Quarterly Performance Report of the Virginia Telecommunication Initiative, Q2 FY2025 (January 2025)
Summary
The Quarterly Performance Report of the Virginia Telecommunication Initiative (VATI), Q2 FY2025, submitted by the Department of Housing and Community Development in January 2025. The executive summary states that FY22, FY23, and FY24 projects will provide access to broadband infrastructure to 324,899 passings, with $818 million in state and federal funding awarded and $1.211 billion in private and local match funding leveraged. It states that 30 of the 56 open projects funded from the American Rescue Plan Act of 2021 (ARPA) and General Funds are scheduled to be completed on time, and that DHCD identifies 26 projects as at risk. The report ends with project tables, with data as of December 2024 Monthly Project Reports.
Summary drafted by a model from the document's text below and checked by script against that text before publication. It is a navigation aid, not a reading of what the document proves. Where AI is used
Cite this document
“Quarterly Performance Report of the Virginia Telecommunication Initiative, Q2 FY2025 (January 2025).”
Archived at Pandemic Darlings, https://pandemicdarlings.com/source-documents/2025-rd73-d3137196ae/
, SHA-256 981fea30dc5cda9752ed142cebac75222ffc558adb3137dad46dfe7f14a6238b.Full text
Quarterly Performance Report of the
Virginia Telecommunication Initiative
Q2 FY2025 Report
Submitted by:
The Department of Housing and Community Development
January 2025
Executive Summary
Virginia funds broadband deployment within the Commonwealth through several
programs. The largest and main program is the Virginia Telecommunication Initiative
(VATI).
VATI provides grants to localities partnered with internet service providers to
finance the deployment of high-speed broadband to locations (called a “passing”) within
the Commonwealth that are determined to be “unserved.” Passings are places where the
internet can be accessed – thus it could be a business, community anchor, a home, or an
apartment complex. A passing is unserved1 if it lacks access to internet speeds of 100
Megabits per second (Mbps) download and 20 Megabits (Mbps) upload (“100/20”).
This quarterly report is required by statute and has been prepared by the Office of
Broadband located within the Virginia Department of Housing and Community
Development (DHCD). This report tracks the technical performance of the VATI
provider partners in their work to deploy broadband. This report adheres to the factors
that the General Assembly directed to be tracked and presents them in the manner
directed by the General Assembly.
Below are the key takeaways from the report:
● Total passings: VATI FY22, FY23, and FY24 projects will provide access
to broadband infrastructure to 324,899 passings across Virginia.
● Leveraged local and private funding: In addition to $818 million in state and
federal funding awarded, FY22, FY23, and FY24 projects leverage a total of
$1.211 billion in private and local match funding. To-date, $270.9 million
of these awarded funds have been expended, with $332.7 million of these
matching funds have been expended.
● Locations Built-To: To date, FY22 and FY23 projects have provided
broadband access to 114,000 locations. The 9 FY24 projects are getting
under contract and will begin final engineering and design, as well as
construction in late 2024 through early 2025.
● Maximum Speeds Available: Over 93.4% of projects funded in FY22, FY23,
and FY24 offer functionally gigabit (1,000 Mbps) download speeds, and
over 73.7% offer functionally gigabit upload speeds.
In conclusion, 30 out of the 56 open projects funded from the American Rescue
Plan Act of 2021 (ARPA) and General Funds from FY22, FY23, and FY24 are
scheduled to being completed on time as of the time of this report’s submission. 4
projects have completed their construction activities are marked ‘closed’ under the risk
category in the tables below. 26 projects, DHCD identifies, are at risk for incompletion
1
In the FY22 VATI process, the definition of unserved was set at 25/3. This definition of unserved has been upgraded
to those passings lacking access to broadband at speeds of 100/20 for the FY23 VATI process
or underperformance. Justification for these delays include the make-ready effort, which
includes preparing existing electric poles for aerial broadband network construction, as
well as supply chain and labor markets, streamlining utility locate efforts, railroad
crossings, the permitting process to lay fiber in state-owned rights of way along roads,
and permitting to cross federally owned lands. Looking forward, DHCD will continue
its ongoing work to monitor these projects, assisting where appropriate in mitigating
these broadband deployment challenges.
Formal Report
Pursuant to Chapter 1 of the Virginia Acts of Assembly of Special Session II of 2021
and continued forward in the 2024 Special Session 1 under Chapter 2 of the Virginia Acts of
Assembly, enclosed is the Quarterly Performance Report of the Virginia Telecommunication
Initiative (VATI).
Item 103 L.6. of the 2024 Acts of Assembly Special Session I requires that DHCD deliver
a quarterly performance report on funds awarded through the 2021 Acts of Assembly Special
Session I (also known as the budget bill) of allocated ARPA funds, as well as state general funds
awarded through the Virginia Telecommunication Initiative since the aforementioned FY2022
budget cycle.
Administered by the Virginia Department of Housing and Community Development
(DHCD), VATI enhances the sustainability and growth of communities throughout the
Commonwealth by preparing those communities to build, utilize, and capitalize on broadband
infrastructure. The primary objective of VATI is to provide financial assistance to supplement
construction costs by private sector broadband service providers to extend service to areas that
presently are unserved by any broadband provider. This program requires a public-private
partnership.
The directive to form this quarterly performance report establishes that:
To the extent possible, the quarterly performance report shall contain
information by grant recipient and year on the following metrics: (1) Number of
passings; (2) Grant dollars expended by fund source (State and Local Recovery
Fund, Capital Project Fund, general fund state grants and match); (3) Contract
performance period, and on-time progress towards project delivery; (4)
Maximum advertised project speeds available; and, (5) Achievement of key
project milestones. The quarterly report shall be due within 30 days of the close
of the quarter. The quarterly performance report shall include an evaluation of
any projects under risk of incompletion or underperformance. The department in
providing such risk assessment shall include a reason for the project's delay.
In accordance with this structure, DHCD has included information in this report of the
projects that were awarded funds since December 2021, and includes the projects announced
in the FY2022, FY2023, and FY2024 cycles, including those projects funded under the
Coronavirus State and Local Fiscal Recovery Fund and Coronavirus Capital Projects Funds
allocations under the American Rescue Plan Act of 2021. Project information displayed in this
report reflects monthly report data from December 2024, which reflects project data as of the
end of November 2024.
Out of the 56 open projects funded in FY22, FY23, and FY24, 26 have requested and
received timeline extensions, and, per DHCD’s analysis, 21 are considered to be at low risk
and 5 are considered to be at high risk. DHCD has established risk definitions specific to
funding year. A summary of these definitions provided in the table below. The definition of
risk category
varies for the FY2022 funding year, as this funding year contained American Rescue Plan Act
funding, which has a statutory expenditure deadline of December 31, 2026.
Year Risk Level Risk Level Definition
• The grantee has not requested a timeline extension beyond
FY22 No Risk the originally approved contract end date; and,
• Based on the sole determination of the Office of Broadband,
the grantee is not significantly behind the current approved
milestone timeline; and,
• The timeline for that project does not have an end date in
2026.
• The grantee has requested a timeline extension beyond the
FY22 Low Risk originally approved contract end date; or,
• Based on the sole determination of the Office of Broadband,
the grantee is significantly behind the current approved
milestone timeline and has not yet requested a timeline
extension from the original completion date.
• The grantee’s contractual end date is in 2026, regardless of
FY22 High Risk if that end date reflects the original contractually established
end date or is a result of an extension.
FY23, FY24 No Risk • The grantee has not requested a timeline extension beyond
the originally approved contract end date; and,
• Based on the sole determination of the Office of Broadband,
the grantee is not significantly behind the current approved
milestone timeline.
FY23, FY24 Low Risk • The grantee has requested a timeline extension beyond the
originally approved contract end date; or,
• Based on the sole determination of the Office of Broadband,
the grantee is significantly behind the current approved
milestone timeline and has not yet requested a timeline
extension from the original completion date.
FY23, FY24 High Risk • The grantee has requested more than one timeline
extension beyond the originally approved contract end
date.
DHCD staff continue to closely monitor the continued impact of challenges surrounding
make-ready, which includes preparing existing electric poles for aerial broadband network
construction. DHCD has recently funded the first projects under the Virginia Make Ready
Initiative, which is designed to mitigate the impacts of elevated make-ready costs. DHCD is
closely monitoring the impact of this program on accelerating delivery of affected VATI
projects.
Other deployment challenges which are being monitored by DHCD include supply
chain and labor markets, streamlining utility locate efforts, railroad crossings, the permitting
process to lay fiber in state-owned rights of way along roads, and permitting to cross federally
owned lands. DHCD and its local government and internet service provider partners are
continuing to develop innovative solutions to meet these challenges and deliver high-speed
broadband access as quickly as possible for residents in these project areas.
The project summaries included in this report are updated quarterly on the VATI Project
Dashboard, accessible through dhcd.virginia.gov/vati.
Q2 FY2025 Quarterly Performance Report for the Virginia Telecommunication Initiative – FY2022 Projects
Award Funding
Percent Source
Complete, GF, General Fund
Total Passings SLFRF,
Passings
Provided Agreement End Reason for a Percent Maximum Advertised
Provided Risk Coronavirus State
Broadband Access Date Project’s Delay Expended, Percent Expended, Project Speeds
Broadband Award Amount and Local Fiscal Out of Total Out of Total Match
Passings in to Date Awarded Funding Match Funding Available (Download/
Grantee Internet Service Provider Partner Project Area Access to Agreement Start Date Recovery Fund Awarded Total Match Funding Funding
Expended Expended Upload Mbps)
Date CPF, Funding
Coronavirus
Capital Projects
Fund
Bedford ZiTEL 5,644 4,696 83% 06/15/2022 3/16/2025 Low Risk OTH $11,480,664.98 GF, SLFRF $8,423,908.42 73% $14,518,564.42 $10,625,129.96 73% 1000/1000
Bedford Shentel 3,204 1,562 48% 09/09/2022 9/31/2025 Low Risk MR, UL, RR, ROW, FED $6,191,796.33 GF, SLFRF $1,874,387.46 30% $13,911,783.67 $4,102,613.38 30% 1000/1000
Botetourt Lumos Networks 1,901 1,485 78% 11/01/2022 12/31/2024 Low Risk MR, RR $3,084,796.00 CPF $1,285,150.16 42% $4,824,937.00 $3,648,742.24 76% 1000/1000
Campbell Shentel 3,509 2,025 57% 09/21/2022 9/31/2025 Low Risk MR, RR, ROW $6,443,000.00 GF, SLFRF $77,468.58 1% $12,978,455.00 $155,881.55 1% 1000/1000
Central Shenandoah PDC MGW 2,470 1,027 42% 06/01/2022 6/1/2025 Low Risk MR, ROW, FED, OTH $7,876,800.00 SLFRF $2,908,225.71 37% $3,118,706.00 $1,256,680.68 40% 1000/50
Chesapeake Cox 279 315 100% 06/01/2022 12/01/2023 Closed None $580,435.00 SLFRF $570,435.00 98% $434,599.00 $738,609.58 170% 940/35
Commonwealth RC Kinex 11,397 7,334 64% 06/14/2022 6/14/2026 High Risk UL, OTH $15,000,000.00 GF $10,685,330.88 71% $13,426,482 $9,765,990.25 73% 200/10
Culpeper All Points Broadband 4,269 1 0% 08/03/2022 2/28/2025 Low Risk MR $8,600,000.00 GF $2,804,691.76 33% $21,914,454.00 $4,857,176.06 22% 1000/1000
Cumberland Plateau PDC Point Broadband 6,982 4,359 77% 09/06/2022 8/6/2025 Low Risk MR $23,478,429.00 CPF $6,050,829.92 26% $6,459,000.00 $1,664,605.11 26% 1000/500
West Piedmont PDC – Dinwiddie RuralBand 417 108 25.90% 07/03/2022 12/31/2026 High Risk RR, ROW $638,718.00 SLFRF $126,029.37 20% $50,570.00 $9,884.66 20% 1000/1000
0 0% 06/20/2022 6/20/2025 No Risk None
West Piedmont PDC - Dinwiddie RiverStreet Networks 5,009 $6,893,337.00 SLFRF $0 0% $18,974,275.00 $0 0% 1000/1000
Eastern Shore of Virginia Broadband Eastern Shore of Virginia 9,330 84% 06/01/2022 11/30/2024 Low Risk OTH
Broadband Authority $8,100,906.38 66% $1,521,110.98 46%
Authority 11,091 $12,310,777.25 SLFRF $3,314,856.00 200/200
Floyd Citizens 723 765 100% 06/01/2022 6/30/2024 Closed None $1,310,267.00 SLFRF $1,300,267 99% $1,111,725.00 $1,126,293.79 101% 1000/500
Franklin Shentel 3,508 1,252 36% 10/17/2022 10/17/2025 Low Risk MR, UL, RR, ROW, FED $11,832,456.00 GF, SLFRF $2,097,221.69 18% $18,646,520.00 $3,305,204.10 18% 1000/1000
Charter Communications 2,323 19% 07/08/2022 7/8/2025 No Risk None $8,539,706.83 40% $6,226,237.82 45%
Hampton Roads PDC 12,223 $21,120,053.50 SLFRF $13,839,523.00 1000/500
Hanover All Points Broadband 6,198 0 0% 08/01/2022 12/31/2025 Low Risk MR $13,970,000.00 SLFRF $3,631,562.45 26% $41,469,332.00 $6,362,226.54 15% 1000/1000
King William All Points Broadband 2,236 58 3% 08/03/2022 3/31/2025 Low Risk MR $5,400,000.00 SLFRF $1,577,320.47 29% $12,330,632.00 $2,156,898.20 17% 1000/1000
Scott County Telephone 5,022 46% 06/13/2022 12/13/2025 Low Risk MR, RR
Cooperative $10,287,330.30 46% $6,354,500.00 $2,979,580.80 47%
LENOWISCO PDC 10,982 $22,190,500.00 SLFRF, CPF 1000/1000
Loudoun All Points Broadband 8,629 0 0% 07/01/2022 10/31/2025 Low Risk MR $17,524,000.00 SLFRF $4,003,000.96 23% $42,376,126.00 $5,448,166.80 13% 1000/1000
Middlesex All Points Broadband 970 0 0% 07/22/2022 1/31/2025 Low Risk MR $2,050,000.00 SLFRF $653,676.38 32% $8,453,887.00 $1,132,991.43 13% 1000/1000
Mount Rogers PDC Point Broadband 27,450 26,390 96% 06/01/2022 5/31/2025 Low Risk MR $65,883,228.00 CPF $45,203,185.88 69% $33,082,600.00 $25,206,378.44 76% 1000/500
New River Valley Regional 342 2.80% 03/13/2023 3/13/2026 High Risk MR, RR
Commission Bland and Montgomery $5,407,430.03 14% $4,833,345.78 13%
Gigabeam 12,094 $39,233,355.00 CPF $38,247,340.00 1000/1000
New River Valley Regional 0 0% 12/06/2022 12/31/2025 Low Risk MR $5,876,181.64 20% $4,594,339.19 18%
Commission Pulaski All Points Broadband 7,872 $29,122,000.00 CPF $26,103,057.19 1000/1000
Northern Neck PDC All Points Broadband 3,411 3,411 100% 09/22/2022 3/31/2025 Low Risk MR $3,190,500.00 SLFRF $1,009,110.94 32% $20,477,692.00 $3,407,205.09 17% 1000/1000
Northern Shenandoah Valley RC All Points Broadband 32,238 0 0% 07/22/2022 6/30/2026 High Risk MR $96,873,500.00 SLFRF $23,828,164.28 25% $206,243,317.00 $35,823,220.74 17% 1000/1000
Roanoke CBEC-Bee Online 495 501 100% 09/09/2022 6/1/2024 Closed None $1,581,584.00 SLFRF $1,571,584.00 99% $1,646,138.00 $1,692,557.30 103% 300/300
Roanoke Cox 396 249 63% 09/01/2022 4/15/2025 Low Risk FED $1,535,264.00 SLFRF $0 0% $1,597,927.00 $0 0% 940/35
Roanoke B2X 520 180 35% 09/22/2022 5/24/2025 Low Risk SCL, OTH $170,609.00 GF $35,295.43 21% $177,572.00 $40,817.85 23% 25/4
Roanoke Shentel 177 0 0% 10/03/2022 5/30/2025 Low Risk MR, RR $490,000.00 SLFRF $0 0% $510,000.00 $0 0% 1000/1000
Shenandoah Shentel 4,139 2423 59% 08/01/2022 8/1/2025 Low Risk MR, UL $12,176,662.00 SLFRF $5,747,201.62 47% $20,733,235.00 $9,785,775.72 47% 1000/1000
EMPOWER Broadband 11,961 81.73% 07/22/2022 7/22/2025 No Risk None $34,952,869.33 50% $42,507,721.25 51%
Southside PDC 14,634 $69,431,635.00 SLFRF $84,677,555.00 1000/1000
Stafford Comcast 634 682 100% 09/06/2022 3/6/2024 Closed None $3,398,156.00 SLFRF $3,388,155.61 99% $2,364,383.00 $2,404,621.63 102% 1200/35
Sussex RuralBand 2,267 1,431 63% 06/13/2022 12/13/2025 No Risk None $4,896,892.00 SLFRF $1,625,776.83 33% $1,678,571.00 $557,353.06 33% 1000/1000
Thomas Jefferson PDC Firefly Broadband 36,225 15,259 42.12% 08/15/2022 8/15/2025 No Risk None $79,027,930.00 SLFRF $40,272,187.78 51% $208,969,670.00 $106,112,588.17 51% 1000/1000
Charter Communications 527 76.38% 08/01/2022 8/1/2025 No Risk None $210,629.93 14% $1,450,145.00 $431,051.56 30%
West Piedmont PDC 690 $1,557,385.00 CPF 1000/500
West Piedmont PDC (East) RiverStreet Networks 24,641 4,853 19.69% 08/03/2022 8/3/2025 No Risk None $87,003,888.00 SLFRF $19,515,003.64 22% $65,421,341.00 $18,923,372.79 29% 1000/1000
0 0.00% 09/30/2022 2/24/2026 High Risk ROW, FED
West Piedmont PDC (West) RiverStreet Networks 10,056 $33,571,073.00 CPF $1,560,374.74 5% $59,425,085.00 $2,972,993.15 5% 1000/1000
*Data as of December 2024 Monthly Project Reports, which reflect project statistics through the end of November.
Abbreviations for Reasons for Project’s Delay: MR – Make Ready, SCL – Supply Chain and Labor, UL – Utility Locates, RR – Railroad, ROW – Right of Way Permitting along State Roads, FED – Federal Land Permitting Challenges, OTH – Other (Described)
Q2 FY2025 Quarterly Performance Report for the Virginia Telecommunication Initiative – FY2023 Projects
Percent
Complet
e,
Total Passings Passings Award Funding Source
Agreemen Maximum Advertised
Provided Reason for a GF, General Fund
Provided t End Risk Percent Expended, Out Percent Expended,
Broadband Access Project’s Delay Award Amount SLFRF, Coronavirus State and Local Fiscal Project Speeds
Passings in Project Broadba Date of Total Awarded Out of Total
to Date Agreement Start Recovery Fund Match Funding Available (Download/
Grantee Internet Service Provider Partner Area nd Awarded Funding Expended Funding Total Match Funding Match Funding
Date CPF, Coronavirus Capital Projects Fund Expended Upload Mbps)
Access to
Date
Bedford County Shentel 565 37 6% 4/1/2024 9/1/2025 No Risk None $1,373,161.74 GF $0 0% $3,204,044.05 $0 0% 1000/1000
Caroline County Breezeline 3,910 93 23% 10/23/2024 10/23/2026 No Risk None $6,446,000.00 GF $333,054.47 5% $15,247,000.00 $875,320.01 6% 1000/600
Verizon 854 418 48% 10/23/2024 4/23/2025 No Risk None GF $0 0% $5,610,501.00 $0 0% 940/880
Caroline County $2,032,334.00
All Points Broadband 494 0 0% 12/1/2023 11/30/2026 No Risk None GF $0 0% $12,494,553.00 $0 0% 1000/1000
Chesterfield County $755,523.00
Essex County Breezeline 3,526 0 0% 09/06/2023 9/6/2026 No Risk None $8,753,009.00 GF $272,971.21 3% $19,113,941.00 $352,746.62 2% 1000/600
Floyd County Citizens 543 462 85% 05/30/2023 2/18/2025 No Risk None $1,339,387.00 GF $343,536.82 26% $827,173.00 $210,643.19 25% 1000/500
Greensville County Verizon 1,347 1,177 87.38% 10/3/2023 4/3/2025 No Risk None $2,956,774.80 GF $0 0% $4,435,162.20 $0 0% 940/880
All Points Broadband 412 0 0% 12/1/2023 11/30/2025 No Risk None GF $0 0% $6,027,280.42 $0 0% 1000/1000
Henrico County $501,620.00
Orange County FiberLync 576 300 52% 10/31/2023 4/21/2025 No Risk None $2,181,000.00 GF $0 0% $8,391,058.00 $0 0% 1000/1000
Shentel 2,440 234 60% 9/26/2023 9/26/2025 No Risk None GF $1,645,735.62 33% $9,168,655.00 $3,056,366.14 33% 1000/1000
Shenandoah County33% $4,936,968.00
EMPOWER Broadband 4,804 956 19.90% 9/26/2023 9/26/2026 No Risk None GF $61,000 0.7% $21,677,288.16 $0 0% 1000/1000
Southside PDC $8,556,028.84
West Piedmont PDC (Pittsylvania) RiverStreet Networks 2,102 188 8.94% 10/5/2023 10/5/2026 No Risk None $3,548,250.00 GF $953497.86 27% $1,856,750 $498,675.03 27% 1000/1000
West Piedmont PDC (East) RiverStreet Networks 3,356 717 21.36% 11/6/2023 11/6/2026 No Risk None $8,155,864.00 GF $2,118,390.09 26% $5,205,136.00 $1,372,398.61 26% 1000/1000
West Piedmont PDC (West) RiverStreet Networks 4,526 0 0% 2/28/2024 2/28/2026 No Risk None $8,013,600.00 GF $20,500 0.25% $5,386,400.00 $0 0% 1000/1000
*Data as of December 2024 Monthly Project Reports, which reflect project statistics through the end of November.
Abbreviations for Reasons for Project’s Delay: MR – Make Ready, SCL – Supply Chain and Labor, UL – Utility Locates, RR – Railroad, ROW – Right of Way Permitting along State Roads, FED – Federal Land Permitting Challenges, OTH – Other (Described)
Q2 FY2025 Quarterly Performance Report for the Virginia Telecommunication Initiative – FY2024 Projects
Percent
Complete, Award Funding Source
Total Passings Passings GF, General Fund Maximum Advertised
Provided Provided Percent Expended, Out Percent Expended, Project Speeds
Reason for a SLFRF, Coronavirus State and Local Fiscal
Passings in Project Broadband Broadband Agreement End of Total Awarded Match Funding Out of Total Available (Download/
Project’s Delay Recovery Fund Awarded Funding Expended
Grantee Internet Service Provider Partner Area Access to Date Access to Agreement Start Date Date Risk Award Amount Funding Total Match Funding Expended Match Funding Upload Mbps)
CPF, Coronavirus Capital Projects Fund
Date
Giles County PemTel 629 0 0% TBD TBD No Risk None $4,199,596.00 GF $0 0% $1,343,604.00 $0 0% 1000/1000
Franklin County ZiTEL 2,543 0 0% TBD TBD No Risk None $4,538,288.00 GF $0 0% $7,737,355.00 $0 0% 1000/1000
Thomas Jefferson PDC Firefly 5,825 0 0% TBD TBD No Risk None $12,208,500.00 GF $0 0% $36,427,182.00 $0 0% 1000/1000
Southside PDC Empower 3,983 0 0% TBD TBD No Risk None $3,353,579.00 GF $0 0% $3,153,579.00 $0 0% 1000/1000
Rockbridge County Brightspeed 1,734 0 0% TBD TBD No Risk None $975,865.00 GF $0 0% $4,938,467.00 $0 0% 1000/1000
Rockbridge County BARC 293 0 0% TBD TBD No Risk None $1,197,320.00 GF $0 0% $1,653,443.00 $0 0% 1000/1000
Orange County FiberLync 425 0 0% TBD TBD No Risk None $2,138,416.00 GF $0 0% $3,155,780.00 $0 0% 1000/1000
Alleghany County CBEC 370 0 0% TBD TBD No Risk None $2,332,353.00 GF $0 0% $1,019,580.00 $0 0% 1000 / 1000
Botetourt County Comcast 62 0 0% TBD TBD No Risk None $395,411.00 GF $0 0% $2,121,571.00 $0 0% 1000 / 1000
*Data as of December 2024 Monthly Project Reports, which reflect project statistics through the end of November.
Abbreviations for Reasons for Project’s Delay: MR – Make Ready, SCL – Supply Chain and Labor, UL – Utility Locates, RR – Railroad, ROW – Right of Way Permitting along State Roads, FED – Federal Land Permitting Challenges, OTH – Other (Described)
File and source
- File
- 2025-RD73.pdf
- Size
- 458,549 bytes
- SHA-256
- 981fea30dc5cda9752ed142cebac75222ffc558adb3137dad46dfe7f14a6238b
- Our copy
- 2025-RD73.pdf
- Original
- No public link identified.