Annual Report on Virginia Business Ready Expedited Permitting Program

Summary

The Annual Report on the Virginia Business Ready Expedited Permitting Program (EPP) for the 2025 fiscal year, administered by the Virginia Economic Development Partnership Authority (VEDP). The report states that the pilot program had a delayed effective date of January 1, 2025, allows up to two eligible sites and four economic development projects per year, and requires local and state agencies to render decisions on relevant permits within 180 days of receiving application materials. It states that two companies partnering with Virginia localities have confirmed participation, announcing nearly $10 billion in capital investment and 1,250 new jobs. Its sections cover legislative history, guidelines, program results, state partnerships and future implementation.

Summary drafted by a model from the document's text below and checked by script against that text before publication. It is a navigation aid, not a reading of what the document proves. Where AI is used

Cite this document

“Annual Report on Virginia Business Ready Expedited Permitting Program.” Archived at Pandemic Darlings, https://pandemicdarlings.com/source-documents/2025-rd962-35b10af96c/, SHA-256 2ddce26f78628305493bc4e7fe230b11cc6f1a563714c5dfc15fac7a9a37bff6.

Full text

Annual Report on Virginia Business Ready
Expedited Permitting Program

Executive Summary
 The Virginia General Assembly passed the Virginia Business Ready Expedited Permitting Program
  (“EPP”) in the 2024 Session, which had a delayed effective date of January 1, 2025.
 The pilot program allows up to two Virginia Business Ready Sites Program-eligible sites (§ 2.2-
  2240.2:1) and four economic development projects to participate in the program per year.
 The EPP requires local and state agencies to process and render decisions on relevant permits or
  requests for approval within 180 days of receiving application materials.
 The EPP has been marketed to economic development prospects since the guidelines were
  established in January 2025, with companies noting the program as a major factor separating
  Virginia from its competitors.
 Since the end of the 2025 fiscal year, two companies partnering with Virginia localities have
  confirmed participation in the program. These projects will have a lasting impact in the
  Commonwealth, announcing nearly $10 billion in capital investment and creating 1,250 new jobs,
  while citing Virginia’s favorable business climate and responsive government support as key
  decision-making factors.


Legislative History
The Virginia Economic Development Partnership Authority (“VEDP”) administers the Virginia Business
Ready Expedited Permitting Program (the “EPP”) in accordance with § 2.2-2240.2:2 of the Code of
Virginia to annually designate up to two eligible sites and four projects for participation in the EPP. The
sites or projects will align with the goals outlined in the Commonwealth’s economic development plan.
The program was established as a pilot during the 2024 General Assembly session with a delayed
effective date of January 1, 2025, and is set to expire on June 30, 2028. No projects will be eligible for
the EPP after December 31, 2027.


Background
The EPP was established to ensure that the Commonwealth keeps pace with business location and
expansion plans, while maintaining rigorous permitting standards. In recent years, economic
development projects have become more sophisticated in the site selection process, requiring sites and
communities to commit to a streamlined permitting experience in order to compete for private
investment. While communities can signal a business-friendly environment by developing sites to a
high level of readiness, many items, such as permits, can only be completed once a final user is

                                                                                                              1
               Annual Report on Virginia Business Ready Expedited Permitting Program
               2025 Fiscal Year
confirmed. These post-prospect development items require a high degree of coordination between local
and state entities to ensure users can meet critical ramp-up timelines. Therefore, a statewide program
codifying the coordination between state agencies and local partners, and committing to accelerated
permitting timelines, provides reassurance to prospects that Virginia can meet the private sector's
needs. Additionally, as economic development projects continue to target aggressive timelines,
providing reliable business support from Virginia’s regulatory agencies gives the Commonwealth a
compelling advantage over competitor proposals that cannot or will not commit to expedited permitting.

The benefit of the EPP is that it does not place the burden solely on state and local agencies, but it
represents a partnership between government and private industry. It requires both parties to move as
quickly as possible to meet permitting timelines. The EPP depends on complete state and local
cooperation and alignment to ensure that permitting timelines can meet the deadlines as outlined in §
2.2-2240.2:2.


Guidelines
VEDP created EPP guidelines in October 2024 and published them as part of the Virginia Business
Ready Sites Program guidelines on its website in January 2025.

VEDP evaluates potential sites for inclusion into the EPP using the following criteria:

1. The property meets the “eligible site” criteria as defined by § 2.2-2240.2:1, under the Virginia
   Business Ready Sites Program (VBRSP);
2. Expedited permitting reduces the total site development timeline and advances the site’s readiness;
3. Expedited permitting improves the site’s marketability and competitiveness for traded-sector
   projects; and
4. The site improves Virginia’s industrial site portfolio and increases the state’s ability to meet market
   demand.

VEDP evaluates potential projects for approval into the EPP using the following criteria:

1. The project meets the eligibility requirements of significant economic development projects; and
2. Expedited permitting improves Virginia’s ability to win the economic development project.

Once a site or project is designated for participation in EPP, VEDP will complete a review process
within 45 business days. This review process allows VEDP to assess permitting needs for the site or
project and provide guidance to the applicant and state partners. The EPP commits agencies to
complete permit application requests for a designated site or project within 180 days. The applicant
may agree to a longer timeframe with a formal memorandum of understanding between the
government agency and the applicant.

In accordance with its authorizing law, the EPP does not reduce or eliminate any legal requirements for
public comment or input related to a requested permit. However, all required reviews by staff at
Commonwealth agencies will be prioritized.


               Annual Report on Virginia Business Ready Expedited Permitting Program                         2
               2025 Fiscal Year
Expedited Permitting Program Results
VEDP offered the EPP in three tailored incentive proposals to companies considering Virginia. Two of
the projects made announcements for Virginia and one ultimately disengaged. Applications for these
two announced projects will be reflected in the FY26 report. VEDP continues to have interest in the
program and expects to fill all four project slots available for FY26.

In FY25, VEDP identified and is in the process of positioning several sites to be ready for the program
in FY26. The candidate sites for the EPP are finalizing additional development items that must be
addressed prior to program participation. Failing to complete these critical path development items may
hinder the ability of permitting agencies to make a complete assessment of the sites and will not
improve speed to market.


State Partnerships
Per § 2.2-2240.2:2.(E), all local government entities and state agencies, whether or not independent,
shall cooperate with the Authority in carrying out the provisions of this section. State agencies regularly
administering relevant permits include the Virginia Department of Environmental Quality, Virginia
Department of Transportation, Virginia Department of Historic Resources, and State Corporation
Commission. VEDP maintains working relationships with partner agencies through its site development
task force and throughout the site selection process. These collaborations ensure coordinated guidance
and faster approvals, making the Expedited Permitting Program more effective in streamlining the
Commonwealth's regulatory processes.


Future Implementation
As previously mentioned, VEDP has two projects committed for FY26 and anticipates two other
projects for EPP in the coming months. VEDP continues to identify and evaluate sites for participation
in the program by coordinating with local and state economic development partners. VEDP anticipates
consistent demand for the program in FY26 and FY27, based on ongoing project activity in Virginia’s
economic development pipeline.




               Annual Report on Virginia Business Ready Expedited Permitting Program                      3
               2025 Fiscal Year


File and source

File
2025-RD962.pdf
Size
131,074 bytes
SHA-256
2ddce26f78628305493bc4e7fe230b11cc6f1a563714c5dfc15fac7a9a37bff6
Our copy
2025-RD962.pdf
Original
No public link identified.
Back to top