Economic Infrastructure Subcommittee — Florida House of Representatives (November 4, 2025)

Summary

Meeting packet for the Florida House of Representatives Commerce Committee Economic Infrastructure Subcommittee, Tuesday, November 4, 2025. The agenda lists a panel discussion on the Development and Deployment of Advanced Nuclear Technologies. The packet includes a Florida Public Service Commission presentation by Cayce Hinton on its Advanced Nuclear Power Feasibility Report, which refers to House Bill 1645 and ends with recommendations. It also includes a Florida Electric Power Coordinating Group presentation by Jacob Williams and Sara Dussich on next generation nuclear, covering 2025 executive orders, federal funding opportunities, Nuclear Regulatory Commission licensing and actions by other states.

Summary drafted by a model from the document's text below and checked by script against that text before publication. It is a navigation aid, not a reading of what the document proves. Where AI is used

Cite this document

“Economic Infrastructure Subcommittee — Florida House of Representatives (November 4, 2025).” Archived at Pandemic Darlings, https://pandemicdarlings.com/source-documents/2025-11-04-3286-economic-infrastructure-subcommittee-meeting-packets-m-be87ea49d0/, SHA-256 2bd4ec809e6470a62b33ae999666ecd8427dfb6c5cd7cf2efa066d173bb750a1.

Full text

 Economic Infrastructure Subcommittee
               Tuesday, November 4, 2025
                   1:30 PM - 4:00 PM
                  Reed Hall (102 HOB)




Daniel Perez                               Chip LaMarca
Speaker                                           Chair
                    The Florida House of Representatives
                                          Commerce Committee
                               Economic Infrastructure Subcommittee
Daniel Perez                                                                                        Chip LaMarca
Speaker                                                                                                    Chair




                                           Meeting Agenda
                                        Tuesday, November 4, 2025
                                            1:30 pm – 4:00 pm
                                          Reed Hall (102 HOB)




  I.   Call to Order

 II.   Roll Call

III.   Welcome and Opening Remarks

IV.    Panel discussion on the Development and Deployment of Advanced Nuclear
       Technologies

 V.    Closing Remarks

VI.    Adjournment




                   214 House Office Building, 402 South Monroe Street, Tallahassee, Fl 32399-1300
                                                   (850) 717-4870
Public Service Commission
Advanced Nuclear Power Feasibility Report

                Presentation to the
  Florida House of Representatives
Economic Infrastructure Subcommittee




                  Cayce Hinton
        Florida Public Service Commission
                November 4, 2025
                  House Bill 1645
• Study and evaluate the technical and economic feasibility of using
  advanced nuclear power technologies, including small modular
  reactors, to meet the electrical power needs of the state

• Research means to encourage and foster the installation and use of
  such technologies at military installations in partnership with public
  utilities

• Consult with FDEP and FDEM

• Submit report by April 2025, containing findings and
  recommendations



                                                                       2
             Methodology
• Workshop

• Post-workshop comments

• Research




                           3
               Workshop
• DOE Gateway to Accelerated Innovation
  in Nuclear (GAIN), Idaho National
  Laboratory

• Electric Power Research Institute (EPRI)

• Florida Electric Power Coordinating Group

                                              4
                 Report Overview
• Chapter 2: Background of Nuclear in Florida

• Chapter 3: Economic and Technical Feasibility

• Chapter 4: Federal and State Actions

• Chapter 5: Military Applications

• Chapter 6: Findings and Recommendations


                                                  5
                    Generation by Fuel Type
                                                            ■ 20 1 5 (Actua l)   ■ 2024 (Actua l)   ■ 2034 (Projected)


      80%

            -------------------------------------------------------------------------,i'. 1%--------------------------------------------------------------------------



      60%
                                                                                                      56. 1%
"C                                                                                                   --------------------------------------------------------------------
"'0                                                                                                  •------•----------------------------------------------------------------
 .
.-l
.s                                                                                                   •------•----------------------------------------------------------------
~                                                                                                    •------•----------------------------------------------------------------
~
= 40%
-z
~
.,
                                                                                                     •------•----------------------------------------------------------------
=
.,u
..,                                                                                                  •------•-----------------------
~                                            23.2%
                                                                                                     •------•-----------------------+-------•---------------------------------
      20%




                                                                                                                                            ------ 4 .9 % --- 4.2% ____ 3.8% ----


      0%
                       Nuclear                                                                                            Renewables                Interchange & All Other




                                                                                                                                                                               6
   Advanced Nuclear Technology

• Passive safety features, Walk-away

• Versatility

• Reduced spent fuel disposal, Re-use

• Factory manufacturing

                                        7
Advanced Nuclear Technology

    Size       Operating (MW - Thermal)   Output (MW - Electric)

    Micro               <=50                     <= 50
 Small (SMR)         150<=900                  50<=300
   Medium           100<=1800                 300<=600
    Large              >1800                     >600




                                                                   8
Large: Westinghouse AP1000

        Pass Ive Containment
        Coollng Water Tank




                               Electricity




                                             9
SMR: NuScale VOYGR Power Plant




                                 10
Microreactor




               11
                 Feasibility
• Technical Feasibility?
  – Yes, technically feasible, but as of yet
    unproven


• Economic Feasibility?
  – First-of-a-Kind to Nth-of-a-Kind
  – FOAK to NOAK


                                               12
         Military Applications
• DOD Strategic Capabilities Office – Project Pele
• Defense Innovation Unit (Army)
• Eielson AFB, Alaska
• Hill AFB, Utah
• Joint Base San Antonio, Texas
• Department of Navy




                                                 13
          Recommendations
• Commission a more comprehensive study
• Ensure recovery for preliminary costs
• Enhance stakeholder engagement and
  education
• Grant funding and workforce development
• Flexibility to approve rate schedules specifically
  for entities (e.g., data centers) that pursue SMRs
  to serve their demand


                                                  14
                Update
• Executive Orders

• NRC

• DOE




                         15
Questions?




             16
Florida Electric Power Coordinating Group
F LORIDA ELECTRIC POWER
C OORDINATING
G ROUP
Economic Infrastructure Subcommittee
Panel Discussion Next Generation Nuclear

Tallahassee, Florida
November 4, 2025

Presenters: Jacob Williams, Past FCG Chair & Current Board Member
           Sara Dussich, Chair, FCG Next Generation Nuclear Work Group
                            FCG BACKGROUND
 For 52 years, FCG has operated as the umbrella organization in
 Florida representing investor-owned utilities, rural electric cooperatives, and
 municipal electric utilities on environmental, transportation, & mutual aid
 assistance issues affecting the utility industry.



FCG Members                                  FCG Associate Members
City of Lake Worth Utilities                 Homestead Energy Services
City of Lakeland (Lakeland Electric)         Kissimmee Utility Authority
City of Tallahassee                          Florida Public Utilities
Duke Energy-Florida                          PowerSouth Energy Cooperative
Florida Municipal Power Agency               Central Florida Electric
Florida Power & Light Company                Escambia River Electric
Gainesville Regional Utilities               Glades River Cooperative
Homestead Energy Services                    Okefenoke Rural Electric
JEA                                          Peace River Electric
Ocala Electric Utility                       Withlacoochee Electric
OUC
Central Florida Tourism Oversight District
Seminole Electric Cooperative, Inc.
Sumter Electric Cooperative
Tampa Electric Company
            FLORIDA GENERATION MIX
Florida Dependent on Natural gas 77%, While Keeping Costs Low;
Nuclear Could Provide Florida Strategic Supply Diversification


       FL Generation Mix (%)             Residential Rate
100%
        Renewable                         (Cents/kWh)
          Other        Solar
                               $27.00
80%                                                              $16.48
                                                        $14.15
                                        $11.44 $11.54
60%                             $9.00
         Natural
          Gas
40%

                                $3.00
          Coal
20%


 0%
         Nuclear
                                $1.00
           2010         2024              FL     US       FL      US
                                          2010                 2024
  INCREASING U.S. NUCLEAR EFFORTS
 Recent Increase in U.S. Power Demand leading to Increased U.S.
 Nuclear Efforts

­ Technology and large-scale manufacturing are driving increase in
  power consumption nationally
   ­ Population growth drives Florida power consumption growth
­ Restarting 3 retired nuclear plants nationally underway
   ­ Three Mile Island – PA
   ­ Duane Arnold – IA
   ­ Palisades – MI
­ Numerous potential new nuclear plants by utilities & big tech
  including
   ­ Tennessee Valley Authority (TVA)
   ­ Energy Northwest in Washington at existing nuclear site
   ­ Kewaunee in Wisconsin – SMR at retired nuclear site
   ­ Duke Energy in North Carolina – adjacent to former coal site
 NUCLEAR STRATEGIC SUPPLY DIVERSITY
Next Generation Nuclear as Strategic Supply Diversification
for Florida
­ In 2024, FCG formed a Next Generation Nuclear Working Group
  (NGNW) to discuss potential state, legal, and regulatory changes
  needed to move advanced nuclear projects forward
   ­ FL Legislature mandated FPSC to conduct Energy Study. The NGNW
     participated in FPSC’s workshop for study development and
     supported the Study's findings (May 2025)
­ New nuclear 8 – 12 years from coming on-line
­ Numerous new small modular reactor (SMR) technologies
­ Standard AP1000 and SMR's being considered on national level
­ Significant pre-development costs to permit site/technology
­ Numerous Federal and other State incentives for nuclear being
  considered and/or implemented
    2025 NUCLEAR EXECUTIVE ORDERS
 Nuclear Gains Additional Federal Support via Executive Orders
 Through Funding & Regulatory Changes to Speed up Permitting
EO 1: Ordering the Reform of the Nuclear Regulatory Commission
• Increase deployment of new nuclear reactors to expand nuclear capacity from 100 GW
  to 400 GW by 2050, extend use of current plants and reactivate closed/partially closed
  plants
• Directs NRC reorganization promoting faster licensing & revise NRC’s NEPA compliance
EO 2: Reinvigorating the Nuclear Industrial Base
­ Prioritizes uprates of 5 GW to existing nuclear plants, have 10 new scale nuclear
  reactors under construction by 2030, & review potential funding for new nuclear plants
­ Directs expanding the nuclear energy workforce.
EO 3: Deploying Advanced Nuclear Reactor Technologies for National Security
­ Advance nuclear reactors like Generation III+, SMRs, microreactors, and stationary &
  mobile reactors, at speed necessary to support national security needs for military,
  national security, and national lab uses
­ Sets deadline of Sept 30, 2028 for a domestic military installation.
EO 4: Reforming Nuclear Reactor Testing at the Dept of Energy
­ Significantly expedite review, approval, and deployment of advance reactors. Requires
  expedited procedures to enable qualified test reactors to safely operate at DOE facilities
  within 2 years.
    FEDERAL FUNDING OPPORTUNITIES
  Federal Government Provides Support for Nuclear through Tax Credits,
  Grants and Loans
    Federal Tax Credits                                        DOE Grants                              DOE Loans
IRS Incentives(1)                                  Gen III + SMR Pathway to                  DOE Loan Program Office (LPO)
IRC Sec:                                           Deployment Program(2)                     can provide loan to support
­ 30% ITC (48E) is a technology-neutral            ­ $800 MM for up to two projects          Advanced Nuclear projects
  ITC for the COD year of the facility               focused on first mover support          ­ LPO originally allocated $250 B for
­ $30.0/MWh(1) PTC (45Y) is a technology-          ­ $100 MM used for fast follower            Energy Dominance financing
  neutral, emissions-based PTC for
  facilities placed in service after 2025            support spread out across multiple         ­ ~$60 B remaining
                                                     awards
$15/MWh PTC (45U) for electricity                                                            ­ Funds must be committed by
generated and sold by existing                                                                 September 2028 and used by
nuclear facilities from 2024 through               Low Enriched Uranium (LEU)                  September 2033
2032; credit offset when gross                     Enrichment Acquisition Program
receipts exceed $26/MWh (2025                      ­ Up to $3.4 B focused on securing a
rate) and worthless when gross                                                               LPO has recently provided support
receipts ~$45/MWh                                    non-Russian supply chain                to two nuclear projects
                                                       ­ $2.7 B has already been             ­ $12 B in loan guarantees for Vogtle
$18/MWh advanced nuclear tax                             appropriated to DOE who will then
credit under Section 45J for new                         sell the LEU to operating U.S.      ­ $1.5 B loan guarantee for Palisades
nuclear generation facilities with pre-                                                        restoration
1994 reactor design; taxpayer must                       facilities
be allocated portion of national
capacity limitation
45X manufacturer credit may be of
interest to certain equipment and
component manufacturers


 1) Many of the tax credit programs cannot be stacked
 2) Program is focused on project teams made up of developers, suppliers, customers, etc.
NRC BACKGROUND AND STRATEGIES
NRC Current Licensing Processes Based on Legacy Nuclear
Technology, Namely Large-scale Light Water Reactors

NRC licensing experience for commercial reactors is based on large-scale light
water reactors (LWRs)
­ Light water reactors require large security and emergency planning areas; licensing
  processes are lengthy due to extended NRC reviews (environmental reviews typically
  take three years)
­ Current licensing processes require each proposed reactor to be treated as a unique
  license since there are no standard reactor designs
NuScale, a LWR, is the only standard design approved by the NRC
­ Design approval means the NRC will not revisit the technical plant design aspects but
  will review site specific details
NRC has also proposed alternative security, physical and emergency
preparedness requirements for SMRs
­ Updated requirements specific to SMRs would facilitate development of new
  advanced reactor projects
       PERMITTING PROCESS OVERVIEW
 Recent Interest in SMR Technology Spurred Industry’s Push for
 Accelerated Permitting Processes
Two current NRC licensing pathways:
     1) Part 50 is a two-step process with a construction permit followed by an operating license
     2) Part 52 is a combined construction and licensing process that references an approved
         reactor design
 ­ These are traditional, prescriptive and lengthy licensing processes
Third proposed NRC licensing pathway for SMRs:
      3) Part 53 is a proposed risk-informed licensing process specifically designed for advanced
          reactor design(1)
 ­ Intended to be more streamlined and efficient than the Standard Review Plan and can be
   completed within two years
 ­ Part 53 pathway rulemaking in progress, including on-going feedback; NRC needs to provide
   additional clarity on site specific requirements (e.g., security) and sequence of licensing steps
There is some risk that limited NRC resources could adversely impact permitting
timelines for select later applicants

NRC’s forecast final rule on Part 53 originally expected by end of 2025, now extended to
                                        May 2026.
   1) Source: https://www.nrc.gov/reactors/new-reactors/advanced/rulemaking-and-guidance/part-53.html
SMR STATE LEGISLATION AND POLICY
More States Embracing Pro-SMR Policies Paving Way for Broad Adoption



                                         MT         ND
                                                                MN

                                                    SD

                                              WY

                                                    NE                              OH
                                                                          IL   IN

                                               co
                                                         KS


                                                         ()I(

                                              NM




                HI




        States that have adopted                                 States with nuclear restrictions
        pro-SMR policies or incentives                    D      or anti-SMR policies
                                                                     States that have not taken any
     States that have taken incremental steps /                      noteworthy action
     are in a pro-SMR policy traj ectory
FPSC’S 2025 FLORIDA ENERGY STUDY
FCG Supports FPSC’s 2025 FL Energy Study Findings & Recommendations

FCG remains supportive of recommendations and conclusions
contained in the FPSC’s Energy Study (May 2025) including:
• Commissioning an expanded Study to focus on economic
 benefits of advanced nuclear technologies, including site
 selection and workforce development
• Cost Recovery for initial site evaluations to mitigate financial risks
 of early phases of project development
• Emphasis on safety benefits of advanced reactors and
 advocating for enhanced public education to build confidence in
 new technologies
FCG appreciates the opportunity to provide this update on the
industry’s perspective of next generation nuclear for Florida
APPENDIX
REGULATORY AND INCENTIVE SUMMARY
 Support for nuclear is widespread, but many of the incentives available today are
 focused on first movers and technology development, not deployment


At federal level, nuclear is seeing support through government funding efforts
as well as regulatory changes to speed up permitting
­ Government funding is currently offered through tax credits, grants and loans
­ NRC rule changes regarding permitting are progressing with final action on Part 53
  expected by May 2026

Many states created working groups to discuss opportunities and regulations
for new nuclear
­ Illinois and others undertaking studies to understand impact of new nuclear on state
­ Idaho convened group to establish “Advanced Nuclear Energy Strategic Framework”
   ­ Mission to promote economic development opportunities around new technology

    While there are many initiatives to support new nuclear at federal level,
   many programs will not have significant impact on projects for several years
        RECENT STATE LEVEL ACTIONS
A handful of states have adopted pro-SMR incentives and policies


Alaska
­ In 2022, Senate Bill 177 was enacted, which makes it easier to obtain
  permits for microreactors in Alaska
Iowa
 ­ In April 2024, Iowa enacted HF 2279 to allow for advanced ratemaking for
   utilities with nuclear facilities
 ­ While there are no direct incentives for SMRs in Iowa, state policymakers and
   the state’s economic development leadership remain interested in nuclear
Illinois
 ­ In 2023, HB 2473 was enacted, which started the process for the creation of
   a regulatory structure for the construction of SMRs, and requires the state to
   perform a study that will inform rules for regulating SMRs, which is set to be
   adopted by state regulators by January 2026
          RECENT STATE LEVEL ACTION
                (CONTINUED)
A handful of states have adopted pro-SMR incentives and policies


Idaho
 ­ In 2023, House Bill 93 was enacted, shifting the existing “renewable energy”
   definition to a “clean energy” definition inclusive of nuclear generation
Tennessee
­ Governor Bill Lee stated his support for SMRs, and partnered with the state’s
  General Assembly to create a $50 MM nuclear fund in the states 2023-2024
  budget, to help support nuclear development and manufacturing
Virginia
­ In 2023, the commonwealth enacted the Virginia Power Innovation Fund, which
  provides $10 MM in support to the development of advanced energy technology,
  including SMRs
   ­ Additional background: There is a significant interest in SMRs especially given
     the large number of data centers within the commonwealth, and the governor
     has publicly stated his desire for an operational SMR by 2032
        RECENT STATE LEVEL ACTIONS
               (CONTINUED)
A handful of states have adopted pro-SMR incentives and policies

Texas
­ Governor directed PUC to sponsor the Advanced Nuclear Task Force in 2023
  ­ Advanced Nuclear Task Force directed to study and plan for SMRs; expected to file a report
    in December 2024
  ­ Dow and X-Energy announced they are planning to develop a SMR in TX in May 2023

Wyoming
­ In 2020, Wyoming enacted legislation to authorize the permitting and operation of SMRs,
  including allowing the operation on previously existing coal or natural gas generation facilities
   ­ The state took these actions to pave the way for the Terrapower project in southwest
     Wyoming
­ In 2022, Governor Mark Gordon signed House Enrolled Act 59 to further set the regulatory
  framework for the Terrapower project
   ­ SMRs are currently subject to a generation tax of $5 per MWh, but the 2022 law set a tax
     exemption if 80% of an advanced nuclear reactor’s uranium used for producing electricity is
     sourced from uranium mines located in the U.S. beginning July 1, 2035
      FEDERAL LEGISLATIVE UPDATE
The bipartisan ADVANCE Act, passed in 2024 aimed to modernize
licensing new reactor technologies

Congress passed bipartisan (Accelerating Deployment of Versatile, Advanced
Nuclear for Clean Energy) ADVANCE Act in early 2024; legislation creates new
authority for the NRC to prioritize and streamline permitting for new nuclear
­ Reduces cost of NRC permitting of advanced reactor designs
­ Requires NRC to issue a combined license not later than 25 months after date of
  which Commission accepts an application
­ Incorporates efficient process for National Environmental Review Act (NEPA) by
  consolidating reviews and increasing funding for increased agency workload
   ­ NRC must consider existing site-specific environmental data and previously
     approved environmental reviews which would allow for existing environmental
     review documents to be utilized for new applications
­ Requires the NRC to speed up permitting when using site locations that have
  retired or retiring fossil generation or at a brownfield site; rulemaking to follow
­ NRC must complete rulemakings for several of the recently passed provisions,
  which will take two to three years for full implementation


File and source

File
2025-11-04_3286_economic-infrastructure-subcommittee_meeting-packets_mtg14859.pdf
Size
1,424,884 bytes
SHA-256
2bd4ec809e6470a62b33ae999666ecd8427dfb6c5cd7cf2efa066d173bb750a1
Our copy
2025-11-04_3286_economic-infrastructure-subcommittee_meeting-packets_mtg14859.pdf
Original
No public link identified.
Back to top