Quarterly Performance Report of the Virginia Telecommunication Initiative, Q4 FY2025 (July 2025)
Summary
Quarterly Performance Report of the Virginia Telecommunication Initiative, Q4 FY2025, submitted by the Department of Housing and Community Development in July 2025. The report states that the Virginia Telecommunication Initiative (VATI) provides grants to localities partnered with internet service providers to finance the deployment of high-speed broadband to locations (called a “passing”) determined to be “unserved.” It states that a passing is unserved if it lacks access to internet speeds of 100 Megabits per second (Mbps) download and 20 Megabits (Mbps) upload. It also states that the report was prepared by the Office of Broadband and tracks the technical performance of the VATI provider partners.
Summary drafted by a model from the document's text below and checked by script against that text before publication. It is a navigation aid, not a reading of what the document proves. Where AI is used
Cite this document
“Quarterly Performance Report of the Virginia Telecommunication Initiative, Q4 FY2025 (July 2025).”
Archived at Pandemic Darlings, https://pandemicdarlings.com/source-documents/2026-rd157-2a911de091/
, SHA-256 10c9d02288671b72e3e33ce2e9c3301b96e83e676b9a7060e35d85b9d91b79d2.Full text
Quarterly Performance Report of the
Virginia Telecommunication Initiative
Q4 FY2025 Report
Submitted by:
The Department of Housing and Community Development
July 2025
Executive Summary
Virginia funds broadband deployment within the Commonwealth through several programs. The
largest and main program is the Virginia Telecommunication Initiative (VATI).
VATI provides grants to localities partnered with internet service providers to finance the
deployment of high-speed broadband to locations (called a “passing”) within the Commonwealth
that are determined to be “unserved.” Passings are places where the internet can be accessed – thus
it could be a business, community anchor, a home, or an apartment complex. A passing is
unserved1 if it lacks access to internet speeds of 100 Megabits per second (Mbps) download and
20 Megabits (Mbps) upload (“100/20”).
This quarterly report is required by statute and has been prepared by the Office of Broadband
located within the Virginia Department of Housing and Community Development (DHCD). This
report tracks the technical performance of the VATI provider partners in their work to deploy
broadband. This report adheres to the factors that the General Assembly directed to be tracked and
presents them in the manner directed by the General Assembly.
Below are the key takeaways from the report:
● Total passings: VATI FY22, FY23, and FY24 projects will provide access to
broadband infrastructure to 319,553 passings across Virginia.
● Leveraged local and private funding: In addition to $813 million in state and federal
funding awarded, FY22, FY23, and FY24 projects leverage a total of $1.189 billion in
private and local match funding. To-date, $372.9 million of these awarded funds and
$574.8 million of these matching funds have been expended.
● Locations Built-To: To date, projects have provided broadband access to 138,512
locations.
● Maximum Speeds Available: Over 93.4% of projects funded in FY22, FY23, and FY24
offer functionally gigabit (1,000 Mbps) download speeds, and over 73.7% offer
functionally gigabit upload speeds.
In conclusion, 25 out of the 56 open projects funded from the American Rescue Plan Act of
2021 (ARPA) and General Funds from FY22, FY23, and FY24 are scheduled to be completed on
time as of this report’s submission. DHCD identifies 31 projects are at risk for incompletion or
underperformance. Justification for these delays include the make-ready effort, which includes
preparing existing electric poles for aerial broadband network construction, as well as supply chain
and labor markets, streamlining utility locate efforts, railroad crossings, the permitting process to
lay fiber in state-owned rights of way along roads, and permitting to cross federally owned lands.
Looking forward, DHCD will continue its ongoing work to monitor these projects, assisting where
appropriate in mitigating these broadband deployment challenges.
1
In the FY22 VATI process, the definition of unserved was set at 25/3. This definition of unserved has been upgraded to those
passings lacking access to broadband at speeds of 100/20 for the FY23 VATI process
Formal Report
Pursuant to Chapter 1 of the Virginia Acts of Assembly of Special Session II of 2021
and continued forward in the 2024 Special Session 1 under Chapter 2 of the Virginia Acts of
Assembly, enclosed is the Quarterly Performance Report of the Virginia Telecommunication
Initiative (VATI).
Item 103 L.6. of the 2024 Acts of Assembly Special Session I requires that DHCD deliver
a quarterly performance report on funds awarded through the 2021 Acts of Assembly Special
Session I (also known as the budget bill) of allocated ARPA funds, as well as state general funds
awarded through the Virginia Telecommunication Initiative since the aforementioned FY2022
budget cycle.
Administered by the Virginia Department of Housing and Community Development
(DHCD), VATI enhances the sustainability and growth of communities throughout the
Commonwealth by preparing those communities to build, utilize, and capitalize on broadband
infrastructure. The primary objective of VATI is to provide financial assistance to supplement
construction costs by private sector broadband service providers to extend service to areas that
presently are unserved by any broadband provider. This program requires a public-private
partnership.
The directive to form this quarterly performance report establishes that:
To the extent possible, the quarterly performance report shall contain
information by grant recipient and year on the following metrics: (1) Number of
passings; (2) Grant dollars expended by fund source (State and Local Recovery
Fund, Capital Project Fund, general fund state grants and match); (3) Contract
performance period, and on-time progress towards project delivery; (4)
Maximum advertised project speeds available; and, (5) Achievement of key
project milestones. The quarterly report shall be due within 30 days of the close
of the quarter. The quarterly performance report shall include an evaluation of
any projects under risk of incompletion or underperformance. The department in
providing such risk assessment shall include a reason for the project's delay.
In accordance with this structure, DHCD has included information in this report of the
projects that were awarded funds since December 2021, and includes the projects announced
in the FY2022, FY2023, and FY2024 cycles, including those projects funded under the
Coronavirus State and Local Fiscal Recovery Fund and Coronavirus Capital Projects Funds
allocations under the American Rescue Plan Act of 2021. Project information displayed in this
report reflects monthly report data from June 2025, which reflects project data as of the end of
May 2025.
Out of the 56 open projects funded in FY22, FY23, and FY24, 29 have requested and
received timeline extensions, and, per DHCD’s analysis, 23 are considered to be at low risk
and 8 are considered to be at high risk. DHCD has established risk definitions specific to
funding year. A summary of these definitions provided in the table below. The definition of
risk category
varies for the FY2022 funding year, as this funding year contained American Rescue Plan Act
funding, which has a statutory expenditure deadline of December 31, 2026.
Year Risk Level Risk Level Definition
• The grantee has not requested a timeline extension beyond
FY22 No Risk the originally approved contract end date; and,
• Based on the sole determination of the Office of Broadband,
the grantee is not significantly behind the current approved
milestone timeline; and,
• The timeline for that project does not have an end date in
2026.
• The grantee has requested a timeline extension beyond the
FY22 Low Risk originally approved contract end date; or,
• Based on the sole determination of the Office of Broadband,
the grantee is significantly behind the current approved
milestone timeline and has not yet requested a timeline
extension from the original completion date.
• The grantee’s contractual end date is in 2026, regardless of
FY22 High Risk if that end date reflects the original contractually established
end date or is a result of an extension.
FY23, FY24 No Risk • The grantee has not requested a timeline extension beyond
the originally approved contract end date; and,
• Based on the sole determination of the Office of Broadband,
the grantee is not significantly behind the current approved
milestone timeline.
FY23, FY24 Low Risk • The grantee has requested a timeline extension beyond the
originally approved contract end date; or,
• Based on the sole determination of the Office of Broadband,
the grantee is significantly behind the current approved
milestone timeline and has not yet requested a timeline
extension from the original completion date.
FY23, FY24 High Risk • The grantee has requested more than one timeline
extension beyond the originally approved contract end
date.
DHCD staff continue to closely monitor the continued impact of challenges surrounding
make-ready, which includes preparing existing electric poles for aerial broadband network
construction. DHCD has recently funded the first projects under the Virginia Make Ready
Initiative, which is designed to mitigate the impacts of elevated make-ready costs. DHCD is
closely monitoring the impact of this program on accelerating delivery of affected VATI
projects.
Other deployment challenges which are being monitored by DHCD include supply
chain and labor markets, streamlining utility locate efforts, railroad crossings, the permitting
process to lay fiber in state-owned rights of way along roads, and permitting to cross federally
owned lands. DHCD and its local government and internet service provider partners are
continuing to develop innovative solutions to meet these challenges and deliver high-speed
broadband access as quickly as possible for residents in these project areas.
The project summaries included in this report are updated quarterly on the VATI Project
Dashboard, accessible through dhcd.virginia.gov/vati.
Q4 FY2025 Quarterly Performance Report for the Virginia Telecommunication Initiative - FY2022 Projects
Award Funding
Source - (GF,
Percent General Fund
Total Complete )(SLFRF, Percent Percent
Maximum
Passings Passings Coronavirus State Expended, Expended, Advertised
Passings Provided Provided Reason and Local Fiscal Out of Out of
Recovery Fund Project Speeds
Internet Service in Broadband Broadband for a Total Total Available
)(CPF, Coronavirus
Provider Project Access to Access to Agreement Agreement End Project’s Capital Projects Awarded Funding Awarded Total Match Match Funding Match (Download/
Grantee Partner Area Date Date Start Date Date Risk Delay Award Amount Fund) Expended Funding Funding Expended Funding Upload Mbps)
Bedford ZiTEL 5644 5593 99.00% 06/15/2022 7/1/2025 Low Risk MR $11,480,664.98 GF & SLFRF $10,855,750.74 94.56% $14,518,564.42 $13,104,026.36 90.26% 1000/1000
MR, UL,
RR, ROW,
Bedford Shentel 3204 2475 77.00% 09/09/2022 9/21/2025 Low Risk FED $6,191,796.33 GF & SLFRF $3,626,351.84 58.57% $13,911,783.67 $7,937,368.58 57.06% 1000/1000
Botetourt Lumos Networks 1901 1870 98.00% 11/01/2022 6/30/2025 Low Risk MR $3,084,796.00 CPF $1,285,150.16 42% $4,824,937.00 $3,648,742.24 75.62% 1000/1000
Campbell Shentel 3509 2746 78.00% 09/21/2022 9/21/2025 Low Risk MR, UL $6,443,000.00 GF & SLFRF $2,487,275.31 38.6% $12,978,455.00 $5,011,093.61 38.61% 1000/1000
Central MR,
Shenandoah ROW,
PDC MGW/ Rob Huff 2470 1114 45.00% 6/1/2022 12/1/2025 Low Risk FED, OTH $7,876,800.00 SLFRF $4,035,847.93 51% $3,118,706.00 $1,746,008.07 55.99% 1000/50
OTH: Ice
Commonwealt storm,
h RC Kinex 11397 7359 65.00% 06/14/2022 6/14/2026 High Risk SCL $15,000,000.00 GF $11,373,545.98 76% $13,426,482 $10,327,984.80 76.92% 200/10
Cumberland
Plateau PDC Point Broadband 5659 5113 90.00% 09/06/2022 9/6/2025 Low Risk MR $23,478,429.00 CPF $14,135,023.55 60% $6,459,000.00 $3,888,595.87 60.2% 1000/500
Eastern Shore
of Virginia
Broadband
Authority ESVBA 11091 9381 85.00% 6/1/2022 11/30/2024 Low Risk OTH $12,310,777.25 SLFRF $8,236,666.46 67% $3,314,865.50 $1,710,030.43 51.57% 1000/1000
Franklin
County
Shentel MR, UL,
Project Shentel 3508 1970 56.00% 10/17/2025 10/17/2025 Low Risk RR $11,832,456.00 GF & SLFRF $4,448,444.13 37.6% $18,646,520.00 $13,985,190.37 75% 1000/1000
Hampton Charter
Roads PDC Communications 12223 2336 19.00% 07/08/2022 6/30/2026 High Risk None $21,120,053.50 SLFRF $8,862,135.08 42% $13,839,523.00 $6,448,892.42 46.7% 1000/500
All Points
Hanover Broadband 6198 1363 22.00% 8/1/2022 12/31/2025 Low Risk MR $13,970,000.00 SLFRF $3,631,562.45 26.00% $41,469,332.00 $6,362,226.54 15.34% 1000/1000
All Points
King William Broadband 2236 2236 100.00% 8/3/2022 3/31/2025 Low Risk MR $5,400,000.00 SLFRF $4,859,999.93 42% $12,330,632.00 $14,828,144.58 120% 1000/1000
Scott County
LENOWISCO Telephone
PDC Cooperative 10982 5856 53.00% 06/13/2022 12/13/2025 Low Risk MR, RR $22,190,500.00 SLFRF & CPF $12,548,349.90 56.55% $6,354,500.00 $3,961,620.55 62.34% 1000/1000
Loudoun All Points
County Broadband 8629 1 0.00% 7/1/2022 10/31/2025 Low Risk MR $17,524,000.00 SLFRF $4,003,000.96 22.84% $42,376,126.00 $5,448,166.80 12.86% 1000/1000
Middlesex All Points
County Broadband 970 802 83.00% 7/22/2022 7/31/2025 Low Risk MR $2,050,000.00 SLFRF $1,845,000 90% $8,453,887.00 $10,184,558.02 120% 1000/1000
Mount Rogers
PDC Point Broadband 27450 26390 96.00% 06/01/2022 5/31/2025 Low Risk MR $66,203,228.00 CPF $53,562,446.46 81% $33,162,600.00 $29,870,642.96 90.07% 1000/500
New River
Valley
Regional
Commission Gigabeam 12094 710 6.00% 03/13/2023 3/13/2026 High Risk RR $39,233,355.00 CPF $13,262,497.22 34% $38,247,340.00 $13,336,035.05 34.87% 1000/1000
New River
Valley
Regional All Points
Commission Broadband 7872 0 0.00% 12/06/2022 12/31/2025 Low Risk MR $29,122,000.00 CPF $5,913,400.39 20.31% $26,103,057.19 $4,594,339.19 17.6% 1000/1000
Northern Neck All Points
PDC Broadband 3411 3411 100.00% 9/22/2022 3/31/2025 Low Risk MR $3,190,500.00 SLFRF $2,874,450 90% $20,477,692.00 $20,477,677.64 99.99% 1000/1000
Northern
Shenandoah
Valley
Regional All Points
Commission Broadband 32238 1 0.00% 7/22/2022 6/30/2026 High Risk MR $96,873,500.00 SLFRF $23,879,664.28 25% $206,243,317.00 $95,212,655.74 46.17% 1000/1000
Roanoke B2X 520 180 35.00% 09/22/2022 10/25/2025 Low Risk SCL, OTH $170,609.00 GF $35,295.43 20.69% $177,572.00 $40,817.85 22.99% 25/4
Roanoke Cox 396 249 63.00% 9/1/2022 10/15/2025 Low Risk FED $1,535,264.00 SLFRF $0.00 0.00% $1,597,927.00 $0.00 0.00% 940/35
Roanoke Shentel 213 0 0.00% 10/03/2022 5/31/2025 Low Risk MR, RR $490,000.00 SLFRF $141,360 28.85% $510,000.00 $215,049.73 42.17% 1000/1000
Shenandoah
County Public
Schools Shentel 4139 3240 78.00% 8/1/2022 8/1/2025 Low Risk MR, UL $12,176,662.00 SLFRF $7,674,299.54 63% $20,733,235.00 $13,067,050.58 63.02% 1000/1000
OTH:
Middle
Mile
EMPOWER Construct
Southside PDC Broadband 14634 11961 81.73% 07/22/2022 6/22/2026 High Risk ion $69,431,635.00 SLFRF $44,660,488.15 64% $84,677,555.00 $54,312,663.06 64.14% 1000/1000
Sussex RuralBand 2267 1320 58.00% 06/13/2022 12/13/2025 Low Risk None $4,896,892.00 SLFRF $4,097,081.35 84% $1,678,571.00 $1,404,572.14 83.68% 1000/1000
Thomas Firefly
Jefferson PDC Broadband 36225 21559 60.00% 08/15/2022 8/15/2025 None None $79,027,930.00 SLFRF $55,228,209.70 70% $208,969,670.00 $145,746,278.52 69.75% 1000/1000
West
Piedmont PDC
- Dinwiddie RuralBand 417 108 26.00% 07/03/2022 12/31/2026 High Risk None $638,718.00 SLFRF $126,029.37 19.73% $50,570.00 $9,884.66 19.55% 1000/1000
West
Piedmont PDC RiverStreet
- Dinwiddie Networks 5009 0 0.00% 06/20/2022 6/30/2026 High Risk None $6,893,337.00 SLFRF $562,354.56 8% $18,974,275.00 $1,376,023.04 7.25% 1000/1000
West
Piedmont PDC RiverStreet
(East) Networks 24641 7795 32.00% 08/03/2022 8/3/2025 None None $87,003,888.00 SLFRF $31,656,219.19 36% $65,421,341.00 $30,300,155.02 46.32% 1000/1000
West
Piedmont PDC RiverStreet FED, MR,
(West) Networks 10056 21 0.00% 09/30/2022 2/24/2026 High Risk RR $33,571,073.00 CPF $1,616,702.12 5% $59,425,085.00 $3,054,768.78 5.00% 1000/1000
West Charter
Piedmont PDC Communications 690 676 98.00% 08/01/2022 8/1/2025 None FED $1,557,385.00 CPF $217,971.68 14% $1,450,145.00 $141,702.52 9.77% 1000/500
*Data as of June 2025 Monthly Project Reports, which reflect project statistics through the end of May.
Abbreviations for Reasons for Project’s Delay: MR – Make Ready, SCL – Supply Chain and Labor, UL – Utility Locates, RR – Railroad, ROW – Right of Way Permitting along State Roads, FED – Federal Land Permitting Challenges, OTH – Other
(Described)
Q4 FY2025 Quarterly Performance Report for the Virginia Telecommunication Initiative – FY2023 Projects
Award Funding
Source - (GF,
Percent General Fund
Total Complete )(SLFRF, Percent Percent
Maximum
Passings Passings Coronavirus State Expended, Expended, Advertised
Internet Passings Provided Provided Reason and Local Fiscal Out of Out of
Recovery Fund Project Speeds
Service in Broadband Broadban for a )(CPF, Coronavirus
Awarded Total Total Available
Provider Project Access to d Access Agreement Agreement Project’s Capital Projects Funding Awarded Total Match Match Funding Match (Download/
Grantee Partner Area Date to Date Start Date End Date Risk Delay Award Amount Fund) Expended Funding Funding Expended Funding Upload Mbps)
Greensville
County Verizon 1347 1336 99% 10/3/2023 4/3/2025 None None $2,956,774.80 GF $2,463,207.18 83% $4,435,162.20 $3,091,509.69 69.70% 940/880
Southside EMPOWER
PDC Broadband 4804 1409 29% 9/26/2023 9/26/2026 None None $8,556,028.84 GF $82000 1% $21,677,288.16 $0.00 0.00% 1000/1000
West
Piedmont
PDC RiverStreet
(Pittsylvania) Networks 2102 494 24% 10/5/2023 10/5/2026 None None $3,548,250.00 GF $2,368,190.33 67% $1,856,750 $1,252,085.28 67.43 1000/1000
West
Piedmont RiverStreet
PDC (East) Networks 3356 990 29% 11/6/2023 11/6/2026 None None $8,155,864.00 GF $4,512,092 55% $5,205,136.00 $2,748,491.08 52.80% 1000/1000
Bedford Shentel 565 545 96% 4/1/2024 9/1/2025 None None $1,373,161.74 GF $260,728.16 19%5 $3,204,044.05 $608,365.72 18.99% 1000/1000
Shenandoah
County
Public
Schools Shentel 2440 1645 67% 9/26/2023 9/26/2025 None None $4,936,968.00 GF $2,301,392.94 47% $9,168,655.00 $4,274,015.31 46.62% 1000/1000
Caroline
County Breezeline 3910 275 7% 10/23/2024 10/23/2026 None MR $6,446,000.00 GF $1,606,282.28 25% $15,247,000.00 $4,221,564.77 27.69% 1000/600
Caroline
County Verizon 854 815 95% 10/23/2024 5/23/2025 None None $2,032,334.00 GF $1,743,577.73 86% $5,610,501.00 $5,345,806.41 95.28% 940/880
Chesterfield All Points
County Broadband 494 0 0% 12/1/2023 11/30/2026 None None $755,523.00 GF $0.00 0.00% $12,494,553.00 $0.00 0.00% 1000/1000
Henrico All Points
County Broadband 412 0 0% 12/1/2023 11/30/2025 None None $501,620.00 GF $0.00 0.00% $6,027,280.42 $0.00 0.00% 1000/1000
Essex
$8,753,009.00
County Breezeline 3526 440 12% 09/06/2023 9/6/2026 None MR GF $1,063,548.93 12% $19,113,941.00 $2,580,523.59 13.5% 1000/600
Floyd
County Citizens 666 654 98% 05/30/2023 8/18/2025 Low Risk None $1,339,387.00 GF $933,560.33 70% $827,173.00 $640,604.23 77.44% 1000/500
Orange
County FiberLync 576 467 81% 10/31/2023 6/5/2025 Low Risk None $2,181,000.00 GF $2,155,031.68 99% $8,391,058.00 $8,242,087.06 98.22% 1000/1000
*Data as of June 2025 Monthly Project Reports, which reflect project statistics through the end of May.
Abbreviations for Reasons for Project’s Delay: MR – Make Ready, SCL – Supply Chain and Labor, UL – Utility Locates, RR – Railroad, ROW – Right of Way Permitting along State Roads, FED – Federal Land Permitting Challenges, OTH – Other
(Described)
Q4 FY2025 Quarterly Performance Report for the Virginia Telecommunication Initiative – FY2024 Projects
Award
Funding
Source - (GF,
General Fund
)(SLFRF, Maximum
Percent Coronavirus Advertised
Total Complete State and
Project
Passings Passings Local Fiscal Percent Percent Speeds
Internet Provided Provided Reason Recovery Expended, Expended, Available
Fund )(CPF,
Service Broadband Broadband for a Awarded Out of Total Match Out of Total (Download/
Coronavirus
Provider Passings in Access to Access to Agreement Agreement Project’s Capital Funding Awarded Total Match Funding Match Upload
Grantee Partner Project Area Date Date Start Date End Date Risk Delay Award Amount Projects Fund) Expended Funding Funding Expended Funding Mbps)
Thomas
Jefferson PDC Firefly 5,825 126 2% 11/1/2024 12/31/2026 None None $12,208,500.00 GF $39,380 0.32% $36,427,182.00 $0.00 0.00% 1000/1000
West
Piedmont RiverStreet
PDC (West) Networks 4526 7 0% 2/28/2024 2/28/2026 None None $8,013,600.00 GF $49,679.11 0.62% $5,386,400.00 $17,149.89 0.32% 1000/1000
Southside
PDC Empower 3,757 1460 39% 11/13/2024 6/30/2027 None None $3,353,579.00 GF $32000 0.95% $3,153,579.00 $0.00 0.00% 1000/1000
Pending Pending
Carroll ZiTEL 2,446 0 0% contract Contract None None $10,347,072.00 GF $0.00 0.00% $7,694,453.00 $0.00 0.00% 1000/1000
Giles County PemTel 629 0 0% 1/21/2025 1/21/2027 None None $4,199,596.00 GF $0.00 0.00% $1,343,604.00 $0.00 0.00% 1000/1000
Franklin $1,774,149.9 $3,356,499.7
County ZiTEL 2,543 0 0% 1/21/2025 1/21/2026 None None $4,538,288.00 GF 0 39% $7,737,355.00 9 43.38% 1000/1000
Rockbridge
BARC BARC 293 0 0% 11/4/2024 11/4/2026 None None $1,197,320.00 GF $0.00 0.00% $1,653,443.00 $0.00 0.00% 1000/1000
Rockbridge Brightspeed 976 0 0% 4/10/2025 5/7/2027 None None $975,865.00 GF $0.00 0.00% $3,901,517.00 $0.00 0.00% 1000/1000
Alleghany 1000 /
County CBEC 370 0 0% 11/21/2024 6/13/2026 None None $2,332,353.00 GF $203,323.04 9% $1,019,580.00 $87,138.45 3.64% 1000
Orange
County FiberLync 546 13 2% 8/8/2024 8/8/2026 None None $2,138,416.00 GF $0.00 0.00% $3,155,780.00 $0.00 0.00% 1000/1000
1000 /
Botetourt Comcast 62 0 0% 12/12/2024 12/12/2026 None None $395,411.00 GF $0.00 0.00% $232,225.00 $0.00 0.00% 1000
*Data as of June 2025 Monthly Project Reports, which reflect project statistics through the end of May.
Abbreviations for Reasons for Project’s Delay: MR – Make Ready, SCL – Supply Chain and Labor, UL – Utility Locates, RR – Railroad, ROW – Right of Way Permitting along State Roads, FED – Federal Land Permitting Challenges, OTH – Other
(Described)
File and source
- File
- 2026-RD157.pdf
- Size
- 455,463 bytes
- SHA-256
- 10c9d02288671b72e3e33ce2e9c3301b96e83e676b9a7060e35d85b9d91b79d2
- Our copy
- 2026-RD157.pdf
- Original
- No public link identified.