. Based on our findings when the report was sent to
SBA for comment, we raised concerns about SBA’s ability to deploy the
system on time and without significant deficiencies. We posed questions
to SBA about 1) how long the agency planned to wait to lift the new
application pause in case of a deployment delay, and 2) in the case of a
delayed deployment or performance issues, whether SBA could
temporarily return to its processes that were previously in place. In its
response, SBA noted that that pause was intended to clear a backlog of
certification applications and did not anticipate significant delays.

As discussed in the report, SBA did experience a delay before deploying
the system. In addition, work still remains to develop additional, more
complex functionality, secure the system, and migrate data. In follow-ups
with SBA, officials reported making recent changes in management of the
UCP. These include the appointment of a Chief Technology Officer and a
new project manager. SBA also noted that they have conducted security
testing with the assistance of the Cybersecurity and Infrastructure
Security Agency. These actions are positive steps toward addressing the
issues we identified in our report and our recommendations.

As agreed with your office, unless you publicly announce the contents of
this report earlier, we plan no further distribution until 7 days from the
report date. At that time we will send copies of this report to the
appropriate congressional committee, the Administrator of SBA, and other
interested parties. In addition, the report will be available at no charge on
the GAO website at https://www.gao.gov.

If you or your staff have any questions about this report, please contact
Carol C. Harris at (202) 512-4456 or HarrisCC@gao.gov, or Courtney
LaFountain at (202) 512-5463 or LaFountainC@gao.gov. Contact points


Page 40                                       GAO-25-106963 SBA IT Modernization
for our Offices of Congressional Relations and Public Affairs may be
found on the last page of this report. GAO staff who made key
contributions to this report are listed in appendix IV.

Sincerely,




Carol C. Harris, Director
Information Technology and Cybersecurity




Courtney LaFountain, Acting Director
Financial Markets & Community Investment




Page 41                                    GAO-25-106963 SBA IT Modernization
Appendix I: Objectives, Scope, and
              Appendix I: Objectives, Scope, and
              Methodology


Methodology

              Our objectives were to (1) describe the Small Business Administration’s
              (SBA) plans for the Unified Certification Platform (UCP) project and the
              status of its efforts; (2) determine to what extent the UCP project has
              adopted leading IT management practices for risk management,
              cybersecurity, and schedule and cost estimation.

              To address our first objective, we reviewed and summarized relevant
              UCP project information such as acquisition plans, solicitation documents,
              monthly meeting minutes, and schedule and cost documentation.
              Specifically, we determined which key UCP project activities had been
              completed as of July 2024 and the expected completion dates for the
              remaining activities. We also reviewed SBA documentation regarding its
              planned pause in accepting certification applications prior to deployment.
              Lastly, we interviewed agency officials to verify SBA’s plans for its
              modernization effort and its current status.

              To address our second objective, we assessed the UCP project and
              SBA’s policies and procedures for managing risks, cybersecurity, and
              schedule and cost estimation.

              •   To determine the extent to which SBA implemented leading practices
                  for risk management, we identified seven risk management leading
                  practices based on prior GAO work and ISACA’s Capability Maturity
                  Model Integration (CMMI).1 These leading practices map to the
                  managed practices of risk management, where projects are planned,
                  performed, measured, and controlled. These selected practices were
                  (1) determining risk sources and categories; (2) defining parameters
                  to analyze and categorize risks; (3) establishing and maintaining a risk
                  management strategy; (4) identifying and documenting risks; (5)
                  evaluating, categorizing, and prioritizing each identified risk; (6)
                  developing a risk mitigation plan in accordance with the risk
                  management strategy; and (7) monitoring the status of each risk
                  periodically and implementing the risk mitigation plan as appropriate.
                  We then evaluated the UCP project documentation, such as the risk
                  registers and SBA policies on risk management, against the seven
                  selected leading practices to determine whether the project fully met,




              1ISACA, CMMI Model V3.0 (Pittsburgh, PA: Apr. 6, 2023). CMMI Model and ISACA©
              [2021] All rights reserved. Used with permission.




              Page 42                                         GAO-25-106963 SBA IT Modernization
Appendix I: Objectives, Scope, and
Methodology




    partially met, or did not meet the practices.2 We also reviewed SBA
    documentation regarding its planned pause in accepting certification
    application and its UCP system deployment plans. We then reviewed
    SBA’s risk register, provided to us in February 2024, for system
    deployment risks and mitigation strategies related to its planned UCP
    system deployment.3
•   To determine the extent that SBA had adopted leading practices for
    cybersecurity, we identified and selected five leading practices that
    represented key elements for addressing cybersecurity requirements
    and needs in an acquisition based on prior GAO work and the
    National Institute of Standards and Technology’s (NIST) guidance on
    Engineering Trustworthy Secure Systems.4 The selected leading
    practices are (1) defining security aspects for how the acquisition
    would be conducted; (2) including security requirements as part of
    system requirements; (3) selecting one or more suppliers that meet
    the security criteria; (4) developing an agreement with supplier that
    includes the security requirements that will be supplied; and (5)
    identifying, acquiring, and maintaining skilled systems and
    cybersecurity personnel to staff ongoing projects.
    We then evaluated documentation related to the UCP project,
    including the UCP project acquisition plan, request for quotes, and
    performance work statements against the selected leading practices
    to determine whether the project fully met, partially met, or did not
    meet the practices.5
•   To determine the extent to which SBA implemented schedule
    estimation leading practices for the UCP project, we reviewed
    documentation supporting the project’s road map from January 2024.
    We assessed this documentation against leading practices for
2“Fully met” means that the agency provided evidence that satisfies the entire practice,
“partially met” means the agency provided evidence that addressed one or more of the
practice activities, but not all of the activities, and “not met” means the agency provided no
evidence that addressed the practice.
3We provided SBA with the opportunity to produce a more recent risk register and other
documentation of the meetings where risks are discussed and documented; however, the
agency has not yet provided us with any such documents.
4National Institute of Standards and Technology, Engineering Trustworthy Secure
Systems, Special Publication 800-160, Volume 1, Revision 1 (Gaithersburg, Md.: Nov. 16,
2022).
5“Fully met” means that the agency provided evidence that satisfies the entire practice,
“partially met” means the agency provided evidence that addressed one or more of the
practice activities, but not all of the activities, and “not met” means the agency provided no
evidence that addressed the practice.




Page 43                                                 GAO-25-106963 SBA IT Modernization
Appendix I: Objectives, Scope, and
Methodology




    developing a comprehensive, well-constructed, credible, and
    controlled schedule, as identified in GAO’s Schedule Assessment
    Guide.6 We also interviewed program officials responsible for
    developing and managing the road map, including the UCP program
    manager, to understand the practices for creating and maintaining the
    road map.
    To assess the reliability of SBA’s schedule data, we evaluated
    relevant UCP documentation such as the project road map, to
    substantiate evidence obtained from interviews with knowledgeable
    agency officials. We determined that the schedule data provided by
    SBA was not complete and reliable. We discuss the limitations of this
    data in the report and we have made appropriate attribution indicating
    the sources of this data.
•   Finally, to determine the extent to which SBA had adopted cost
    estimation leading practices, we reviewed documentation supporting
    SBA’s UCP project cost estimates from May 2023. We assessed this
    documentation against the leading practices in GAO’s Cost Estimating
    and Assessment Guide.7 These leading practices map to four
    characteristics of a high-quality, reliable cost estimate. Those
    characteristics are: comprehensive, well-documented, accurate, and
    credible. To understand UCP’s methodology, data, and approach we
    interviewed relevant agency officials, including the UCP program
    manager. In performing our analysis for the UCP project, we
    determined the extent to which each characteristic was either not met,
    minimally met, partially met, substantially met, or fully met.8
    We shared our preliminary cost findings with project officials to verify
    that the information on which we based our findings was complete,
    accurate, and up-to-date. We then discussed our preliminary
    assessment results with the project management officials.
    To assess the reliability of SBA’s cost data, we evaluated relevant
    UCP documentation, such as the cost estimate and contracts, to

6GAO, Schedule Assessment Guide: Best Practices for Project Schedules, GAO-16-89G
(Washington, D.C.: Dec. 22, 2015).
7GAO, Cost Estimating and Assessment Guide: Best Practices for Developing and
Managing Program Costs, GAO-20-195G (Washington, D.C.: Mar. 12, 2020).
8“Not met” means SBA provided no evidence that satisfies any of the leading practices
criterion. “Minimally met” means SBA provided evidence that satisfies a small portion of
the criterion. “Partially met” means SBA provided evidence that satisfies about half of the
criterion. “Substantially met” means SBA provided evidence that satisfies a large portion of
the criterion. “Fully met” means SBA provided evidence that completely satisfies the
leading practices criterion.




Page 44                                               GAO-25-106963 SBA IT Modernization
Appendix I: Objectives, Scope, and
Methodology




    substantiate evidence obtained from interviews with knowledgeable
    agency officials. We determined that the cost data provided by SBA
    was not complete and reliable. We discuss the limitations of this data
    in the report and we have made appropriate attribution indicating the
    sources of this data.
For both objectives, we interviewed cognizant agency officials in SBA’s
Office of Government Contracting and Business Development, as well as
SBA’s Office of the Chief Information Officer to obtain their views and
verify the information provided.

We conducted this performance audit from July 2023 to November 2024
in accordance with generally accepted government auditing standards.
Those standards require that we plan and perform the audit to obtain
sufficient, appropriate evidence to provide a reasonable basis for our
findings and conclusions based on our audit objectives. We believe that
the evidence obtained provides a reasonable basis for our findings and
conclusions based on our audit objectives.




Page 45                                     GAO-25-106963 SBA IT Modernization
Appendix II: SBA UCP Project Cost Estimate
                                         Appendix II: SBA UCP Project Cost Estimate
                                         Compared to Leading Practices


Compared to Leading Practices

                                         According to the GAO Cost Estimating and Assessment Guide,1 the four
                                         characteristics of a high-quality, reliable cost estimate are
                                         comprehensive, well-documented, accurate, and credible. Table 7
                                         provides our assessment of the Unified Certification Platform (UCP)
                                         project’s cost estimate compared to these characteristics and the
                                         associated leading practices, as of October 2024.

Table 7: Assessment of the Unified Certification Platform (UCP) Cost Estimate Compared to Leading Practices, as of October
2024

                      Overall                                                                                         Individual
Characteristic        assessment         Leading practice                                                             assessment
Comprehensive         Partially met      The cost estimate includes all life cycle costs.                             Partially met
                                         The cost estimate is based on a technical baseline description that          Partially met
                                         completely defines the program, reflects the current schedule, and is
                                         technically reasonable.
                                         The cost estimate is based on a work breakdown structure (WBS) that is Substantially
                                         product-oriented, traceable to the statement of work, and at an        met
                                         appropriate level of detail to ensure that cost elements are neither
                                         omitted nor double-counted.
                                         The cost estimate documents all cost-influencing ground rules and            Partially met
                                         assumptions.
Well documented       Minimally met      The cost estimate documentation shows the source data used, the              Minimally met
                                         reliability of the data, and the estimating methodology used to derive
                                         each element’s cost.
                                         The cost estimate documentation describes how the estimate was               Minimally met
                                         developed so that a cost analyst unfamiliar with the program could
                                         understand what was done and replicate it.
                                         The cost estimate documentation discusses the technical baseline             Not met
                                         description and the data in the technical baseline are consistent with the
                                         cost estimate
                                         The cost estimate documentation provides evidence that the cost              Partially met
                                         estimate was reviewed and accepted by management.
Accurate              Partially met      The cost estimate is based on a model developed by estimating each           Minimally met
                                         WBS element using the best methodology from the data collected.
                                         The cost estimate is adjusted properly for inflation.                        Minimally met
                                         The cost estimate contains few, if any, minor mistakes.                      Substantially
                                                                                                                      met
                                         The cost estimate is regularly updated to ensure it reflects program         Not applicable
                                         changes and actual costs.
                                         The cost estimate documents, explains, and reviews variances between         Not applicable
                                         planned and actual costs.


                                         1GAO, Cost Estimating and Assessment Guide: Best Practices for Developing and
                                         Managing Program Costs, GAO-20-195G (Washington, D.C.: Mar 12, 2020).




                                         Page 46                                                 GAO-25-106963 SBA IT Modernization
                                                              Appendix II: SBA UCP Project Cost Estimate
                                                              Compared to Leading Practices




                                 Overall                                                                                                  Individual
 Characteristic                  assessment                    Leading practice                                                           assessment
                                                               The cost estimate is based on a historical record of cost estimating and   Minimally met
                                                               actual experiences from other comparable programs
 Credible                        Not met                       The cost estimate includes a sensitivity analysis that identifies a range of Not met
                                                               possible costs based on varying major assumptions, parameters, and
                                                               data inputs.
                                                               The cost estimate includes a risk and uncertainty analysis that quantifies Not met
                                                               the imperfectly understood risks and identifies the effects of changing
                                                               key cost driver assumptions and factors.
                                                               The cost estimate employs cross-checks—or alternate methodologies—         Not met
                                                               on major cost elements to validate results.
                                                               The cost estimate is compared to an independent cost estimate that is      Not applicable
                                                               conducted by a group outside the acquiring organization to determine
                                                               whether other estimating methods produce similar results.

Fully met: SBA provided complete evidence that satisfies the entire criterion.
Substantially met: SBA provided evidence that satisfies a large portion of the criterion.
Partially met: provided evidence that satisfies about half the criterion.
Minimally met: SBA provided evidence that satisfies a small portion of the criterion.
Not met: SBA provided no evidence that satisfied any of the criterion.
Source: GAO analysis of UCP project cost estimate and supporting documentation. | GAO-25-106963




                                                              Page 47                                               GAO-25-106963 SBA IT Modernization
Appendix III: Comments from the Small
              Appendix III: Comments from the Small
              Business Administration


Business Administration




              Page 48                                 GAO-25-106963 SBA IT Modernization
Appendix III: Comments from the Small
Business Administration




Page 49                                 GAO-25-106963 SBA IT Modernization
Appendix III: Comments from the Small
Business Administration




Page 50                                 GAO-25-106963 SBA IT Modernization
Appendix III: Comments from the Small
Business Administration




Page 51                                 GAO-25-106963 SBA IT Modernization
Appendix III: Comments from the Small
Business Administration




Page 52                                 GAO-25-106963 SBA IT Modernization
Appendix III: Comments from the Small
Business Administration




Page 53                                 GAO-25-106963 SBA IT Modernization
Appendix III: Comments from the Small
Business Administration




Page 54                                 GAO-25-106963 SBA IT Modernization
Appendix III: Comments from the Small
Business Administration




Page 55                                 GAO-25-106963 SBA IT Modernization
Appendix III: Comments from the Small
Business Administration




Page 56                                 GAO-25-106963 SBA IT Modernization
Appendix IV: GAO Contacts and Staff
                  Appendix IV: GAO Contacts and Staff
                  Acknowledgments


Acknowledgments

                  Carol C. Harris at (202) 512-4456 or HarrisCC@gao.gov
GAO Contacts
                  Courtney LaFountain at (202) 512-5463 or LaFountainC@gao.gov

                  In addition to the contact named above, the following staff made key
Staff             contributions to this report: Jon Ticehurst (Assistant Director), Marshall
Acknowledgments   Hamlett (Assistant Director), Lee Hinga (Analyst-in-Charge), Donna Epler,
                  Emile Ettedgui, Michael Farrell, Jason Lee, Lisa Maine, and Richard
                  Zarrella.




                  Page 57                                    GAO-25-106963 SBA IT Modernization
                         The Government Accountability Office, the audit, evaluation, and investigative
GAO’s Mission            arm of Congress, exists to support Congress in meeting its constitutional
                         responsibilities and to help improve the performance and accountability of the
                         federal government for the American people. GAO examines the use of public
                         funds; evaluates federal programs and policies; and provides analyses,
                         recommendations, and other assistance to help Congress make informed
                         oversight, policy, and funding decisions. GAO’s commitment to good government
                         is reflected in its core values of accountability, integrity, and reliability.

                         The fastest and easiest way to obtain copies of GAO documents at no cost is
Obtaining Copies of      through our website. Each weekday afternoon, GAO posts on its website newly
GAO Reports and          released reports, testimony, and correspondence. You can also subscribe to
                         GAO’s email updates to receive notification of newly posted products.
Testimony
Order by Phone           The price of each GAO publication reflects GAO’s actual cost of production and
                         distribution and depends on the number of pages in the publication and whether
                         the publication is printed in color or black and white. Pricing and ordering
                         information is posted on GAO’s website, https://www.gao.gov/ordering.htm.
                         Place orders by calling (202) 512-6000, toll free (866) 801-7077, or
                         TDD (202) 512-2537.
                         Orders may be paid for using American Express, Discover Card, MasterCard,
                         Visa, check, or money order. Call for additional information.

                         Connect with GAO on Facebook, Flickr, X, and YouTube.
Connect with GAO         Subscribe to our RSS Feeds or Email Updates. Listen to our Podcasts.
                         Visit GAO on the web at https://www.gao.gov.

                         Contact FraudNet:
To Report Fraud,
                         Website: https://www.gao.gov/about/what-gao-does/fraudnet
Waste, and Abuse in
                         Automated answering system: (800) 424-5454 or (202) 512-7700
Federal Programs
                         A. Nicole Clowers, Managing Director, ClowersA@gao.gov, (202) 512-4400, U.S.
Congressional            Government Accountability Office, 441 G Street NW, Room 7125, Washington,
Relations                DC 20548

                         Sarah Kaczmarek, Managing Director, KaczmarekS@gao.gov, (202) 512-4800,
Public Affairs           U.S. Government Accountability Office, 441 G Street NW, Room 7149
                         Washington, DC 20548

                         Stephen J. Sanford, Managing Director, spel@gao.gov, (202) 512-4707
Strategic Planning and   U.S. Government Accountability Office, 441 G Street NW, Room 7814,
External Liaison         Washington, DC 20548




                            Please Print on Recycled Paper.


File and source

File
gao-25-106963.pdf
Size
2,294,383 bytes
SHA-256
50c674273ed35a080d84c029ee63052ff5e836a12b46b557fccfc550e0821f07
Our copy
gao-25-106963.pdf
Original
www.gao.gov
Back to top