Virginia Telecommunication Initiative (VATI) Quarterly Report: Technical Performance of VATI Provider Partners

Summary

Quarterly report on broadband deployment prepared by the Office of Broadband within the Virginia Department of Housing and Community Development (DHCD), tracking the technical performance of Virginia Telecommunication Initiative (VATI) provider partners. Its key takeaways state that VATI FY22, FY23, and FY24 projects will provide access to broadband infrastructure to 334,873 passings across Virginia, with $828.4 million in state and federal funding awarded and $1.228 billion in private and local match funding leveraged. It states that 32 out of the 61 projects funded from ARPA and General Funds are scheduled to be completed on time, and that DHCD identifies 29 projects at risk for incompletion or underperformance. Project tables carry data as of September 2024 Monthly Project Reports.

Summary drafted by a model from the document's text below and checked by script against that text before publication. It is a navigation aid, not a reading of what the document proves. Where AI is used

Cite this document

“Virginia Telecommunication Initiative (VATI) Quarterly Report: Technical Performance of VATI Provider Partners.” Archived at Pandemic Darlings, https://pandemicdarlings.com/source-documents/2024-rd738-8d6ec09dad/, SHA-256 d858cab4c85a78f4a9f9f2b6c8150d780f889d4a81932c6d26a8bc7fb4750282.

Full text

                                                 Executive Summary

          Virginia funds broadband deployment within the Commonwealth through several programs.
    The largest and main program is the Virginia Telecommunication Initiative (VATI).

           VATI provides grants to localities partnered with internet service providers to finance the
    deployment of high-speed broadband to locations (called a “passing”) within the Commonwealth
    that are determined to be “unserved.” Passings are places where the internet can be accessed – thus
    it could be a business, community anchor, a home, or an apartment complex. A passing is
    unserved1 if it lacks access to internet speeds of 100 Megabits per second (Mbps) download and
    20 Megabits (Mbps) upload (“100/20”).

           This quarterly report is required by statute and has been prepared by the Office of Broadband
    located within the Virginia Department of Housing and Community Development (DHCD). This
    report tracks the technical performance of the VATI provider partners in their work to deploy
    broadband. This report adheres to the factors that the General Assembly directed to be tracked and
    presents them in the manner directed by the General Assembly.

          Below are the key takeaways from the report:

            ● Total passings: VATI FY22, FY23, and FY24 projects will provide access to
              broadband infrastructure to 334,873 passings across Virginia.
            ● Leveraged local and private funding: In addition to $828.4 million in state and federal
              funding awarded, FY22, FY23, and FY24 projects leverage a total of $1.228 billion in
              private and local match funding. To-date, $237 million of these awarded funds have
              been expended, with $297.7 million of these matching funds have been expended.
            ● Locations Built-To: To date, FY22 and FY23 projects have provided broadband access
              to 106,000 locations. The 10 FY24 projects are getting under contract and will begin
              final engineering and design, as well as construction in late 2024 through early 2025.
            ● Maximum Speeds Available: Over 93.4% of projects funded in FY22, FY23, and FY24
              offer functionally gigabit (1,000 Mbps) download speeds, and over 73.7% offer
              functionally gigabit upload speeds.

          In conclusion, 32 out of the 61 projects funded from the American Rescue Plan Act of 2021
    (ARPA) and General Funds from FY22, FY23, and FY24 are scheduled to being completed on
    time as of the time of this report’s submission. 29 projects, DHCD identifies, are at risk for
    incompletion or underperformance. Justification for these delays include the make-ready effort,
    which includes preparing existing electric poles for aerial broadband network construction, as well
    as supply chain and labor markets, streamlining utility locate efforts, railroad crossings, the
    permitting process to lay fiber in state-owned rights of way along roads, and permitting to cross
    federally owned lands. Looking forward, DHCD will continue its ongoing work to monitor these
    projects, assisting where appropriate in mitigating these broadband deployment challenges.




1
  In the FY22 VATI process, the definition of unserved was set at 25/3. This definition of unserved has been upgraded to
those passings lacking access to broadband at speeds of 100/20 for the FY23 VATI process.
                                        Formal Report

        Pursuant to Chapter 1 of the Virginia Acts of Assembly of Special Session II of 2021
and continued forward in the 2024 Special Session 1 under Chapter 2 of the Virginia Acts of
Assembly, enclosed is the Quarterly Performance Report of the Virginia Telecommunication
Initiative (VATI).

      Item 103 L.6. of the 2024 Acts of Assembly Special Session I requires that DHCD deliver
a quarterly performance report on funds awarded through the 2021 Acts of Assembly Special
Session I (also known as the budget bill) of allocated ARPA funds, as well as state general funds
awarded through the Virginia Telecommunication Initiative since the aforementioned FY2022
budget cycle.
       Administered by the Virginia Department of Housing and Community Development
(DHCD), VATI enhances the sustainability and growth of communities throughout the
Commonwealth by preparing those communities to build, utilize, and capitalize on broadband
infrastructure. The primary objective of VATI is to provide financial assistance to supplement
construction costs by private sector broadband service providers to extend service to areas that
presently are unserved by any broadband provider. This program requires a public-private
partnership.

      The directive to form this quarterly performance report establishes that:
             To the extent possible, the quarterly performance report shall contain
             information by grant recipient and year on the following metrics: (1) Number of
             passings; (2) Grant dollars expended by fund source (State and Local Recovery
             Fund, Capital Project Fund, general fund state grants and match); (3) Contract
             performance period, and on-time progress towards project delivery; (4)
             Maximum advertised project speeds available; and, (5) Achievement of key
             project milestones. The quarterly report shall be due within 30 days of the close
             of the quarter. The quarterly performance report shall include an evaluation of
             any projects under risk of incompletion or underperformance. The department in
             providing such risk assessment shall include a reason for the project's delay.
       In accordance with this structure, DHCD has included information in this report of the
projects that were awarded funds since December 2021, and includes the projects announced
in the FY2022, FY2023, and FY2024 cycles, including those projects funded under the
Coronavirus State and Local Fiscal Recovery Fund and Coronavirus Capital Projects Funds
allocations under the American Rescue Plan Act of 2021. Project information displayed in this
report reflects monthly report data from September 2024, which reflects project data as of the
end of August 2024.
       Out of the 61 projects funded in FY22, FY23, and FY24, 29 have requested and received
timeline extensions, and, per DHCD’s analysis, 25 are considered to be at low risk and 4 are
considered to be at high risk. DHCD has established risk definitions specific to funding year.
A summary of these definitions provided in the table below. The definition of risk category
varies for the FY2022 funding year, as this funding year contained American Rescue Plan Act
funding, which has a Congressional expenditure deadline of December 31, 2026.


 Year              Risk Level        Risk Level Definition
                                         •   The grantee has not requested a timeline extension beyond
 FY22              No Risk                   the originally approved contract end date; and,
                                         •   Based on the sole determination of the Office of Broadband,
                                             the grantee is not significantly behind the current approved
                                             milestone timeline; and,
                                         •   The timeline for that project does not have an end date in
                                             2026.
                                         •   The grantee has requested a timeline extension beyond the
 FY22              Low Risk                  originally approved contract end date; or,
                                         •   Based on the sole determination of the Office of Broadband,
                                             the grantee is significantly behind the current approved
                                             milestone timeline and has not yet requested a timeline
                                             extension from the original completion date.
                                         •   The grantee’s contractual end date is in 2026, regardless of
 FY22              High Risk                 if that end date reflects the original contractually established
                                             end date or is a result of an extension.
 FY23, FY24        No Risk               •   The grantee has not requested a timeline extension beyond
                                             the originally approved contract end date; and,
                                         •   Based on the sole determination of the Office of Broadband,
                                             the grantee is not significantly behind the current approved
                                             milestone timeline.

 FY23, FY24        Low Risk              •   The grantee has requested a timeline extension beyond the
                                             originally approved contract end date; or,
                                         •   Based on the sole determination of the Office of Broadband,
                                             the grantee is significantly behind the current approved
                                             milestone timeline and has not yet requested a timeline
                                             extension from the original completion date.

 FY23, FY24        High Risk             •   The grantee has requested more than one timeline
                                             extension beyond the originally approved contract end
                                             date.

        DHCD staff continue to closely monitor the continued impact of challenges surrounding
make-ready, which includes preparing existing electric poles for aerial broadband network
construction. DHCD has recently funded the first projects under the Virginia Make Ready
Initiative, which is designed to mitigate the impacts of elevated make-ready costs. DHCD is
closely monitoring the impact of this program on accelerating delivery of affected VATI
projects.
      Other deployment challenges which are being monitored by DHCD include supply
chain and labor markets, streamlining utility locate efforts, railroad crossings, the permitting
process to lay fiber in state-owned rights of way along roads, and permitting to cross federally
owned lands. DHCD and its local government and internet service provider partners are
continuing to develop innovative solutions to meet these challenges and deliver high-speed
broadband access as quickly as possible for residents in these project areas.
     The project summaries included in this report are updated quarterly on the VATI Project
Dashboard, accessible through dhcd.virginia.gov/vati.
                                                                                                                                   Q3 2024 Quarterly Performance Report for the Virginia Telecommunication Initiative – FY2022 Projects
                                                                                                                  Percent
                                                                                                                Complete,                                                                                                     Award Funding Source
                                                                                               Total Passings                                                                                                                                                                                                                                                                  Maximum Advertised
                                                                                                                 Passings                                                                                                       GF, General Fund                                            Percent Expended, Out                                          Percent Expended,
                                                                                                 Provided                                                                       Reason for a                                                                                                                                                                                      Project Speeds
                                                                         Passings in Project                     Provided                                                                                            SLFRF, Coronavirus State and Local Fiscal                                of Total Awarded                                                Out of Total
                                                                                                Broadband                                         Agreement End                Project’s Delay                                                                   Awarded Funding Expended                                                 Match Funding                        Available (Download/
              Grantee                  Internet Service Provider Partner        Area                            Broadband    Agreement Start Date                  Risk                             Award Amount                 Recovery Fund                                                     Funding          Total Match Funding                      Match Funding
                                                                                               Access to Date                                          Date                                                                                                                                                                                Expended                               Upload Mbps)
                                                                                                                 Access to                                                                                             CPF, Coronavirus Capital Projects Fund
                                                                                                                   Date
              Bedford                                ZiTEL                      5,644              4,114            73%          06/15/2022        3/15/2025      Low Risk          None            $11,480,664.98                   GF, SLFRF                         $6,217,592.17                 54%               $14,518,564.42      $8,273,635.69         57%                1000/1000
              Bedford                               Shentel                     3,204              1,239            39%          09/09/2022        3/15/2025      Low Risk          None             $6,191,796.33                   GF, SLFRF                          $375,607.14                   6%               $13,911,783.67       $822,119.70          6%                 1000/1000
             Botetourt                          Lumos Networks                  1,901              1,193           63%           11/01/2022        12/31/2024     Low Risk          None            $3,084,796.00                       CPF                            $1,285,150.16                 42%               $4,824,937.00       $3,648,742.24         76%                1000/1000

             Campbell                               Shentel                     3,509              1,050           30%           09/21/2022        12/31/2024     Low Risk          None            $6,443,000.00                    GF, SLFRF                          $77,468.58                   1%                $12,978,455.00      $155,881.55            1%                1000/1000
      Central Shenandoah PDC                         MGW                        2,470              1,026           42%           06/01/2022         6/1/2025      Low Risk        ROW, SCL          $7,876,800.00                      SLFRF                           $2,908,225.71                 37%               $3,118,706.00       $1,256,680.68         40%                 1000/50

           Chesapeake                                  Cox                       279                315            100%          06/01/2022         3/31/2024      No Risk          None              $580,435.00                      SLFRF                            $570,435.00                  98%                 $434,599.00        $738,609.58          170%                 940/35
        Commonwealth RC                               Kinex                    11,397              7,334            62%          06/14/2022         6/14/2026     High Risk         None            $15,000,000.00                      GF                             $9,922,095.03                 66%                 $13,426,482       $9,247,108.43          69%                 200/10
            Culpeper                          All Points Broadband              4,269                0              0%           08/03/2022         2/28/2025     Low Risk           MR              $8,600,000.00                      GF                             $2,804,691.76                 33%               $21,914,454.00      $4,857,176.06          22%               1000/1000
    Cumberland Plateau PDC                      Point Broadband                 6,982              4,359            62%          09/06/2022         9/6/2025      Low Risk           MR             $23,478,429.00                      CPF                            $5,889,734.30                 25%                $6,459,000.00      $1,620,287.13          25%                1000/500
  West Piedmont PDC - Dinwiddie                     RuralBand                    417                 0              0%           07/03/2022        12/31/2026     High Risk         None              $638,718.00                      SLFRF                                $0                        0%                 $50,570.00             $0                0%                1000/1000

  West Piedmont PDC - Dinwiddie              RiverStreet Networks               5,009                0              0%           06/20/2022        6/20/2025      No Risk           None            $6,893,337.00                      SLFRF                                $0                       0%                $18,974,275.00           $0                0%                1000/1000


                                            Eastern Shore of Virginia
 Eastern Shore of Virginia Broadband                                                               9,330                         06/01/2022        12/31/2024     Low Risk          None                                                                               $7,329,784.96                 60%                                   $1,521,110.98         46%
                                              Broadband Authority
              Authority                                                        11,091                              84%                                                                              $12,310,777.25                     SLFRF                                                                           $3,314,856.00                                                 200/200
               Floyd                                Citizens                     723                765            100%          06/01/2022        6/30/2024      Low Risk          None            $1,310,267.00                      SLFRF                           $1,179,240.30                 90%               $1,111,725.00       $1,126,293.79         101%               1000/500

              Franklin                              Shentel                     3,508              1,178           34%           10/17/2022        10/17/2025     Low Risk    MR, SCL, RR, ROW      $11,832,456.00                   GF, SLFRF                          $746,783.09                  6%                $18,646,520.00      $1,176,923.99          6%                1000/1000

                                            Charter Communications                                 2,368                         07/08/2022        07/08/2025     No Risk           None                                                                               $6,217,729.01                 29%                                   $4,640,580.19         34%
        Hampton Roads PDC                                                      12,223                              19%                                                                              $21,120,053.50                     SLFRF                                                                           $13,839,523.00                                                1000/500
             Hanover                          All Points Broadband              6,198                0             0%            08/01/2022        12/31/2025     Low Risk           MR             $13,970,000.00                     SLFRF                           $3,631,562.45                 26%               $41,469,332.00     $6,362,226.54          15%                1000/1000
           King William                       All Points Broadband              2,236                0             0%            08/03/2022         3/31/2025     Low Risk           MR              $5,400,000.00                     SLFRF                           $1,577,320.47                 29%               $12,330,632.00     $2,156,898.20          17%                1000/1000

                                            Scott County Telephone
                                                                                                   4,877                         06/13/2022        12/13/2024     Low Risk          MR, RR                                                                             $10,065,435.07                45%                                   $2,921,668.79         46%
                                                  Cooperative                                                                                                                                                                                                                                                          $6,354,500.00
          LENOWISCO PDC                                                        10,982                              44%                                                                              $22,190,500.00                  SLFRF, CPF                                                                                                                                      1000/1000
                                                                                                                                                                                                                                                                                                                                           $5,448,166.80
              Loudoun                         All Points Broadband              8,629                0              0%           07/01/2022        10/31/2025     Low Risk           MR             $17,524,000.00                     SLFRF                           $4,003,000.96                 23%               $42,376,126.00                            13%                1000/1000
                                                                                                                                                                                                                                                                                                                                           $1,132,991.43
             Middlesex                        All Points Broadband               970                 0              0%           07/22/2022        1/31/2025      Low Risk           MR             $2,050,000.00                      SLFRF                            $653,676.38                  32%               $8,453,887.00                             13%                1000/1000
         Mount Rogers PDC                       Point Broadband                27,450              26,390          96%           06/01/2022        5/31/2025      Low Risk           MR             $65,883,228.00                      CPF                            $45,203,185.88                695               $33,082,600.00     $25,206,378.44         76%                1000/500

    New River Valley Regional
                                                                                                    200                          03/13/2023        3/13/2026      High Risk          MR                                                                                $3,452,307.84                 9%                                    $2,717,018.24          7%
 Commission Bland and Montgomery
                                                   Gigabeam                    12,094                               2%                                                                              $39,233,355.00                      CPF                                                                            $38,247,340.00                                               1000/1000
     New River Valley Regional
                                                                                                     0                           12/06/2022        12/06/2024     Low Risk           MR                                                                                 $35,531.25                  0.12%                                       $0                0%
       Commission Pulaski                     All Points Broadband              7,872                               0%                                                                              $29,122,000.00                      CPF                                                                            $26,103,057.19                                               1000/1000
                                                                                                                                                                                                                                                                                                                                           $3,407,205.09
         Northern Neck PDC                    All Points Broadband              3,411              2,234           65%           09/22/2022        9/30/2024      Low Risk           MR             $3,190,500.00                      SLFRF                           $1,009,110.94                 32%               $20,477,692.00                            17%                1000/1000

  Northern Shenandoah Valley RC               All Points Broadband             41,690                0              0%           07/22/2022        7/22/2025      Low Risk           MR             $96,873,500.00                     SLFRF                           $2,3828,164.28                25%              $206,243,317.00     $35,823,220.74         17%                1000/1000
              Roanoke                           CBEC-Bee Online                  495                501            100%          09/09/2022         6/1/2024       No Risk           None           $1,581,584.00                      SLFRF                           $1,571,584.00                 99%               $1,646,138.00       $1,692,557.30         103%                300/300
              Roanoke                                Cox                         396                249             63%          09/01/2022        10/15/2024     Low Risk            FED           $1,535,264.00                      SLFRF                                $0                        0%               $1,597,927.00            $0                0%                 940/35
                                                                                                                                                                               SCL, OTH (Private
              Roanoke                                 B2X                        520                180            35%           09/22/2022        10/24/2024     Low Risk                           $170,609.00                        GF                              $35,295.43                   21%                $177,572.00         $40,817.85           23%                   25/4
                                                                                                                                                                                 Easements)
              Roanoke                               Shentel                      177                 0             0%            10/03/2022        5/30/2025      Low Risk       MR, RR, ROW         $490,000.00                       SLFRF                                $0                        0%                $510,000.00             $0               0%                 1000/1000
            Shenandoah                              Shentel                     4,139              1,605           39%           08/01/2022        8/1/2025       Low Risk         ROW, MR          $12,176,662.00                     SLFRF                           $4,977,448.05                 41%               $20,733,235.00      $8,475,114.22         41%                1000/1000

                                             EMPOWER Broadband                                     11,864                        07/22/2022        07/22/2025     No Risk           None                                                                               $31,457,093.67                45%                                  $3,824,3728.53         55%
          Southside PDC                                                        14,634                               81%                                                                             $69,431,635.00                     SLFRF                                                                           $84,677,555.00                                               1000/1000
             Stafford                               Comcast                      634                 682           100%          09/06/2022         9/6/2024       No Risk          None             $3,398,156.00                     SLFRF                           $3,058,340.05                 90%                $2,364,383.00      $2,404,621.63         102%                1200/35
              Sussex                               RuralBand                    2,267               1,044           46%          06/13/2022        12/13/2025     Low Risk          None             $4,896,892.00                     SLFRF                           $1,625,776.83                 33%                $1,678,571.00       $557,353.06           33%               1000/1000
       Thomas Jefferson PDC                    Firefly Broadband               36,225              13,949           39%          08/15/2022        08/15/2025      No Risk          None            $79,027,930.00                     SLFRF                           $35,191,537.59                45%              $208,969,670.00     $97,472,695.02          46%               1000/1000

                                            Charter Communications                                  434                          08/01/2022        08/01/2025     No Risk         MR, ROW                                                                               $187,146.52                  13%               $1,450,145.00       $141,702.52           10%
        West Piedmont PDC                                                        690                               63%                                                                              $1,557,385.00                       CPF                                                                                                                                         1000/500
     West Piedmont PDC (East)                RiverStreet Networks              24,641              3,878           16%           08/03/2022        08/03/2025     No Risk           None            $87,003,888.00                     SLFRF                           $16,315,896.72                19%               $65,421,341.00     $14,390,426.36         22%                1000/1000
                                                                                                                                                                              OTH (Delayed APCO
     West Piedmont PDC (West)                RiverStreet Networks              10,056                0              0%           09/30/2022        02/24/2026     High Risk   SCC Application and   $33,571,073.00                      CPF                             $515,300.35                  2%                $59,425,085.00      $4,231,782.77          7%                1000/1000
                                                                                                                                                                                   Approval)
*Data as of September 2024 Monthly Project Reports, which reflect project statistics through the end of August.

Abbreviations for Reasons for Project’s Delay: MR – Make Ready, SCL – Supply Chain and Labor, UL – Utility Locates, RR – Railroad, ROW – Right of Way Permitting along State Roads, FED – Federal Land Permitting Challenges, OTH – Other (Described)
                                                                                                                                 Q3 2024 Quarterly Performance Report for the Virginia Telecommunication Initiative – FY2023 Projects
                                                                                                                Percent
                                                                                                              Complete,                                                                                                     Award Funding Source
                                                                                             Total Passings                                                                                                                                                                                                                                                                  Maximum Advertised
                                                                                                               Passings                                                                                                       GF, General Fund                                            Percent Expended, Out                                          Percent Expended,
                                                                                               Provided                                                                        Reason for a                                                                                                                                                                                     Project Speeds
                                                                       Passings in Project                     Provided                                                                                            SLFRF, Coronavirus State and Local Fiscal                                of Total Awarded                                                Out of Total
                                                                                              Broadband                                         Agreement End                 Project’s Delay                                                                  Awarded Funding Expended                                                 Match Funding                        Available (Download/
             Grantee                 Internet Service Provider Partner        Area                            Broadband    Agreement Start Date                    Risk                           Award Amount                 Recovery Fund                                                     Funding          Total Match Funding                      Match Funding
                                                                                             Access to Date                                          Date                                                                                                                                                                                Expended                               Upload Mbps)
                                                                                                               Access to                                                                                             CPF, Coronavirus Capital Projects Fund
                                                                                                                 Date
          Bedford County                          Shentel                      565                  0             0%             4/1/2024            9/1/2025     No Risk          None           $1,373,161.74                       GF                                  $0                       0%                 $3,204,044.05          $0                 0%                1000/1000
          Caroline County                        Breezeline                   3,910                89             8%            10/23/2024          10/23/2026    No Risk          None           $6,446,000.00                       GF                              $333,054.47                  5%                $15,247,000.00      $875,320.01            6%                 1000/600
                                                  Verizon                      854                                                                                                 None                                               GF                                                                              $5,610,501.00                                                 940/880
                                                                                                  389            45%            10/23/2024          4/23/2025     No Risk                                                                                                 $0                       0%                                         $0                0%
          Caroline County                                                                                                                                                                         $2,032,334.00
                                            All Points Broadband               494                                              12/1/2023           11/30/2026                     None                                               GF                                                                             $12,494,553.00                                               1000/1000
                                                                                                   0              0%                                              No Risk                                                                                                 $0                       0%                                         0                 0%
        Chesterfield County                                                                                                                                                                        $755,523.00
           Essex County                           Breezeline                  3,526                0             0%             09/06/2023          09/06/2026    Low Risk   OTH (Design Delay)   $8,753,009.00                       GF                              $145,382.62                   2%               $19,113,941.00      $352,746.62           2%                  1000/600
           Floyd County                            Citizens                    543                370            68%            05/30/2023          02/18/2025     No Risk         None           $1,339,387.00                       GF                              $343,536.82                  26%                 $827,173.00       $210,643.19           25%                 1000/500
        Greensville County                         Verizon                    1,347               575            43%            10/3/2023            4/3/2025      No Risk         None           $2,956,774.80                       GF                                  $0                        0%                $4,435,162.20          $0                0%                   940/880
                                            All Points Broadband               412                                              12/1/2023           11/30/2025                     None                                               GF                                                                              $6,027,280.42                                               1000/1000
                                                                                                   0              0%                                              No Risk                                                                                                 $0                       0%                                         0                 0%
          Henrico County                                                                                                                                                                           $501,620.00
          Orange County                          FiberLync                     576                230            40%            10/31/2023          04/21/2025    No Risk          ROW            $2,181,000.00                       GF                                  $0                       0%                $8,391,058.00            $0                0%                1000/1000
                                                  Shentel                     2,440                              48%            9/26/2023            9/26/2025                     None                                               GF                                                                             $9,168,655.00                                                1000/1000
                                                                                                 1,164                                                            No Risk                                                                                            $1,577,743.98                 32%                                   $2,930,095.95         32%
        Shenandoah County                                                                                                                                                                         $4,936,968.00
                                               EMPOWER Broadband              4,804                                                                                                None                                               GF                                                                             $21,677,288.16                                               1000/1000
                                                                                                   40             1%            9/26/2023           9/26/2026     No Risk                                                                                              $26,000                    0.3%                                        0                 0%
           Southside PDC                                                                                                                                                                          $8,556,028.84
  West Piedmont PDC (Pittsylvania)         RiverStreet Networks               2,102               162            8%             10/5/2023           10/5/2026     No Risk          None           $3,548,250.00                       GF                              $403,927.05                  11%                $1,856,750          $208,245.84          11%                1000/1000
    West Piedmont PDC (East)               RiverStreet Networks               3,356               623            19%            11/6/2023           11/6/2026     No Risk          None           $8,155,864.00                       GF                             $1,859,555.68                 23%               $5,205,136.00       $1,209,811.42         23%                1000/1000
                                                                                                                                                                                   None
    West Piedmont PDC (West)               RiverStreet Networks               4,526                0              0%            2/28/2024           2/28/2026     No Risk                         $8,013,600.00                       GF                               $18,250                    0.23%              $5,386,400.00            $0                0%                1000/1000
*Data as of September 2024 Monthly Project Reports, which reflect project statistics through the end of August.

Abbreviations for Reasons for Project’s Delay: MR – Make Ready, SCL – Supply Chain and Labor, UL – Utility Locates, RR – Railroad, ROW – Right of Way Permitting along State Roads, FED – Federal Land Permitting Challenges, OTH – Other (Described)




                                                                                                                                 Q3 2024 Quarterly Performance Report for the Virginia Telecommunication Initiative – FY2024 Projects
                                                                                                                Percent
                                                                                                              Complete,                                                                                                     Award Funding Source
                                                                                             Total Passings                                                                                                                                                                                                                                                                  Maximum Advertised
                                                                                                               Passings                                                                                                       GF, General Fund                                            Percent Expended, Out                                          Percent Expended,
                                                                                               Provided                                                                        Reason for a                                                                                                                                                                                     Project Speeds
                                                                       Passings in Project                     Provided                                                                                            SLFRF, Coronavirus State and Local Fiscal                                of Total Awarded                                                Out of Total
                                                                                              Broadband                                           Agreement End               Project’s Delay                                                                  Awarded Funding Expended                                                 Match Funding                        Available (Download/
             Grantee                 Internet Service Provider Partner        Area                            Broadband    Agreement Start Date                    Risk                           Award Amount                 Recovery Fund                                                     Funding          Total Match Funding                      Match Funding
                                                                                             Access to Date                                            Date                                                                                                                                                                              Expended                               Upload Mbps)
                                                                                                               Access to                                                                                             CPF, Coronavirus Capital Projects Fund
                                                                                                                 Date
            Giles County                          PemTel                       629                 0              0%               TBD                 TBD        No Risk          None           $4,199,596.00                       GF                                  $0                       0%                $1,343,604.00            $0                0%                1000/1000
          Franklin County                          ZiTEL                      2,543                0              0%               TBD                 TBD        No Risk          None           $4,538,288.00                       GF                                  $0                       0%                $7,737,355.00            $0                0%                1000/1000
                                                                                                                                                                                   None
       Thomas Jefferson PDC                        Firefly                    5,825                0              0%               TBD                 TBD        No Risk                         $12,208,500.00                      GF                                  $0                       0%                $36,427,182.00           $0                0%                1000/1000

           Southside PDC                         Empower                      3,983                0              0%               TBD                 TBD        No Risk          None           $3,353,579.00                       GF                                  $0                       0%                $3,153,579.00            $0                0%                1000/1000
         Rockbridge County                      Brightspeed                   1,734                0              0%               TBD                 TBD        No Risk          None            $975,865.00                        GF                                  $0                       0%                $4,938,467.00            $0                0%                1000/1000
         Rockbridge County                          BARC                       293                 0              0%               TBD                 TBD        No Risk          None           $1,197,320.00                       GF                                  $0                       0%                $1,653,443.00            $0                0%                1000/1000
          Orange County                          FiberLync                     425                 0              0%               TBD                 TBD        No Risk          None           $2,138,416.00                       GF                                  $0                       0%                $3,155,780.00            $0                0%                1000/1000
        Spotsylvania County                 Port 80                    522                0              0%                        TBD                 TBD        No Risk          None           $10,347,072.00                      GF                                  $0                       0%                $16,070,215.89           $0                0%               1000 / 1000
         Alleghany County                    CBEC                      370                0              0%                        TBD                 TBD        No Risk          None            $2,332,353.00                      GF                                  $0                       0%                 $1,019,580.00           $0                0%               1000 / 1000
         Botetourt County                  Comcast                     62                 0              0%                        TBD                 TBD        No Risk          None             $395,411.00                       GF                                  $0                       0%                 $2,121,571.00           $0                0%               1000 / 1000
*Data as of September 2024 Monthly Project Reports, which reflect project statistics through the end of August.

Abbreviations for Reasons for Project’s Delay: MR – Make Ready, SCL – Supply Chain and Labor, UL – Utility Locates, RR – Railroad, ROW – Right of Way Permitting along State Roads, FED – Federal Land Permitting Challenges, OTH – Other (Described)


File and source

File
2024-RD738.pdf
Size
477,608 bytes
SHA-256
d858cab4c85a78f4a9f9f2b6c8150d780f889d4a81932c6d26a8bc7fb4750282
Our copy
2024-RD738.pdf
Original
No public link identified.
Back to top