Siting and Permitting Reform in Washington — Report to the Washington Department of Commerce (Beveridge & Diamond, 2024)

Summary

Report by Beveridge & Diamond, PC, dated June 2024, to the Washington Department of Commerce under RCW 43.394.020(3)(a), on siting and permitting reform in Washington. The executive summary says the report analyzed permitting models from a number of states, the federal government, and the European Union, and that its recommendations are process-oriented only. It concludes that permitting in Washington is often too slow and too unpredictable. It recommends that SEPA processes designate the lead agency within 14 days after receipt of the application, determine within 30 days of submission whether the SEPA Checklist is complete, and issue the final EIS no more than two years after the determination of significance.

Summary drafted by a model from the document's text below and checked by script against that text before publication. It is a navigation aid, not a reading of what the document proves. Where AI is used

Cite this document

“Siting and Permitting Reform in Washington — Report to the Washington Department of Commerce (Beveridge & Diamond, 2024).” Archived at Pandemic Darlings, https://pandemicdarlings.com/source-documents/2024-permitting-reform-beveridge-diamond-2024-07-23-1-b12c257d-88ee-45-1333a6e6c1/, SHA-256 28dcf2bd3d4636fec6bc571f22f1d519b00f1c2d4d3452c3c2333e9ebbb818c4.

Full text

SITING AND PERMITTING REFORM IN
          WASHINGTON:
  A REPORT TO THE WASHINGTON
    DEPARTMENT OF COMMERCE
     UNDER RCW 43.394.020(3)(a)




    BEVERIDGE & DIAMOND, PC
           JUNE 2024
     SITING AND PERMITTING REFORM IN WASHINGTON:
A REPORT TO THE WASHINGTON DEPARTMENT OF COMMERCE
                 UNDER RCW 43.394.020(3)(a)




             BEVERIDGE & DIAMOND, PC
                    JUNE 2024



                   Primary Authors
                 Eric Lee Christensen
                 Christopher M. Bolte
                 Katherine S. O’Keefe
                    Jesse C. Miles
                  Joseph R. Ruggiero
                      Jason Frank

                   Technical Support
                  Kevin D. Fitzgerald
                  Natasha L. Johnston
                                                   TABLE OF CONTENTS

TABLE OF CONTENTS .............................................................................................................. I
EXECUTIVE SUMMARY .......................................................................................................... 1
BACKGROUND: GOALS AND LEGISLATIVE MANDATE FOR THIS REPORT, HOW
IT WAS PREPARED AND HOW IT RELATES TO WASHINGTON’S CLIMATE
MANDATES .................................................................................................................................. 5
   A.   STUDY GOALS...................................................................................................................... 5
   B.   STUDY BACKGROUND .......................................................................................................... 8
     1.    Legislative Mandate .................................................................................................... 8
     2.    How This Report Was Developed ............................................................................. 10
   C. WASHINGTON’S AGGRESSIVE CLIMATE GOALS: RAPID DEVELOPMENT OF CARBON-FREE
   RESOURCES IS ESSENTIAL TO MEET THESE GOALS ................................................................... 11
PERMITTING CLEAN ENERGY INFRASTRUCTURE IN WASHINGTON TODAY .. 13
   A. THE PROJECT DEVELOPMENT CYCLE AND ATTRACTING CAPITAL INVESTMENT IN THE
   CLEAN ECONOMY ...................................................................................................................... 13
   B. KEY PERMITTING ISSUES ................................................................................................... 17
   C. THE EFSEC PROCESS ........................................................................................................ 20
     1.    Background ............................................................................................................... 20
     2.    HB 1812, Modernizing the EFSEC Process .............................................................. 22
     3.    Criticisms of EFSEC ................................................................................................. 23
   D. LOCAL PERMITTING PROCESSES AND CRITICISMS.............................................................. 28
     1.    Growth Management Act .......................................................................................... 28
     2.    Shoreline Management Act ....................................................................................... 30
     3.    Police Powers and Zoning ......................................................................................... 31
     4.    Criticisms of Local Permitting Processes .................................................................. 31
   E. THE CONSOLIDATED PERMITTING PROCESS ....................................................................... 34
   F. THE HEAL ACT: ENVIRONMENTAL JUSTICE IN WASHINGTON .......................................... 37
   G. TRIBAL CONSULTATIONS ................................................................................................... 38
MODELS FOR REFORM FROM OTHER JURISDICTIONS ............................................ 38
   A.   FEDERAL PERMITTING REFORMS ....................................................................................... 38
        1.  FAST 41 and the Federal Permitting Improvement Steering Council ...................... 38
        a. Background ............................................................................................................... 38
        b. FAST-41 Timeline .................................................................................................... 39
     2.     Regulatory and Permitting Information Desktop Toolkit ......................................... 41
     3.     Federal NEPA Reform .............................................................................................. 41
     4.     Nationwide Permits under the Bald and Golden Eagle Protection Act ..................... 42
     5.     Expanded NEPA Categorical Exclusions for Transmission ..................................... 42
     6.     EPA Permitting Dashboard ....................................................................................... 43
     7.     Conservation Leasing ................................................................................................ 43
     8.     Federal-State Modern Grid Deployment Initiative ................................................... 44
   B. STATE PERMITTING REFORMS ............................................................................................ 46
     1.     California ................................................................................................................... 49
     2.     New York .................................................................................................................. 51
                                                                      i
        3.      Illinois ........................................................................................................................ 53
        4.      Michigan .................................................................................................................... 55
        5.      Minnesota .................................................................................................................. 56
        6.      State Energy Authorities ........................................................................................... 58
        7.      Track Record to Date ................................................................................................ 59
        8.      A Negative Example: Ohio ....................................................................................... 60
   C.        EUROPEAN UNION RENEWABLE ENERGY DIRECTIVE ........................................................ 61
PERMITTING REFORM RECOMMENDATIONS .............................................................. 62
   A.        ACROSS-THE-BOARD REFORMS ......................................................................................... 62
   B.        PERMITTING OVERSIGHT AND INFORMATION CLEARINGHOUSE ......................................... 67
   C.        EFSEC REFORMS .............................................................................................................. 72
   D.        LOCAL GOVERNMENT REFORMS ........................................................................................ 75
   E.        WASHINGTON RENEWABLE ENERGY AUTHORITY ............................................................. 76
CONCLUSION ........................................................................................................................... 78
APPENDIX A ............................................................................................................................ A-1
APPENDIX B ............................................................................................................................ B-1
APPENDIX C ............................................................................................................................ C-1
APPENDIX D ............................................................................................................................ D-1
APPENDIX E ............................................................................................................................ E-1
APPENDIX F .............................................................................................................................F-1
APPENDIX G ............................................................................................................................ G-1
APPENDIX H ............................................................................................................................ H-1




                                                                         ii
                                   EXECUTIVE SUMMARY

       Many states, along with the Biden Administration and foreign governments, have

adopted ambitious goals to decarbonize their electricity sectors and, in many cases, to

decarbonize their entire economies, by mid-century. To reach these goals will require a rapid

build-out of new renewable energy generation, electric transmission, and other clean economy

infrastructure. A consensus across a broad range of interests and perspectives has now developed

that current permitting processes are too slow and unpredictable to permit the needed build-out,

undercutting the environmental goals these laws were originally enacted to achieve.

       In this report, we have analyzed permitting models from a number of states, the federal

government, and the European Union; consulted a variety of experts involved in permitting clean

infrastructure; and considered a broad range of studies recommending reforms to permitting

processes. This report builds on the 2022 Low-Carbon Energy Project Siting Improvement

Report, in which the Departments of Commerce and Ecology engaged a broad cross-section of

Tribes and stakeholders to develop recommendations for improving siting processes in

Washington. We emphasize that our recommendations are process-oriented only. We have not

been asked to recommend changes to any of Washington’s substantive environmental laws and

have not done so.

       Based on this investigation, our conclusions and recommendations include the following:

   Washington’s Permitting Processes Require Significant Reform: Permitting in Washington

    is often too slow and too unpredictable, especially for large renewable generation projects

    and electric transmission infrastructure that is essential to meet decarbonization goals.

    Permitting processes are unnecessarily delayed for a number of reasons, but the most

    important are a lack of specific timelines for completing permitting, lack of clarity about



                                                 1
    mitigation and other requirements that might arise during permitting, and uncertainty about

    how many studies and surveys will be required over what time period.

Recommended Reforms

    Based on our investigation, we recommend the following measures to improve permitting

    processes in Washington:

    All permitting processes should:

        o Be adequately staffed, including staff with expertise in project management and
          community engagement that can keep permitting processes moving forward as
          efficiently as possible and ensure that involved agencies coordinate their efforts to the
          greatest extent possible.

        o All SEPA processes should incorporate the following:1

                   The lead agency should be designated within 14 days after receipt of the
                    application.

                   A determination whether the SEPA Checklist is complete should be made
                    within 30 days of submission, and the adequacy of any documents filed to
                    address gaps in the initial Checklist determined within seven days.

                   The determination of significance should be made within 60 days of receipt of
                    the complete SEPA Checklist and the project proponent should be provided
                    the opportunity to revise its plans or propose mitigation that would avoid
                    impacts and thereby avoid a full Environmental Impact Statement (“EIS”).

                   The final EIS should be issued no more than two years after the determination
                    of significance, with shorter periods for projects that have less impact or are
                    subject to a non-project environmental review.

                   Building on the existing process adopted in HB 1216, non-project reviews
                    should be conducted for all clean energy technologies that are expected to be
                    widely deployed in Washington.

                   Issues should be identified to the greatest extent possible in the pre-
                    application and scoping stages and new issues should not be inserted into late-
                    stage processes absent clear justification demonstrating that they could not
                    have been raised earlier.

1
 Many of these reforms have already been adopted in, for example, HB 1812 or HB 1216. We recommend that they
apply in all SEPA processes, not just in, for example, the EFSEC or Consolidated Permitting process.

                                                     2
             The Social Cost of Carbon metric should be used in all SEPA processes where
              greenhouse gas emissions are an issue.

   o Standardized Mitigation: Standard mitigation measures should be developed that can
     be easily adopted by project developers for commonly encountered environmental
     impacts.

   o Standardized Permits & Categorical Exclusions: Washington should adopt
     standardized permits, similar to the nationwide permits recently adopted by the U.S
     Fish & Wildlife Service (“USFWS”) for bald and golden eagle protections, that
     include clear requirements that project proponents can meet to avoid full permitting
     processes. Similarly, categorical exclusions like those recently proposed by the U.S.
     Department of Energy that avoid environmental review processes for common
     transmission construction that poses little risk to the environment, should be adopted.

Reforms Involving New or Existing Agencies:

Permitting Oversight and Information Clearinghouse: Washington should have an agency
charged with the following functions:

   o Permitting Dashboard: A permitting dashboard should be created to track the
     progress of permitting for clean energy infrastructure, which would include a process
     for all involved agencies to develop a permitting timetable that would be altered only
     in limited circumstances.

   o Mapping: Maps and other information relevant to siting should be assembled in one
     place so that project developers can easily identify the best opportunities for
     renewable energy development with the least conflicts likely to arise.

   o Least-Conflict Process: Using existing models, the agency should assemble interested
     parties to identify areas of agreement concerning where projects should be sited
     without threats to protected resources.

   o Renewable Energy Zones: Based on the least-conflict process, non-project
     environmental reviews required by HB 1216, and other relevant information,
     Renewable Energy Zones should be established where renewable energy
     development should be concentrated based on quality of renewable resources and low
     likelihood of permitting conflicts.

   o Technical Assistance: Technical assistance would be provided to Tribes, local
     agencies, and overburdened communities to help them manage permitting processes,
     understand renewable technologies (especially novel technologies), and identify
     workable mitigation measures.



                                           3
    o Pre-Application Roundtable: The agency would convene all interested parties,
      affected local and state agencies, and the project proponent in a pre-application
      process to identify all issues that could create conflict and to develop agreed
      mitigation strategies.

    o Community Benefits: Working with the Tribes, underrepresented and overburdened
      communities, organizations representing those communities, and the Environmental
      Justice Council, the agency would develop a set of standard community benefits
      agreements and labor agreements that could be adopted by project developers to
      ensure environmental justice goals are met as efficiently as possible.

   EFSEC Reforms: In addition to recent reforms, these additional reforms should be
    adopted:

       o Clear Standard for Approval: The Energy Facility Siting Evaluation Council’s
         (“EFSEC”) governing statute should be amended to provide clear direction that
         EFSEC must approve projects if they meet relevant standards for protection of the
         environment, historical and cultural resources, and provide sufficient benefits to
         local and overburdened communities.

       o EFSEC Decisionmakers: EFSEC decisions should be made by a three-member
         panel of individuals with relevant knowledge and experience, who are appointed
         by the Governor and approved by the Senate, and who are specifically assigned
         the duty of determining whether a project should be recommended for approval
         based on the standard specified in the previous bullet point.

       o Technology-Specific Standards: EFSEC should adopt technology-specific
         requirements that wind, solar and other renewable technologies must meet to
         qualify for permits and permits should be granted if these standards are met.

       o Mediation: EFSEC should employ mediation and other informal mechanisms to
         settle disputes to avoid expensive and time-consuming formal adjudications and
         its governing statute should be amended to facilitate this goal.

   Local Government Reforms: Legislation should be adopted to:

       o Standard Conditions: Set specific setbacks and other standards for renewable
         energy development that the local government could adopt or ease, but could not
         make more restrictive.

       o Limit Moratoria: Local governments would not be permitted to enact moratoria
         barring renewable energy development for those technologies with mitigation
         measures specified by statute. Nor would they be permitted to “move the
         goalposts” on regulatory requirements.



                                            4
             o Standard Regulation: Local governments would be permitted to require permits,
               impact fees, and other ordinary development regulations, but these could not
               place unique burdens on renewable energy or clean infrastructure projects.

       Washington Renewable Energy Authority: A new authority should be created that would:

             o Transmission: Be empowered to work with state and federal agencies, Tribes, and
               planning bodies to identify high-priority transmission corridors in Washington,
               particularly corridors necessary to connect Renewable Energy Zones with
               population centers, and to obtain property rights and permits necessary to
               construct transmission. Transmission rights would then be sold to utilities or
               developers.

             o Renewable Energy Permitting: Be authorized to obtain permits for renewable
               energy development, focusing on brownfields, degraded lands, and government
               lands. Once all permits are obtained, the authority would sell “build-ready”
               projects (that is, sites with all permits and land rights secured, so that construction
               can begin immediately) to utilities or developers.

BACKGROUND: GOALS AND LEGISLATIVE MANDATE FOR THIS REPORT, HOW
  IT WAS PREPARED AND HOW IT RELATES TO WASHINGTON’S CLIMATE
                           MANDATES

        A.       Study Goals

        A recent report from the Bipartisan Policy Center summed up the emerging consensus on

permitting reform issues:

        There is growing understanding that an unnecessarily slow environmental review process
        produces worse environmental outcomes, rather than better. America’s current permitting
        process helps to lock-in the status quo of energy infrastructure by hamstringing new
        development and improvements. With drastic scaleup of clean energy technologies
        needed, reforming the permitting process can align both the desire for improved
        environmental outcomes and energy sector growth by unlocking a wave of more
        sustainable project development. This approach requires recognizing that some historical
        arguments against permitting reform need to be reconsidered, while also acknowledging
        the importance of a clear, transparent review process for projects to ensure safety.2

        The report aptly describes Washington’s current permitting dilemma. Washington has

adopted aggressive greenhouse gas (“GHG”) reduction goals that will require large expansions



2
 X. Fishman et al., Finding the Goldilocks Zone: A Synthesis Report Based on Seven Roundtable Discussions, at 2
(Bipartisan Policy Center, January 2024).

                                                       5
of infrastructure to support a decarbonized economy, including new renewable energy resources,

a substantially expanded electric transmission system, the construction of industrial facilities to

produce sustainable aviation fuel, energy conservation equipment, equipment to support electric

vehicles and renewable energy generation, and facilities to treat and recycle these products when

they reach the end of their useful life.

        But recent experience demonstrates that Washington’s processes for permitting this

infrastructure in many cases are unpredictable, expensive, and can take many years, creating a

major barrier to this needed investment. A recent example is the Horse Heaven Clean Energy

Center, a combined solar-wind-battery storage project that would, if approved, be Washington’s

largest source of carbon-free power. It took EFSEC more than three years to process the

application for the Horse Heaven project from the time a final application was submitted until

EFSEC’s recent recommendation to approve a substantially scaled down project. EFSEC’s

recommendation was recently rejected by Governor Inslee and sent back to EFSEC, so final

resolution of the application may still take another 90 days, plus whatever time is needed to

resolve any resulting litigation.

        Reflecting on this experience, the founder and CEO of Scout Clean Energy, the sponsor

of the Horse Heaven project, stated publicly: “It’s just too risky to invest in Washington.”3

Similarly, one representative of an independent renewable energy developer we interviewed

described industry participants as “terrified” of investing in electric transmission infrastructure

given that proposals for new transmission infrastructure almost always result in local opposition

and that recent high-profile transmission projects in the region have taken from 12 to 20 years to




3
 See Conrad Swanson, How An Endangered Hawk Could Topple Plans for Washington’s Largest Wind Farm,
Seattle Times, Feb. 21, 2024.

                                                   6
fully permit.4 Given the level of investment needed to meet Washington’s decarbonization goals,

policymakers should be concerned that energy developers have reached these conclusions.

         The aim of this study is to recommend reforms to the permitting process that will

reassure investors by creating a process that is more predictable and less time-consuming, while

not compromising Washington’s laws protecting the environment, public health, cultural

resources, and other protected values. The Bipartisan Policy Center calls this the “Goldilocks

Zone” of permitting reform, in which the environment, public health, cultural resources, and

overburdened communities are adequately protected, but permitting processes are not so

burdensome as to slow needed investment in green energy and infrastructure. Accordingly, this

study identifies the challenges with Washington’s permitting processes that are causing

unnecessary delays, expense and unpredictability, and recommends improvements in these

processes based on permitting reforms that the federal government, other state governments, and

the European Union have enacted.




4
  The Boardman-to-Hemingway transmission project, which will connect a substation located near Hemingway
Butte in southwest Idaho to a substation near Boardman, Oregon, and would help carry renewable energy from
Idaho into Oregon and Washington, will take twenty years to permit and construct. The need for the line was first
identified in 2006 and final litigation over the project’s permits was recently settled and a final permit was issued.
The project’s in-service date is now anticipated in 2026. See B2H History - Idaho Power. Puget Sound Energy’s
Energize Eastside project took twelve years to permit, largely because of determined opposition from property
owners along the Energize Eastside route, even though it is a relatively modest project, involving construction of a
single substation and upgrades to 16 miles of an existing transmission line. See https://energizeeastside.com/.

                                                           7
        B.        Study Background

             1.     Legislative Mandate

        This report is prepared at the direction of the Washington Legislature, which, in 2023,

directed the newly formed Interagency Clean Energy Siting Coordination Council (“ICESCC”)

to:

        (a) Advise the department of commerce in:

        (i) Contracting with an external, independent third party to:

               (A) Carry out an evaluation of state agency siting and permitting processes for
        clean energy projects and related federal and state regulatory requirements, including the
        energy facility site evaluation council permitting process authorized in chapter
        80.50 RCW;

                (B) Identify successful models used in other states for the siting and permitting of
        projects similar to clean energy projects, including local and state government programs
        to prepare build ready clean energy sites; and

                (C) Develop recommendations for improving these processes, including potential
        policy changes and funding, with the goal of more efficient, effective siting of clean
        energy projects; and

        (ii) Reporting on the evaluation and recommendations in (a)(i) of this subsection to the
        governor and the legislature by July 1, 2024.5

        The Washington Departments of Commerce (“Commerce”) and Ecology in 2022 jointly

prepared a report, entitled Low-Carbon Energy Project Siting Improvement Report (“Low-

Carbon Siting Report”),6 which is the starting point for this study. The Commerce-Ecology

report was based on consultation with industry, local governments, Native American Tribes, and




5
 RCW 43.394.020(3)(a).
6
 Shorelands and Environmental Assistance Program, Washington Department of Ecology and Energy Division,
Washington Department of Commerce, Low-Carbon Energy Project Siting Improvement Report: Report and
Recommendations for Improving Siting and Permitting of Industrial Clean Energy Facilities, Publication No. 22-06-
013 (Nov. 2022).

                                                       8
other interested parties, and sets forth a series of recommendations for improvement of the siting

process from a variety of perspectives.

        Commerce is also preparing studies on renewable energy development in Washington’s

rural areas7 and on a planning and evaluation process for potential offshore wind development

off Washington’s coast.8 We therefore touch only lightly on those subjects.

        For purposes of this report, we used the term “clean energy projects” as it was defined in

House Bill 1216. The Legislature broadly defined “clean energy projects” to include clean

energy product manufacturing facilities, electrical transmission facilities, facilities to produce

non-emitting electric generation or electric generation from renewable resources, energy storage

facilities, biofuel and biomass facilities, facilities to produce sustainable aviation fuel, and

facilities that manufacture products used in clean energy facilities or energy conservation,

facilities that produce semiconductors, and projects or facility upgrades undertaken by

emissions-intensive, trade-exposed industries to reduce greenhouse gas emissions. We suggest

that the Legislature consider broadening this definition to include other types of facilities that are

likely to be necessary in a decarbonized economy, including, for example, carbon sequestration

projects and end-of-life facilities such as EV battery recycling plants. In addition, it would be

useful to include a catch-all for technologies that produce significant reductions in greenhouse

gas emissions GHGs over standard industrial processes so that technologies that are not yet fully

developed can in the future benefit from HB 1216’s Consolidated Permitting Process.




7
 The report is mandated by Section 307 of HB 1216 and is due by December 1, 2024.
8
 The Department of Commerce issued a Request for Proposals to develop recommendations for a planning and
evaluation process for offshore wind projects in October 2023.

                                                     9
             2.   How This Report Was Developed

       Commerce contracted with Beveridge & Diamond, PC (“B&D”), a national

environmental law firm, to provide the report mandated by the Legislature. Established 50 years

ago by pioneers in the then-emerging field of environmental law, B&D is the nation’s leading

environmental law firm. B&D assists clients to comply with the full range of local, state, federal

and international environmental laws. It assists a broad range of private companies and

government agencies to obtain the permits required to construct major projects, including clean

energy projects such as utility-scale battery storage projects and sustainable aviation fuel

production facilities. B&D also assists these clients to navigate the nation’s complex system of

energy regulation to, for example, obtain rights to transmission service on the nation’s high-

voltage grid, to obtain approvals necessary to construct energy facilities on federal lands, and to

comply with the rapidly evolving world of climate law. B&D’s Seattle office, opened in 2017,

features several of the region’s leading practitioners in energy and environmental law.

       In cooperation with Commerce, B&D agreed to develop this report using the following

resources:

      B&D practitioners from around the United States who helped identify permitting
       practices from state governments, the federal government, and certain foreign
       governments, that have substantially improved the speed and efficiency of permitting,
       particularly for clean energy resources.

      Starting with the recommendations contained in the Low-Carbon Siting Report, review
       relevant studies and policy papers to identify problems with existing permitting processes
       and reforms that may overcome these problems.

      Interview renewable energy developers, environmental advocates, renewable energy
       advocates, permitting professionals, regulators, and think tank experts to identify
       preferred approaches to permitting.

      Describe relevant federal laws, including laws that constrain action by the State of
       Washington and those that can be harnessed to advanced decarbonization of
       Washington’s economy.

                                                 10
        Review the relevant permitting laws and approaches from other jurisdictions and identify
         particular features that can be adapted to Washington’s permitting process to improve the
         speed and efficiency of permitting while honoring commitments to environmental
         protection, environmental justice, and tribal treaty rights.

        Share drafts with relevant state agencies and take comments from those agencies into
         account.

        Identify a set of recommended best practices for permitting in Washington.

         C.       Washington’s Aggressive Climate Goals: Rapid Development of Carbon-
                  Free Resources Is Essential to Meet These Goals

         Over the last two decades, the State of Washington has adopted increasingly aggressive

goals for reducing the state’s GHG emissions and has adopted legislation that sets GHG limits,

and requires substantial reductions in GHG emissions, across all sectors of the economy.

Specifically, Washington has enacted statutory limits to reduce its statewide GHG emissions by

95% over 1990 levels by 2050. For the electricity sector, Washington law mandates carbon

neutrality by 2030, with a carbon-free grid by 2045.9 The Legislature has mandated that the

Utilities & Transportation Commission (“UTC”), Commerce, EFSEC, Ecology and all other

state agencies “must incorporate” Washington’s goal of 100% clean electricity into “all relevant

planning” and must “utilize all programs authorized by statute” to achieve the 100% clean goal.10

         Currently, electricity consumed in Washington comes primarily from hydroelectric power

(about 54%), with smaller but significant contributions from natural gas (10%), coal (8.6%),11

wind (8%), and nuclear (4%), and smaller contributions from solar, biomass and other renewable

resources, with nearly 13% from “unspecified” market purchases.12 To replace retiring fossil-

fired generation and to meet this expected new demand will require huge investments in new


9
  We describe the most important Washington statutes addressing climate issues in Appendix A.
10
   RCW 19.405.050(4),
11
   Washington’s last coal-fired plant, Unit 2 of the Centralia generation plant is set to retire at the end of 2025.
12
   See https://www.commerce.wa.gov/growing-the-economy/energy/fuel-mix-disclosure/.

                                                           11
renewable energy. Transmission resources will need to be added to Washington’s energy

portfolio to meet these expected increases in electricity demand while at the same time meeting

decarbonization goals.

        To achieve these goals will require a major expansion of Washington’s renewable energy

generation fleet and transmission infrastructure. Washington’s 2021 State Energy Strategy

(“SES”)13 notes that GHG emissions from transportation accounts for 45% of the state’s GHG

emissions, while emissions from buildings accounts for 23%, and electricity production accounts

for only 16%. The SES contemplates that electrification will be a one of the most important

strategies to reduce GHG emissions from both transportation and buildings. The SES projects

that these new demands, combined with ordinarily-expected increases in electricity demand, will

result in increased electricity demand of 13 to 20% over 2020 levels by 2030, and 92% over

2020 levels by 2050.

        Recent trends suggest that the SES may well have underestimated future demands. In

May 2024, a regional industry forecast projected that electricity demand will increase from about

23,700 average megawatts (aMW) in 2024 to about 31,100 aMW in 2033, an increase of 7,400

aMW, or over 30% in the next 10 years.14 This is a substantial increase in the forecast from only

one year ago, which projected demand to increase by 24% in 10 years.15 Other recent reports

agree that current projections may well underestimate future needs because of growing electricity




13
   https://www.commerce.wa.gov/growing-the-economy/energy/2021-state-energy-strategy/.
14
   Pacific Northwest Utilities Conference Committee, Northwest Regional Forecast of Power Loads and Resources:
August 2024 through July 2034 (May 2024).
15
   Id.

                                                      12
demand from data centers, especially those used to support artificial intelligence, and hydrogen

fuel facilities, as well as from electrification efforts.16

     PERMITTING CLEAN ENERGY INFRASTRUCTURE IN WASHINGTON TODAY

        A.       The Project Development Cycle and Attracting Capital Investment in the
                 Clean Economy

        Sound permitting reform should recognize the myriad difficulties developers of

renewable energy projects face, and how permitting processes that cause undue delay and

uncertainty can create a serious drag on development. Accordingly, we provide a brief

description of the process for developing a typical utility-scale renewable energy generation

facility. The following graphic, from the Solar Energy Industries Association, shows a typical

project development timeline for a utility-scale solar project:




16
 Id.; Electric Power Research Institute, White Paper, Powering Intelligence: Analyzing Artificial Intelligence and
Data Center Energy Consumption (May 2024); J. Wilson & Z. Zimmerman, The Era of Flat Power Demand is
Over, Grid Strategies at 3 (Dec. 2023).

                                                        13
We note that other types of clean energy projects face many, but not all, of the same difficulties.

Projects not involving energy generation, for example, generally do not need to obtain

transmission interconnections:

        Locating Economic Resources: To develop an economic project, a developer must first
         locate areas with sun, wind, geothermal or other renewable resources that can, with
         reasonable assurance, be developed economically. Generally, at least one year of
         meteorological readings from a specific site are necessary to provide assurance that
         available renewable resources are productive enough to ensure an economical project. In
         addition, the proposed facility generally must be located near existing electric
         transmission lines. It can be extremely expensive – often $1 million per mile or more – to
         construct high-voltage lines, so a project that is otherwise economically viable may not
         be able to support construction of a long tie line to connect with the existing transmission
         system.

        Land Rights: Once a site with renewable resources that can be developed economically is
         identified with sufficient certainty, the project developer must obtain rights to use the
         land. On private lands, this generally requires the developer to pay for options that can be
         exercised once permits and financing are obtained. On public lands, development rights
         generally require the developer go through a lengthy process requiring extensive
         environmental reviews and may also involve competitive bidding on leases or other
         lengthy and, at times, expensive administrative processes.

        Power Purchase Agreement: A project will not be viable until the developer obtains a
         commitment from an electricity buyer to purchase the power produced by the project. In
         Washington, because utilities in almost all cases control access to retail markets, the
         developer must obtain a contract to sell power to a utility.17 Often, this requires winning a
         competitive bidding process that requires the project developer to have obtained land
         rights, have made substantial progress in obtaining transmission rights, and have most or
         all permits necessary to develop the project in place.

         Transmission Rights: To move power from the generator to the purchaser, it is necessary
         for the project developer to obtain rights to transmit power over the nation’s electric
         transmission grid. To transmit power on the interstate grid, the developer must file an
         interconnection application with the transmission utility or utilities that will move its
         power. With rapidly growing demand for renewable energy resources in recent years, the
         interconnection process is not functioning efficiently. Projects must now wait a national
         average of approximately five years to make it through the study process triggered by an
         interconnection request and to successfully interconnect with the transmission grid,18 and


17
  See Appendix C discussing utility regulation in Washington.
18
  E.g., J. Rand et al., Lawrence Berkeley National Laboratory, Queued Up: Characteristics of Power Plants
Seeking Transmission Interconnection As of the End of 2022 (April 2023).

                                                      14
         delays have recently gotten worse.19 The Federal Energy Regulatory Commission
         (“FERC”) is actively addressing these problems, both through reforms of the
         interconnection process and through transmission planning reform. But even if these are
         successful, it will likely take several years to see tangible results.20

        Transmission Permitting: When an energy project developer applies for rights to transmit
         power on the electric grid, its application triggers a series of engineering studies that
         identify any upgrades needed on the transmission system to accommodate the power that
         would be produced by the developer’s project, as well as equipment necessary to reliably
         move power from the generator to the point of interconnection with the existing grid.
         Generally, the new generation facility cannot start generating power, or may generate
         only at reduced capacity, until these upgrades and interconnection equipment are
         installed. While the upgrades and protective equipment are required to meet mandatory
         reliability standards, permitting those facilities is generally within the purview of state
         and local governments. Delays in permitting necessary transmission facilities therefore
         can substantially delay interconnection of new renewable generators, adding delays on
         top of the already lengthy transmission study process. This process is discussed in more
         detail in Appendix C.

        Equipment, Engineering, and Construction Contracts: With growing demand for wind
         turbines, solar cells, and other key equipment, project developers often must get in
         factory queues for such equipment, which may require that they order the equipment
         months or even years in advance. Similarly, experts with the specialized knowledge
         necessary to design renewable generators and necessary supporting facilities like
         substations, switchyards, and interconnection facilities, are in high demand, and a project
         developer may have to get in line to obtain these services.

        Financing: While financing for renewable energy projects is now available from many
         financial institutions, these institutions generally require the power purchase agreement,
         land rights, equipment and engineering contracts, transmission rights, as well as all
         necessary permits to be in place to ensure repayment of financing.

         Because financial institutions are reluctant to loan money to a project before everything

necessary to assure repayment of the loan is in place, the project developer usually must fund the

whole range of upfront work necessary to get all land and contractual rights, power purchase

agreements, transmission rights, and required permits in place. This process can take years and




19
   J. Rand et al., Lawrence Berkeley National Laboratory, Queued Up: 2024 Edition, Characteristics of Power
Plants Seeking Transmission Interconnection As of the End of 2023 (April 2024).
20
   FERC’s transmission reform efforts are addressed in greater detail in Appendix C.

                                                       15
cost tens of millions of dollars, even more for a large project or a project with particular technical

challenges, like offshore wind.

        Unforeseen permitting delays or other complications, such as unanticipated permit

conditions that force significant reductions in a project’s capacity, can add substantial costs to

this process, sometimes enough to kill an otherwise viable project. A recent study by the

Lawrence Berkeley National Laboratory found that about one-third of wind and solar projects for

which applications were submitted in the last five years were cancelled, and about half

experienced delays of six months or more. Average sunk costs for cancelled projects were about

$7.5 million for wind projects and $2.5 million for solar projects, and project delays cost about

$200,000 per megawatt (“MW”) for both wind and solar. The leading causes of cancellations

were local opposition, local ordinances and zoning, and problems obtaining grid

interconnection.21

        In most cases, interconnection and transmission is a federal matter and, as noted above,

Washington can influence the speed of interconnection only by speeding up the permitting of

transmission upgrades that may be required for new projects to interconnect, and by participating

in transmission planning processes. On the other hand, many of the project developers we

interviewed identified the permitting process as the greatest source of uncertainty in project

development, and unforeseeable delays in permitting as one of the chief factors determining

whether a project can be built or fails before the development process is complete. Because

permitting, including permitting of transmission projects, is generally a state or local function,

Washington policy makers can make a substantial difference in expedited construction of clean




21
  R. Nilson et al., Lawrence Berkeley National Laboratory, Survey of Utility-Scale Wind and Solar Developers (Jan.
2024).

                                                       16
energy projects by improving the speed and predictability of siting and permitting processes for

these projects.

        B.        Key Permitting Issues

        Project developers must comply with a broad range of environmental laws requiring

study of environmental impacts, protection of public resources like air and water, wildlife

conservation, and preservation of historical and archaeological resources, summarized in

Appendix B. Certain types of projects must comply with additional regulatory regimes aimed at

ensuring safe aviation, navigation, fire safety, or other specific values. For example, wind energy

developers must ensure that wind towers are marked with lights complying with Federal

Aviation Administration (“FAA”) requirements, and that they do not interfere with radar or other

flight operations of the U.S. military. Developers of hydroelectric projects must obtain a FERC

license under Part I of the Federal Power Act, which is intended to ensure that hydroelectric

developments do not interfere with river navigation, are part of a plan to optimize development

of river systems, and otherwise comply with applicable environmental laws.22

        Environmental analysis in nearly every case is a critical concern for project developers.

The federal National Environmental Policy Act (“NEPA”) was intended to incorporate

environmental considerations into all aspects of federal administrative processes.23 The most

important provision of NEPA requires federal agencies to prepare a full EIS if a proposed federal

action has a “reasonably foreseeable significant effect on the quality of the human

environment.”24 Preparation of an EIS often takes months or years and may encompass hundreds

or even thousands of pages of analysis, although recent federal legislation, discussed below, has



22
   Federal Power Act Part I requirements are summarized in Appendix C.
23
   See generally U.S. Environmental Protection Agency, Summary of the National Environmental Policy Act.
24
   42 USC § 4336 (b)(1).

                                                      17
imposed both time and page limits in EISs. An Environmental Assessment (“EA”) is required if

the federal action “does not have a reasonably foreseeable significant effect on the quality of the

human environment.” EAs are generally more concise than EISs and less time-consuming to

develop. Finally, Categorical Exclusions are available for actions that agency concludes, after

following the required administrative process, that are not ordinarily expected to have a

significant environmental impact.25

           Washington has adopted a state analogue to NEPA, the State Environmental Policy Act

(“SEPA”).26 SEPA extends the requirement for agencies to consider the environmental

consequences of their decisions to all state and local agencies in Washington. Hence, SEPA

applies to any permitting process in Washington, whether state or local. Like NEPA, SEPA

requires a full EIS for agency decisions anticipated to have significant environmental impacts. A

“Determination of Non-Significance” (“DNS”) may be issued for projects that are not expected

to have significant environmental impacts, and a “Mitigated Determination of Non-Significance”

(“MDNS”) may be issued for projects that have mitigated their environmental impacts so that

they are not expected to be significant. SEPA also allows for Categorical Exclusions for specific

types of agency actions not expected to have significant environmental impacts. One important

innovation adopted under SEPA is the “SEPA Checklist,” a form document that spells out all of

the different impacts a project sponsor should consider and document that are considered for

permitting under Washington law. Most permitting specialists consider the SEPA Checklist to be

an important and useful tool for preparing a project application.




25
     42 U.S.C. § 4336c.
26
     RCW Chapter 43.21C. See generally Department of Ecology, State Environmental Policy Act.

                                                       18
       Twenty-nine federally recognized Native American Tribes have traditional homelands

and reservations in Washington. Under the Stevens Treaties, these Tribes have usufructuary

rights for fishing, hunting, and gathering on their usual and accustomed territories outside

reservation lands. In addition, several other Tribes have interests in Washington that may be

affected by permitting processes in this state. Tribes play a critical role in permitting processes,

as described in greater detail in Appendix D. In addition, millions of acres of land in Washington

are set aside as designated Wilderness or National Parks or are subject to regulation by federal

and state agencies like the U.S. Forest Service or the Washington Department of Natural

Resources (“DNR”), summarized in Appendix E.

       This report does not propose changes to any of these substantive laws. Rather, we

recommend procedural changes to improve the process of permitting. The proposed reforms are

based on what we have heard from the many entities we have interviewed for this study, what we

have read in the many studies and white papers we have reviewed, which represent multiple

perspectives, including project developers, environmental groups, trade groups, permitting

experts, and attorneys with deep experience in energy project development. The consensus

among these informed observers is that, while some siting and permitting processes work well,

too often these processes are unnecessarily unpredictable, expensive, and time-consuming.

       For the reasons we now discuss, these criticisms apply to varying degrees whether a

project developer elects to go through the EFSEC process or through the local permitting

processes. Whichever process is chosen, developers can face years-long delays with uncertain

outcomes, as we now explain in more detail. Developers now have a third option, the Ecology’s

new “Coordinated Clean Energy Permit Process.” Because it is so new, Ecology is still




                                                 19
developing regulations for the process and there is not yet a track record to judge how effective

this process is at reducing unnecessary permitting barriers.

           C.        The EFSEC Process

                1.     Background

           In 1970, fearing that the region was bumping up against the limits of its vast

hydroelectric system, urgent construction of new nuclear and coal-fired plants was thought to be

needed to meet anticipated electricity demand. In response, the Legislature created EFSEC, then

known as the “Thermal Power Plant Site Evaluation Council.”27 EFSEC was empowered to

permit thermal power plants with a capacity of 250 MW or more. In 2001, the Legislature added

provisions allowing the developers of renewable energy projects of any size to seek EFSEC

approval as an alternative to going through the local permitting process. Over the years,

EFSEC’s mandate has been broadened to include authority to permit electric transmission lines,

natural gas and petroleum pipelines, and, more recently, emerging technologies like green

electrolytic hydrogen and biogas facilities as well as clean energy product manufacturing

facilities.

           EFSEC is intended to provide a centralized permitting process that balances the statewide

need for abundant, affordable energy, environmental protection, and local concerns. EFSEC is

composed of representatives of a number of state agencies with interests in energy development

or environmental protection, and also includes, on a case-by-case basis, local officials from the

area where a project is proposed.

           Applicants seeking EFSEC approval must pay a $50,000 deposit (potentially more) to

cover costs that arise during the process. The application must also provide technical studies,



27
     1970 Wash. Laws Chapter 45 (1st Exec. Sess.).

                                                     20
biological studies, historical resource studies and other information to allow EFSEC to make an

informed decision. An applicant may request a pre-application review, in which case EFSEC

staff must review the applicant’s draft application and provide comments on additional studies,

or stakeholder or Tribal input, that should be included in a final application.28

        When an application is received, EFSEC must notify a variety of potential stakeholders,

including legislators representing the city and county where the project would be located, the

department of archaeology and historical preservation, and potentially affected Tribes. EFSEC

must conduct an informational public hearing within 60 days of receiving the application at a

location as close as is practical to the proposed site. After this hearing, EFSEC is required to

conduct another public hearing to determine whether the proposed site is consistent with local

land use plans or zoning ordinances, although the informational public hearing and the land use

consistency hearings are often held simultaneously.

        Once this process is complete, EFSEC must, within 12 months, formally recommend to

the Governor that the proposed project be approved or rejected, although this one-year deadline

is often extended to permit, for example, completion of environmental analyses or site surveys,

especially with large projects. If EFSEC recommends that a project be approved, it must submit

a draft certification agreement that specifies the terms and conditions of construction and

operation of the facility. The governor has 60 days from receipt of EFSEC’s recommendation to

1) approve the application and execute the draft agreement, 2) reject the application, or 3) direct

EFSEC to reconsider certain aspects of the draft certification agreement. If a project is certified

by the Governor, it greenlights the project. Certification binds the state, its agencies, and political



28
   RCW 80.50.340, .380. The Legislature has provided for a specific pre-application process for electric
transmission facilities which requires EFSEC to consider electric transmission corridors designated by other
agencies. RCW 80.50.330.

                                                        21
subdivisions as to the approval of the site and construction and operation of the proposed energy

facility. The Governor’s final decision is subject to judicial review under the Administrative

Procedure Act, with expedited appeal directly to the Washington Supreme Court available.

       If a project can demonstrate that it is without significant environmental impacts, or that

those impacts are mitigated to a non-significant level and the project is consistent with local land

use regulations, the project is eligible for expedited processing by EFSEC.29

       EFSEC may preempt local rules. Initially, it must determine whether or not the proposed

site is “consistent and in compliance with city, county, or regional land use plans or zoning

ordinances on the date of the application.”30 But EFSEC is authorized to preempt local laws.31 If

it does so, it must “include conditions in the draft certification agreement to implement the

provisions of this chapter including, but not limited to, conditions to protect state, local

governmental, or community interests, or overburdened communities . . ., and conditions

designed to recognize the purpose of laws or ordinances, or rules or regulations promulgated

thereunder.”32

           2.     HB 1812, Modernizing the EFSEC Process

       In 2022, Governor Inslee signed into law House Bill 1812, which amended EFSEC’s

governing statute in several important ways:

          The list of facilities eligible for the EFSEC process was expanded to include “clean
           energy product manufacturing facilities,” defined broadly to include facilities that
           manufacture products used for clean energy facilities, charging and other
           infrastructure related to electric vehicles, and facilities for the production of green
           electrolytic hydrogen (hydrogen without a fossil fuel feedstock). The bill also
           expanded the list of energy projects eligible for the EFSEC process to include
           renewable natural gas and energy storage facilities.


29
   RCW 809.50.075; WAC 463-43-070.
30
   RCW 80.50.090(2).
31
   RCW 80.50.110(2); WAC 463-28-030, -080.
32
   RCW 80.50.100(2).

                                                  22
            Electric transmission projects eligible for the EFSEC process were expanded to
             include any electric line with a capacity of 115 kV or greater that will cross two or
             more jurisdictions with land use plans or zoning ordinances, eliminating the previous
             requirement that the transmission line could not be in an existing transmission
             corridor.

            The requirements for EFSEC to consult with state and local government agencies and
             with federally recognized Tribes is spelled out in some detail, especially for Tribal
             consultations.

            The composition of EFSEC council members was changed modestly, and the EFSEC
             chair was empowered to hire a staff director, and the director was empowered to hire
             additional professional and administrative staff. EFSEC’s power to hire consultants
             was also expanded. In addition, EFSEC was formally separated from the Utilities and
             Transportation Commission.

            The provision allowing expedited treatment for projects with no significant
             environmental impacts was modified so that a project proponent seeking such
             treatment will be notified if EFSEC preliminarily determines that the project is not
             eligible for expedited treatment and will be given the opportunity to revise its
             proposal to qualify for expedited treatment.

            3.       Criticisms of EFSEC

        We have heard several consistent criticisms of EFSEC from a broad spectrum of project

developers, industry trade groups, and environmental organizations. The primary criticisms are:

            Lengthy and Unnecessary Delays: Recent applications, especially for large projects,
             have taken three years or more from the time a final application is submitted for the
             EFSEC process to be completed. The process is often considerably longer if pre-
             application consultations and preliminary project work are considered. For example,
             the proposed Horse Heaven Hills project began on-site wildlife surveys in 2016 and
             has been involved in consultations with state and federal agencies and Tribes since
             February 2017.33 EFSEC’s final recommendation to the Governor to approve the
             project, with conditions that will reduce its capacity by at least half, were delivered to
             Gov. Inslee on April 29, 2024,34 more than three years after the final application was
             submitted and more than seven years after pre-application consultation processes
             were started. On May 23, 2024, Governor Inslee rejected EFSEC’s recommendation
             and directed the agency to reconsider the conditions it imposed on its
             recommendation for approval within 90 days.35 Delays are attributed to several
             factors, including repeated requests for information on environmental or other
             conditions from project developers (often involving lengthy delays to collect the

33
   See Scout Clean Energy Application for EFSEC Site Certification, at Table 1.12-1 p. 1-57 (Feb. 2021).
34
   Report to the Governor on Application Docket No. EF 220011 (April 29,2024).
35
   See Letter from Governor Inslee re Horse Heaven Wind Farm Project EFSEC Recommendation.

                                                        23
               required information), time-consuming formal adjudication processes, overstretched
               staff, and lack of project oversight such as agreed deadlines for agency review of
               project applications. In addition, many of those we interviewed asserted that there is a
               lack of clear guidance from the involved agencies concerning protocols and
               expectations for field surveys and environmental studies, which contributes to the
               process of repeated demands for information and lengthens the timeline for the site
               certification process.

           The chart below summarizes the length of the EFSEC process for renewable energy

projects over the last several years:36

     Project Name               Pre-          Proposed         Application     Approved       Recommendation
                             Application      Capacity                         Capacity         to Governor
                              Activities
     Badger Mountain                                            October 5,
                                2019           200 MW                             TBD                TBD
     Solar37                                                      2021
                                            160 MW solar
                   38                                           February
     Carriger Solar             2020           63 MW                              TBD                TBD
                                                                20, 2023
                                               battery
                                                               October 16,
     Columbia Solar39           2017            25 MW                            25 MW         August 21, 2018
                                                                  2017
                                               180 MW          November
                                              (revised to        3, 2006
     Desert Claim Wind
                                2002         190 MW and          Revised        190 MW        December 4, 2009
     Power Project40
                                              finally 100      January 29,
                                                 MW)              2009
                                                               January 19,
     Goose Prairie Solar41      2019            80 MW                            80 MW        October 19, 2021
                                                                  2021
     High Top and Ostrea                                         April 7,        80 MW
                                2020         80 MW each                                       February 17, 2023
     Solar Project42                                              2022            each
                                            500 MW solar
                                                                December
     Hop Hill Solar43           2021          500 MW                              TBD                TBD
                                                                22, 2022
                                               battery



36
   We understand that EFSEC has recently adopted a standardized application for solar projects, which may help
explain why recent solar projects have generally been approved within one year or less of the final application.
However, we were unable to locate sufficient information to evaluate this program.
37
   See Badger Mountain Solar Energy Project Application for Site Certification.
38
   See Carriger Solar Project Application for Site Certification.
39
   See Columbia Solar Projects Washington EFSEC Application for Site Certification; Report to the Governor on
Application No. 2017-01.
40
   See Desert Claim Wind Power Project Application for Site Certification; Desert Claim Wind Power Project
Revised Application; Desert Claim Wind Power Project – Recommendation of Approval.
41
   See Goose Prairie Solar Application for Site Certificate; Goose Prairie Solar Revised Application for Site
Certificate; Report to the Governor on Application No. 2021-01.
42
   See High Top and Ostrea Application; Report to the Governor on Application No. EF-220212.
43
   See Application for Site Certification Hop Hill Solar and Storage Project.

                                                        24
                                                                               Estimated
     Horse Heaven Wind                                        February 8,
                               2016           1,150 MW                           ~50%          April 29, 2024
     Project44                                                   2021
                                                                              reduction45
     Kittitas Valley Wind                                     January 12,     97.5 – 195
                               2002            200 MW                                           May 2, 2007
     Power Project46                                             2003             MW
     Wallula Gap Solar                                         February
                               2021            60 MW                             TBD                TBD
     Project47                                                 23, 2024
                                            470 MW solar
     Wautoma Solar                                              May 20,
                               2021           470 MW                             TBD                TBD
     Energy Project48                                            2022
                                               battery
                                                                              Limited to
     Whistling Ridge                         75 MW (50         March 10,
                               2003                                               35          January 4, 2012
     Energy Project49                         turbines)         2009
                                                                               turbines
                                                                               273 MW
     Wild Horse Wind                                            March 8,         wind
                               2002            312 MW                                          May 25, 2005
     Power Project50                                             2004          500 kW
                                                                                 solar

              Lack of Coordination in Process: Project developers and permitting experts we
               interviewed asserted that EFSEC lacks expertise in project management, with the
               result that project reviews by different agencies are often uncoordinated, contributing
               to unnecessary delays. HB 1812 authorizes EFSEC to acquire new staff and EFSEC
               has been emphasizing employees with project management skills, and the agency
               reports that it has hired eight new staff with such expertise.

              Lack of Expertise and Staff: While agency personnel who participate in the EFSEC
               process generally have deep expertise related to the agency’s mission (for example,
               Washington Department of Fish and Wildlife (“WDFW”) personnel tend to have
               deep expertise in wildlife conservation issues), many developers we interviewed
               criticized the departmental representatives who participate in the EFSEC process for
               having limited expertise in energy project development.51 In addition, EFSEC has had
               insufficient staff to keep the application process moving expeditiously. One
               interviewee expressed concern that the shortage of staff may be exacerbated by the
               Legislature’s recent expansion of projects eligible for EFSEC consideration in HB



44
   See Scout Clean Energy Application for EFSEC Site Certification; Report to the Governor on Application Docket
No. EF-220011.
45
   Governor Inslee remanded to EFSEC to reconsider limitations placed on the project. See Letter from Governor
Inslee re Horse Heaven Wind Farm Project EFSEC Recommendation.
46
   See Application for Site Certification for the Kittitas Valley Wind Power Project; Kittitas Valley Wind Power
Project – Recommendation of Approval.
47
   See Wallula Gap Solar Project Application for Site Certification.
48
   See Wautoma Solar Energy Project Application for Site Certification.
49
   See Whistling Ridge Energy Project Application for Site Certification; Whistling Ridge Energy, LLC –
Recommendation Package for Approval.
50
   See Wild Horse Wind Power Project EFSEC Application; Wild Horse Wind Power Project Special Meeting.
51
   In EFSEC’s early years, agency representatives were expected to have significant energy expertise and were also
expected to act independently of their agency.

                                                       25
             1812, although HB 1812, as noted, authorizes EFSEC to add staff and it has been
             doing so.

            Lack of Mechanism to Balance Interests: The governing statute directs EFSEC to
             “report to the governor its recommendations as to the approval or rejection of an
             application for certification within twelve months” of receipt of an application for
             certification, but provides little or no binding guidance as to what applicants must
             demonstrate to receive a recommendation for approval.52 Further, as a council of
             agency designees, EFSEC may provide an efficient venue to resolve each agency's
             individual concerns and requirements based on its own mission and priorities, but it is
             ill-suited to evaluate projects relative to overarching state policies, including the
             state's climate and clean energy requirements. The EFSEC Council is composed of
             representatives from Ecology, WDFW, Commerce, the UTC, and DNR, and the
             substantive analyses of EFSEC applications are performed by these agencies
             (primarily Ecology and WDFW), along with the Department of Archaeological and
             Historical Preservation (“DAHP”). Because these agencies are mission-driven, they
             tend to recommend conditions on certification that maximize protection for, for
             example, wildlife species, while failing to consider the extent to which these
             conditions would hinder clean energy project development, either in a particular case
             or in the wider context. This view was expressed universally by the developers, trade
             groups, and permit specialists we interviewed.

             The treatment of mitigation measures for ferruginous hawks included in EFSEC’s
             recommendations for the Horse Heaven project illustrate the problem. At the outset, it
             should be noted that the ferruginous hawk has been listed as “endangered” in
             Washington and the species has experienced precipitous declines in the state over the
             last three decades, primarily due to the loss of sage-steppe habitat to agricultural
             development and sprawling urban development, as well as habitat loss in the Great
             Plains and other habitat areas outside Washington, where the birds spend the majority
             of their time.53 But the species as a whole is not endangered. The Cornell Lab of
             Ornithology rates the species as of “low conservation concern,” noting that its overall
             population increased approximately 1% per year from 1996 through 2019 based on
             the results of the North American Breeding Bird Survey.

             Although WDFW has identified loss of sage-steppe habitat loss as the primary culprit
             for the decline of ferruginous hawks in our state, EFSEC missed the opportunity to
             directly address that problem by requiring Horse Heaven to mitigate its impacts by
             preserving or restoring sage-steppe habitat. Instead, at WDFW’s recommendation,
             EFSEC imposed a 2-mile buffer around all ferruginous hawk nests, even though no

52
   RCW 80.50.100. The statute’s statement of legislative intent, set forth at RCW 80.50.010, states that the
Legislature intends EFSEC to “balance” demands for clean energy against “the broad interests of the public” based
on a list of six “premises.” Statements of legislative intent are generally viewed as precatory, and, while a useful
guide to interpreting a statute if it is ambiguous, do not create binding obligations on an agency. Even if it were
binding, the “balancing” language in RCW 80.50.010 provides little assurance that, if a project developer avoids or
adequately mitigates environmental impacts, its project will be approved.
53
   See G. Hayes & J. Watson, WDFW, Periodic Status Review for the Ferruginous Hawk (Aug. 2021).

                                                         26
            active nests have been identified in the project area since 2019 and, sadly, the record
            suggests that, because of habitat loss, they are unlikely to be used again. If this
            condition had been approved by Governor Inslee, it would have forced the Horse
            Heaven project to reduce its proposed capacity by 50% or more.54 The two-mile
            buffer is more restrictive than those imposed by other agencies managing ferruginous
            hawk habitat, notably including the U.S. Fish & Wildlife Service, which recommend
            setbacks of 0.5 to 1 mile for active nests.55 The area restricted under the WDFW’s 2-
            mile buffer is about sixteen times larger than the 0.5-mile buffer and about four times
            the size of the 1 mile buffer.

            EFSEC could have adopted mitigation measures that would have resulted in less
            drastic reductions in project capacity but likely would have been at least as effective
            in protecting ferruginous hawks. For example, rather than simply barring any
            development within a two-mile radius of hawk nests, EFSEC could have required
            monitoring of nests and adaptive management if any of those nests are occupied in
            the future. If the nest is used, the project operator could be required to shut down
            wind turbines within a reasonable radius of the nest until the hawks have fledged and
            migrated. Generally, this would occur in the spring when wind turbines are often
            scheduled for maintenance anyway, and this would allow the turbines to produce
            when hawks are absent in Washington and when nests are not occupied. As Governor
            Inslee concluded, “[t]he outright prohibition of turbine locations should be replaced
            with mitigation in the form of operational conditions that allow for build-out of the
            vast majority of the proposed Project.” The far more extreme approach taken by
            EFSEC, however, will force a drastic reduction in renewable energy capacity with, at
            best, marginal benefits to ferruginous hawks.

            The EFSEC statute assigns EFSEC’s director administrative authority only, and there
            is no structural mechanism for balancing conditions recommended by the agencies
            involved in the process against the state’s overarching goals for developing clean
            energy projects. To put it another way, EFSEC lacks a mechanism to balance the
            state’s interest in expanding clean energy projects against the project’s impacts on
            wildlife, aesthetics, and other resources. Because urgent action is needed to avoid the
            worst effects of climate change, including damage to Washington’s environment and
            wildlife, the lack of an effective balancing mechanism could result in counter-
            productive decision-making, causing EFSEC to reject projects that would have a net
            positive impact on Washington’s natural resources when their effects on climate
            stabilization, along with required mitigation measures, are taken into account.

           Lack of Predictability: The EFSEC process is generally centered around developing
            an extensive environmental analysis, without particularized parameters to guide
            avoidance of environmental impacts, mitigation, or limits on how much information

54
  See Conrad Swanson, Plans for WA’s Largest Wind Farm Slashed in Half, Seattle Times, April 17, 2024.
55
  See, e.g., Laura A. Romin and James A. Muck, Utah Field Office Guidelines for Raptor Protection From Human
and Land Use Disturbances, Table 2 at 29 (Jan. 2002); U.S. Fish and Wildlife Service, Region 6 Wildlife Buffer
Recommendations for Wind Energy Projects at 1 (Mar. 31, 2021); Wyoming Ecological Services Field Office,
Protections for Raptors, Table 1 at 5 at (Mar. 9, 2022).

                                                      27
            must be provided. As a result, even after agency concerns are identified in the pre-
            application process and project developers design their projects to avoid identified
            impacts, it is difficult for project developers to predict what additional concerns will
            be identified, what additional studies or surveys will be demanded, what level of
            mitigation will be required, and whether changes to the project to address these
            concerns will render the project uneconomic. Developers we interviewed also
            asserted that agencies often “move the goalposts” by relying on guidance or other
            documents that have not been published, subject to agency review, or peer review by
            scientists. These documents sometimes appear well after an application has been
            received and accepted by EFSEC, adding substantial uncertainty to the process.

       D.        Local Permitting Processes and Criticisms

       In Washington, counties and cities have permitting and regulatory authority for activities

within their jurisdictions. Historically, renewable energy projects were permitted at the local

level, with EFSEC as an alternative process, generally relied upon by developers facing barriers

to project approval at the local level or approvals across multiple jurisdictions.

       Although specifics vary by jurisdiction, counties, cities and towns generally regulate

development, including energy development, under the following legal regimes:

            1.       Growth Management Act

       The Growth Management Act (“GMA”) is the primary statutory framework for local land

use planning and development in Washington.56 The GMA identifies fifteen non-prioritized

goals, which are sometimes in tension, to guide local land use plans and development

regulations.57 The GMA also requires 29 fast-growing cities and counties to adopt

comprehensive plans to ensure those cities and counties will be able to effectively provide urban

services, infrastructure, water and other resources to accommodate projected population

growth.58




56
   RCW 36.70A
57
   RCW 36.70A.020.
58
   RCW 36.70A.210.

                                                 28
        The plans must contain elements of, for example, land use, housing, capital facilities,

rural development for counties, transportation, and climate change and resiliency.59 Optional

elements include economic development, parks and recreation, conservation, solar energy,

subarea plans, and ports.60 Cities and counties must periodically review these plans and revise

them if necessary. The 2024 Legislature adopted legislation requiring climate mitigation,

including reduction of GHG emissions, to be added as a mandatory element of comprehensive

plans.61

        In addition, all cities and counties must designate natural resource lands and adopt

regulations governing the use of these lands. Cities and counties must also adopt critical area

regulations. The GMA defines five types of critical areas: (1) wetlands; (2) critical groundwater

recharging areas that may impact aquifers used for potable water; (3) frequently flooded areas;

(4) geologically hazardous areas; and (5) fish and wildlife habitat conservation areas. The

function of these areas must be protected using the best available science.62

        Policies developed under the GMA can have substantial impacts on clean energy project

development and, like any other type of development, clean energy projects can have substantial

local impacts. For example, buffers around critical areas generally preclude development or at

least require potentially expensive mitigation measures. Similarly, comprehensive plans may

result in restrictions on clean energy development in areas that are zoned to preclude such

development. Often, clean energy projects can be developed only with a conditional use permit,

which requires the project developer to apply for a permit from the relevant county or city. Some

counties do not have zones that allow for renewable energy development, so that such


59
   RCW 36.70A.070.
60
   RCW 36.70A.080, .085.
61
   SB 6140 (effective June 6, 2024).
62
   RCW 36.70A.170; RCW 36.70A.172

                                                29
development is possible only with a zoning change. Generally, this requires the developer to seek

approval from EFSEC as the only practicable alternative.

       Except for certain project-level disputes that are resolved by the Superior Courts under

the Land Use Petition Act,63 the Growth Management Hearings Board resolves disputes under

the GMA, including disputes about the adequacy of SEPA analyses connected with zoning or

permitting decisions under the GMA. The GMA provides the governor with authority to impose

sanctions on cities, counties, and state agencies that do not comply with the GMA as determined

by the Growth Management Hearings Board.64

          2.      Shoreline Management Act

       The Shoreline Management Act (“SMA”)65 works similarly to the GMA. It requires all

39 Washington Counties and about 250 cities and towns to develop Shoreline Master Programs

that comply with the SMA’s mandates. Those mandates require localities to develop and adopt

Shoreline Master Programs to regulate development on shorelines, which includes lakes, rivers,

streams with more than 20 cubic feet per second of flow, wetlands, and floodplains, along with

lands 200 feet shoreward of these water bodies. The SMA also mandates protection of

“shorelines of statewide significance,” which includes Puget Sound, Hood Canal, the state’s

large rivers and lakes, and associated wetlands. Restrictions arising under the SMA can limit

clean energy projects within the buffer zones and also may limit development of clean energy

projects relying on, for example, small hydroelectric dams or tidal energy.




63
   RCW 36.70C.
64
   RCW 36.70A.340-.345.
65
   RCW Chapter 90.58.

                                                30
            3.       Police Powers and Zoning

          In addition to the requirements of the GMA and SMA, local governments possess their

own police powers, which are exercised in a variety of ways that may impact development of

renewable energy resources. For example, city and county governments frequently require major

projects to address impacts on traffic, roads, schools, and generally require building permits and

grading permits for any construction activity.

        For developers seeking a project permit, zoning is the most important exercise of these

police powers. Zoning is a tool of local police power authority that implements the community’s

vision of how it should develop. In communities that fully plan under the GMA, zoning and

other development regulations are subordinate to the comprehensive plan and implement local

land use policies it contains. Each jurisdiction in Washington has its own county, city, or

municipal code. These codes impose regulations on subjects such as land use, building and

construction, environmental protection and historic preservation, and may provide zoning

maps.66

        Planning and zoning can impact where clean energy project development may occur and,

where allowed, a special use permit is generally required, creating the consequences discussed

above. And, like any construction project, a clean energy project will have to pay impact fees

and address impacts on traffic, schools, and other local interests.

            4.       Criticisms of Local Permitting Processes

        Local opposition to renewable energy is growing nationwide, placing many areas of the

country entirely off limits to renewable energy development and creating permitting barriers,



66
  See e.g., Seattle Municipal Code, available at https://library.municode.com/wa/seattle/codes/municipal_code.
County and city codes and other relevant information is available on the website of the Municipal Research and
Services Center at https://mrsc.org/

                                                        31
delay and expense for developers seeking to expand the nation’s supply of carbon-free power.

An increasing number of localities, and at least two states, have made renewable energy

development off limits in their jurisdictions.67 Local opposition unchecked by any countervailing

emphasis given to statewide and nationwide goals for renewable energy development has

become a major impediment to the achieving the nation’s decarbonization goals.68

         Local opposition has become a major barrier to renewable energy development in at least

some Washington localities and in the EFSEC process, as well. These problems are not

universal. We have heard from many developers that Washington counties and cities have

successfully permitted some renewable energy projects with little delay or unnecessary burden.

Further, local permitting processes are generally faster and less burdensome than the EFSEC

process. In addition, local processes, if done well, can lead to reasonable accommodations of

local concerns while allowing renewable project development to proceed at the pace needed to

meet decarbonization goals.

         However, significant problems can arise in local permitting processes, often with little

warning. Among tactics that are strongly criticized by project proponents are:

      Unpredictable Moratoria: After a project application is received by a local government,
       that government enacts a moratorium of uncertain duration, placing the project in limbo
       and potentially killing it through delay.69 Project developers and permit specialists we
       interviewed cited several examples of this occurring both in Washington and in
       neighboring states. Columbia University’s Sabin Center on Climate Change Law recently



67
   A recent USA Today article includes an interactive map showing graphically the rapid rise of local restrictions on
renewable energy development. US Counties are Blocking the Future of Renewable Energy: These Maps, Graphics
Show How, USA Today (Feb. 4, 2024, updated Feb. 27, 2024).
68
   See, e.g, M. Eisenson, Sabin Center for Climate Change Law, Columbia Law School, Opposition to Renewable
Energy Facilities in the United States (May 2023 Ed.); I. Ko et al., Rural Backlash Could Impede Climate
Ambition, Univ. of Penn. Regulatory Review (Jan. 22, 2024).
69
   Counties and cities are permitted to enact moratoria for up to six months subject to public hearing. Moratoria can
be extended to one year if a work plan is developed for studying the issue given rise to the moratorium. A
moratorium can be extended for additional six-month periods subject to public hearing and appropriate findings of
fact. RCW 35A.63.200; RCW 36.70A.390.

                                                         32
         identified moratoria that have been imposed on solar development in Klickitat, Grant,
         Kittitas, and Yakima Counties.70

        Unreasonable conditions: Localities have attempted to place large zones off-limits to
         clean energy project development in the name of protecting, for example, farmlands and
         critical areas, with little heed either to statewide decarbonization goals or mitigation
         strategies that could avoid or minimize impacts to those areas. For example, one Pacific
         Northwest county imposed seven-mile buffer zones around multiple areas of concern,
         effectively making the county off-limits to renewable energy development. While the
         individual we interviewed did not identify the specific county referred to, we believe this
         likely refers to Douglas County, which adopted ordinances requiring energy generation
         facilities to “be located at least 7 miles from” urban growth boundaries, town or city
         limits, or the boundaries of local airports, and from “habitat associated with sensitive,
         candidate, threatened or endangered plants or wildlife as identified on state and federal
         lists.71

        Lack of Information: Local governments and local citizens often lack information about
         renewable energy developments, especially those involving new technologies like utility-
         scale battery storage. For local governments, the reaction can be to take drastic actions
         like placing moratoria on specific types of development as a means of ensuring that lack
         of information does not create unintended consequences for the local community. For
         local citizens, lack of information may lead to uninformed opposition, unnecessary delays
         in permitting, political pressure on officials to deny permits that they would otherwise
         approve, and litigation with little or no basis. For example, persistent rumors, apparently
         gleaned from internet conspiracy sites, suggesting that solar panels leach huge amounts
         of toxic chemicals have repeatedly appeared in solar energy permitting processes our firm
         has been involved with, despite reams of scientific evidence demonstrating that this
         concern is without basis. Lack of information can also lead to over-reaction when there is
         legitimate cause for concern. For example, utility-scale battery storage facilities, at least
         using certain batteries chemistries, present unique fire hazards. But the generally-
         accepted solution72 is to install protective firewalls and other protective equipment, to
         provide communications devices that alert plant operators and fire department personnel
         if hazardous conditions develop, and, if the local fire department lacks necessary training
         or equipment, providing funding for that training and equipment. An outright ban on
         these facilities, on the other hand, undermines electric reliability and grid resiliency for
         everyone.

        Public Participation Plans. Some but not all localities lack well-developed public
         participation policies, which can complicate permitting processes. Without a specific

70
   M. Eisenson et al., Opposition to Renewable Energy in the United States: June 2024 Edition, Sabin Center for
Climate Change Law (June 2024).
71
   DCC 18.16.355(B)–(C). These restrictions were addressed in EFSEC’s Land Use Inconsistency Order concerning
the Badger Mountain Solar Project. Order Finding Project Inconsistent With Local Land Use Regulations, EFSEC
Docket No. EF-210747, Order No. 881 (issued March 13, 2022).
72
   We note that Washington follows the International Fire Code. WAC 51-54A-003. Section 1207 of the
International Fire Code addresses fire hazards for electric energy storage systems.

                                                      33
       policy in place, developers are sometimes left to develop a process for notifying
       potentially affected parties with little guidance from the relevant governing body, which
       can lead to unnecessary distrust, opposition that arises late in the process, and even
       litigation over public notice requirements. In addition, one of the advantages of local
       processes repeatedly noted by developers we interviewed is that it helps developers
       identify community concerns and to develop appropriate mitigation measures and
       community benefits agreements. These processes can be unnecessarily complicated if a
       well-developed public participation plan is not in place.

      Local Benefits. While local communities should reasonably expect to benefit from
       development in their communities, there is little standardization of how community
       benefits are provided by developers. There is also concern that overly generous payments
       to individuals or communities impacted by project development will result in higher
       electric rates to consumers, which undercuts Legislative goals favoring least-cost energy
       planning, as well as undermining efforts to reduce energy burdens on disadvantaged
       communities.

   One example of an extremely drawn out local permitting process is Puget Sound Energy’s

Energize Eastside transmission project. Although the project involved relatively modest

upgrades – a single substation and upgrades to about 16 miles of transmission lines – the project

required Conditional Land Use permits from four different cities and a SEPA process that took

nearly three years. Altogether, obtaining the necessary permits took twelve years and the project

is only now beginning construction. As noted, HB 1812 provided an option for transmission

projects involving lines of 115 kV or more and passing through more than one jurisdiction with

land use or zoning ordinances to go through the EFSEC process rather than local processes, so an

effective EFSEC process offers hope of a shorter and more predictable permitting process.

       E.      The Consolidated Permitting Process

       The Legislature is cognizant that delays and inefficiencies in permitting imperil its

ambitious goals for addressing climate change. In response to these concerns, it has recently

adopted major legislation aimed at addressing permitting problems, including SB 1812,

discussed above, and several other bills, discussed in Appendix H. Of most importance, in 2023,



                                                34
the Legislature adopted HB 1216, which creates a new coordinated permitting process for “clean

energy projects,” defined broadly as discussed above.

         The Coordinated Permitting Process73 is voluntary process available to clean energy

projects that do not seek EFSEC approval. Ecology acts as the central point of contact using the

following process:

        Initial Assessment: Ecology must, within 60 days of receiving a request for treatment
         under the coordinated permitting process, conduct an initial assessment of the state and
         local permits required for approval of the proposed project, the information anticipated to
         be required, the level of anticipated SEPA review and the estimated time required for that
         review, and inform the applicant in writing of these determinations.

        Application: Following receipt of the initial assessment, a project proponent may submit
         an application to participate in the coordinated permitting process, which must include a
         detailed description of the proposed project, information on proposed mitigation
         measures, a description of the proponent’s efforts to engage with Tribes, local
         governments, and overburdened communities. If Ecology determines that the project
         “raises complex coordination, permit processing, or substantive permit review issues,”
         the project may be processed under the coordinated permitting process.

        Work Plan: Within 30 days of receiving a complete application that is eligible for the
         coordinated permitting process (or longer if agreed upon with the project proponent),
         Ecology must, in consultation with the project proponent, local government, and
         permitting agencies, develop a schedule for permit processing, and invite relevant federal
         agencies and Tribes to participate. Once the permitting schedule is complete, Ecology
         publishes the permitting process schedule, shares it with the project proponent,
         participating state agencies, the SEPA lead agency, participating cities and counties, and
         the public. Thereafter, if any agency is unable to meet a timeline in the work plan, it must
         notify Ecology and Ecology may amend the timeline or otherwise propose a solution to
         the delay.

        Coordination and Acceleration of Permitting: When a clean energy project is eligible for
         the coordinated permitting process, local governments are required to enter into an
         agreement with Ecology or the project proponent to expedite the permitting process and
         the project proponent must enter into a development agreement with the local
         government. Ecology must also facilitate in-depth consultations with Tribes and with
         state agencies with permitting responsibilities.


73
  See Ecology’s Clean Energy Coordinated Permitting Process page: https://ecology.wa.gov/regulations-
permits/sepa/clean-energy/clean-energy-coordinated-permit-process#:~:text=Ecology%20has%20established%
20a%20new,agencies%20may%20also%20be%20involved..

                                                   35
Other notable provisions of HB 1216 include:

   Nonproject Reviews: HB 1216 requires Ecology to prepare nonproject environmental
    impact statements (equivalent to a “programmatic EIS” under NEPA) for three types of
    clean energy projects, including projects with battery energy storage: green electrolytic or
    renewable hydrogen projects, utility-scale solar energy projects, and onshore utility-scale
    wind projects. The nonproject environmental impact statements are to consider issues
    common to developments of the specified types of renewable energy projects, including
    historic and cultural resources, protected species, landscape scale habitat connectivity and
    wildlife migration corridors, environmental justice and overburdened communities,
    cultural resources relevant to tribal rights, land uses, and military installations and
    operations. The scope of the nonproject reviews is to be developed by Ecology in
    collaboration with stakeholders, including Tribes. Clean energy project proposals that
    follow the recommendations of nonproject environmental reviews will be required to
    conduct environmental analyses only with respect to project-specific impacts and not to
    the general impacts address in the non-project reviews.

   Opportunity to Revise Application: After the applicant for a clean energy project submits
    the SEPA checklist, the lead SEPA agency provides an anticipated determination of
    significance and opportunity for the applicant to withdraw and revise the checklist so that
    the applicant might obtain an MDNS or DNS. If the lead agency determines that an EIS
    is required, it has 24 months to prepare the final EIS from the time of that determination.
    The time limit may be extended if the applicant agrees.

   Renewable Energy Zones: Based in part on the results of the nonproject environmental
    reviews, the ICESCC must recommend to the Legislature and Governor areas to
    designate as “clean energy preferred zones,” and to recommend regulatory, tax,
    environmental, and other benefits that should accrue to projects in these zones.

   Demonstration of Need: Prohibits local governments from requiring a demonstration of
    need for clean energy projects, although the applicant may be required to submit
    documentation from FERC, the UTC, or another relevant agency supporting the need for
    the project. Notably, several interviewees identified local requirements to demonstrate
    need for a project to be problematic for clean energy projects.

   Meteorological Equipment: Bars local governments from prohibiting the installation of
    wind and solar resource evaluation equipment necessary for the design and
    environmental planning of a renewable energy projects.

   Pumped Storage: Directs Washington State University’s energy program to carry out a
    process to identify issues and interests that may affect the siting of pumped storage
    projects. This is important because pumped storage is the only technology currently
    available to store electricity over a time horizon longer than several hours.




                                            36
        F.       The HEAL Act: Environmental Justice in Washington

        In 2021, Washington enacted the Healthy Environment for All Act (“HEAL Act”). The

HEAL Act aims to “reduce environmental and health disparities in Washington state and

improve the health of all Washington state residents,” and particularly to address communities of

color and low-income communities that bear a disproportionate share of environmental burdens.

For purposes of this report, the HEAL Act is important because it creates an additional layer of

review and a new set of considerations that must be addressed in the permitting process.

        The HEAL Act contains six key elements:

      Certain Washington agencies, generally those with significant permitting or other
       responsibilities related to overburdened communities, must incorporate environmental
       justice goals into decision-making. Other agencies may adopt those goals voluntarily.

      Agencies must develop equitable community engagement and public participation plans
       that incorporate overburdened communities into the decision-making process.

      Agencies must conduct environmental justice assessments when considering significant
       agency actions.

      The Environmental Justice Council (“EJC”) is created and tasked with advising agencies
       on incorporating environmental justice principles into agency activities.

      Agencies are required to consult with federally-recognized Tribes.

      Environmental justice principles must be incorporated into agency budgeting processes.

     The starting point for environmental justice analysis is the Environmental Health Disparities

map, a tool developed jointly by several Washington agencies, the University of Washington,

and public interest advocates.74 The HEAL Act provides funding to keep the Environmental

Health Disparities Map up to date.




74
  See https://doh.wa.gov/data-and-statistical-reports/washington-tracking-network-wtn/washington-environmental-
health-disparities-map.

                                                      37
       G.        Tribal Consultations

    Tribal consultations are a point of concern for project developers, state agencies, and the

Tribes themselves. Project developers and permitting consultants have expressed frustration in

finding the correct contacts for Tribes, and in Tribal issues often surfacing late in the permitting

process. State agencies share similar concerns, and also are concerned that, under the Centennial

Accord, many Tribes reasonably expect consultations to take place between the Tribe and the

Governor, which complicates agency consultation processes. Finally, there has been a surge of

interest in recent years for developing renewable energy projects on Tribal lands. Although

recent legislation mandated Tribal consultations in permitting and other processes, the mechanics

and timing of consultations remains problematic in many cases.

                 MODELS FOR REFORM FROM OTHER JURISDICTIONS

       We have reviewed siting laws from a number of other jurisdictions, including the

European Union, the U.S. federal government, and many states. We summarize below permitting

regimes that we believe should serve as models for Washington’s permitting reform efforts. The

states were chosen primarily because they face the same dilemma as Washington—they have

adopted aggressive decarbonization mandates, all requiring decarbonization of their state

economies by mid-century, but have realized that existing permitting practices create barriers to

constructing the infrastructure necessary to achieve these goals. We also include on example of a

reform that has failed, Ohio’s SB 52.

       A.        Federal Permitting Reforms

            1.     FAST 41 and the Federal Permitting Improvement Steering Council

                       a.      Background

       Enacted on December 4, 2015, the Fixing America’s Surface Transportation Act (“FAST

Act”) created the FAST-41 process and the Federal Permitting Improvement Steering Council

                                                 38
(“FPISC”) for project oversight.75 FAST-41 intends to improve early consultation and

coordination among government agencies, increase transparency through the publication of

project-specific timetables with completion dates for all federal authorizations and environmental

reviews, and increase accountability through consultation and reporting on projects. FPISC has

representatives from fifteen federal agencies.

         FAST-41 coverage provides project developers with a comprehensive, integrated federal

permitting timetable publicly posted on the federal infrastructure permitting dashboard. FAST-41

requires that agencies establish and maintain timetables and consult with the project developer

on any timing changes.

         Projects eligible for FAST-41 treatment include:

        Projects in one of eighteen “covered project” sectors76 that are (1) subject to NEPA; (2)
         likely to require a total investment of more than $200 million; and (3) do not qualify for
         an “abbreviated authorization or environmental review process” under an applicable law.

        Projects FPISC elects to cover, which must be: (1) subject to NEPA; and (2) of a size and
         complexity that makes it, in the opinion of FPISC, likely to benefit from enhanced
         oversight and coordination.

        Tribal-developed projects that are within one of the eighteen covered project sectors and
         are subject to NEPA, but the project need not meet the $200 million threshold.

        Infrastructure to support carbon capture and sequestration projects.

                           b.       FAST-41 Timeline

         The accelerated and monitored timeline is core to the FAST-41 program. A project

developer submits the notice of a proposed FAST-41 “covered project” to the FPISC executive



75
   Full text of the FAST Act is available here.
76
   “Covered project” sectors are renewable energy production, conventional energy production, electricity
transmission, surface transportation, aviation, ports and waterways, water resource projects, broadband, pipelines,
manufacturing, mining, carbon capture, semiconductors, artificial intelligence and machine learning, high-
performance computer and advanced computer hardware and software, quantum information science and
technology, data storage and data management, and cybersecurity.

                                                         39
director and facilitating agency. The executive director must add this project to the permitting

dashboard within 14 days of receipt unless the facilitating/NEPA lead agency determines the

project does not qualify. The facilitating agency must identify all federal and non-federal

agencies likely to have any review, financing, or permitting responsibility for the project and

invite them to participate within 21 days of the dashboard posting. A lead agency for NEPA

purposes must be identified within 60 days. States may opt in to participate in the FAST-41

process.

           The lead agency must establish a comprehensive permitting timetable based on the

executive director’s recommended performance schedule that includes intermediate and final

completion dates for action on all federal environmental reviews and authorizations to begin

construction.77 This timetable requires cooperating agency concurrence and the FPISC executive

director and Office of Management and Budget resolve timetable disputes. FPISC posts the

permitting timetable on the dashboard in accordance with interagency and project developer

consultation and public disclosure requirements.

           The FPISC executive director administers the timetable, including processing extension

requests and resolving interagency and developer issues. Agencies seeking to extend an agreed-

upon deadline must seek approval for the extension from FPSIC at least thirty days prior to the

deadline, which encourages agencies to carefully manage timelines. There is no specific deadline

in FAST-41 for final agency action, although the publication of timelines in the dashboard

encourages timely agency action and has provided Congress with clear information about

permitting timelines. These publications have informed a number of amendments to FAST-41

since it was initially adopted.


77
     The Permitting Dashboard can be found at https://www.permits.performance.gov/.

                                                        40
              2.       Regulatory and Permitting Information Desktop Toolkit

           The United States Department of Energy (“DOE”) developed the Regulatory and

Permitting Information Desktop (“RAPID”) toolkit to provide permitting information, best

practices, and reference material for renewable energy and bulk transmission project

development.78 The toolkit makes regulatory and permitting information accessible from a single

location by providing an overall analysis of the permitting process, centralized contact

information for federal and state regulators, best practice information, reference material, and

links to permit applications, manuals, and related information.

           Of note, as part of the RAPID Toolkit, the FPISC has identified best practices for

effectively permitting renewable energy and bulk transmission projects.79 These practices

include coordinating permitting for the projects, developing landscape-scale mitigation plans,

drafting memorandums of understanding (“MOU”) for interstate transmission siting, online

permitting systems, public involvement, purpose and need statements, and general tips.

              3.       Federal NEPA Reform

           Congress included NEPA reforms in the Fiscal Responsibility Act, passed in late May

2023. The new statute largely codifies practices that have been developed since NEPA’s

adoption in 1969, including a requirement that a lead agency be designated where two or more

federal agencies are involved.

           The new statute also imposed two important requirements. First, EISs are required to be

completed within 2 years after an agency determines that a proposed federal action will have

significant environmental impacts. Second, environmental assessments (“EA”) and EISs are




78
     The toolkit can be found at https://openei.org/wiki/RAPID.
79
     Available at https://openei.org/wiki/RAPID/Best_Practices?technology=Transmission.

                                                        41
limited to 75 and 150 pages, respectively, plus appendices, with limited exceptions for complex

projects.80

              4.    Nationwide Permits under the Bald and Golden Eagle Protection Act

        The FWS recently published a final rule creating general permits under the Bald and

Golden Eagle Protection Act (“BGEPA”) authorizing incidental take of eagles associated with

the operation of wind farms, power lines, and other activities. The FWS issues incidental take

permits upon the project applicant’s demonstration that eligible projects and power lines pose a

low risk of eagle take.

        For onshore wind, if turbines are located at least two miles from a golden eagle nest and

at least 660 feet from a bald eagle nest, any incidental take is automatically authorized up to

specific thresholds. Operators must conduct monitoring to examine eagle take and provide

adaptive management measures if the project exceeds take thresholds. For power lines,

applicants must develop either a reactive retrofit strategy, a proactive retrofit strategy, a collision

response strategy, or a shooting response strategy.81

              5.    Expanded NEPA Categorical Exclusions for Transmission

        The DOE issued a proposed rulemaking on November 16, 2023, to add categorical

exclusions for certain energy storage systems and to revise categorical exclusions for upgrading

and rebuilding transmissions lines.82 DOE establishes and revises categorical exclusions that are

supported by a record showing that actions normally do not have significant impacts,

individually or cumulatively. The proposed revisions would expand transmission categorical


80
   The President’s Council on Environmental Quality adopted regulations implementing these statutory changes on
May 1, 2024. CEQ, National Environmental Policy Act Implementing Regulations Revisions Phase 2, 89 Fed. Reg.
35442 (May 1, 2024).
81
   Final rule available at https://www.govinfo.gov/content/pkg/FR-2024-02-12/pdf/2024-02182.pdf.
82
   Proposed rule available at https://www.federalregister.gov/documents/2023/11/16/2023-25174/national-
environmental-policy-act-implementing-procedures.

                                                      42
exclusions to a class of actions normally requiring an EA, and to a class of actions normally

requiring an environmental impact statement. If implemented, the categorical exclusion for

upgrading and rebuilding existing powerlines would truncate the permitting timeline and greatly

expedite the permitting process. Recent studies indicate that new technologies could, using this

process, significantly expand the capacity of the existing transmission system without requiring

major construction.83

           6.       EPA Permitting Dashboard

        On April 2, 2024, EPA announced that it will launch a new centralized website,

epa.gov/permits, that will display the status of EPA permits for large scale infrastructure

projects, as well as providing centralized information about EPA permitting programs,

environmental justice permitting information, and information about funding provided to EPA

under the Inflation Reduction Act to improve its permitting efficiency.84

           7.       Conservation Leasing

        On May 9, 2024, the Bureau of Land Management (“BLM”) published the Public Lands

Rule, which aims to protect and restore public lands using science and data-based decision-

making processes. The rule was enacted partly pursuant to the BLM’s statutory mandates to

manage public lands “under principles of multiple use and sustained yield” under 43 U.S.C.

1732(a) and to “take any action necessary to prevent unnecessary or undue degradation” of

public lands under 43 U.S.C 1732(b).




83
   E.g., U.S. Department of Energy, Pathways to Commercial Liftoff: Innovative Grid Deployment (April 2024); M.
O’Boyle et al., Supporting Advanced Conductor Deployment: Barriers and Policy Solutions, GridLab & Goldman
School of Public Policy, University of California at Berkeley (April 9, 2024).
84
   News Release, EPA Launches New Website to Improve Transparency in Permitting (April 2, 2024) (available at
https://www.epa.gov/newsreleases/epa-launches-new-website-improve-transparency-permitting).

                                                      43
        To carry out its statutory mandate, and most relevant for renewable energy project

development, the rule establishes two types of conservation leases: restoration leases and

mitigation leases. Qualified individuals, businesses, non-governmental organizations, Tribal

governments, conservation districts, and State fish and wildlife agencies may use restoration and

mitigation leases to restore public lands or to mitigate impacts from authorized activities on

public lands. These leases will be issued and overseen directly by the BLM and will not interfere

with existing rights, or state or Tribal land use management. Restoration and mitigation leases

also will not preclude subsequent uses of lands so long as those uses are compatible with the

leased restoration or mitigation activities.

        Renewable energy developers will most likely apply for mitigation leases in instances

where projects proposed on public lands present unavoidable impacts to wilderness or recreation

resources. In such cases, the BLM may determine that compensatory mitigation is appropriate

and lease an area in a different location to the developer in order to protect or restore resources

for the duration of a project’s impacts.

        Conservation leases under the Public Lands Rule complement the BLM’s Renewable

Energy Rule, published on May 1, 2024. According to the BLM, that final rule “reduces acreage

rents and capacity fees, improves the BLM’s application process, and delivers greater

predictability for how the BLM will administer future solar and wind project authorizations.”

           8.       Federal-State Modern Grid Deployment Initiative

        In May 2024, the Biden-Harris Administration launched the Federal-State Modern Grid

Deployment Initiative (the “Initiative”).85 The Initiative recognizes that deployment of new



85
  Federal-State Modern Grid Deployment Initiative, WHITE HOUSE (May 2024), https://www.whitehouse.gov/wp-
content/uploads/2024/05/Federal-State-Modern-Grid-Deployment-Initiative-Principles_formatted.pdf; Fact Sheet:
Biden-Harris Administration Launches Federal-State Initiative to Bolster America’s Power Grid, WHITE HOUSE

                                                      44
transmission assets—necessary to meet growing energy demands and accommodate the

deployment of new generation—requires a significant amount of time and resources. It therefore

promotes state and federal cooperation to achieve additional capacity on the existing grid via

installation of high-performance conductors and Grid Enhancing Technologies (“GETs”). GETs

include dynamic line ratings, a blanket term encompassing technologies and methodologies that

assess real-time data to determine, and optimize, line capacity.

        21 states have signed on to the Initiative: Arizona, California, Colorado, Connecticut,

Delaware, Hawai’i, Illinois, Kentucky, Maine, Maryland, Massachusetts, Michigan, New Jersey,

New Mexico, New York, North Carolina, Oregon, Pennsylvania, Rhode Island, Washington, and

Wisconsin. In exchange for policy, technical, and analytical assistance from the federal

government, these states have committed to prioritizing the adoption of modern grid solutions to

increase capacity on existing infrastructure.

        To achieve the goals of the Initiative, $10.5 billion in competitive grant funding has been

made available through the Grid Resilience and Innovation Partnership (“GRIP”) program.86 The

Initiative complements other recent transmission-modernization efforts, including FERC’s Order

1920, which mandates long-term regional transmission planning and requires transmission

providers to consider the use of advanced conductors and GETs in their planning processes.87




BRIEFING ROOM (May 28, 2024), https://www.whitehouse.gov/briefing-room/statements-releases/2024/05/28/fact-
sheet-biden-harris-administration-launches-federal-state-initiative-to-bolster-americas-power-grid/.
86
   Fact Sheet: Biden-⁠Harris Administration Announces Key Actions to Strengthen America’s Electric Grid, Boost
Clean Energy Deployment and Manufacturing Jobs, and Cut Dangerous Pollution from the Power Sector, WHITE
HOUSE BRIEFING ROOM (April 25, 2024), https://www.whitehouse.gov/briefing-room/statements-releases/
2024/04/25/fact-sheet-biden-harris-administration-announces-key-actions-to-strengthen-americas-electric-grid-
boost-clean-energy-deployment-and-manufacturing-jobs-and-cut-dangerous-pollution-from-the/; Grid Resilience
and Innovation Partnerships (GRIP) Program, DEPARTMENT OF ENERGY GRID DEPLOYMENT OFFICE,
https://www.energy.gov/gdo/grid-resilience-and-innovation-partnerships-grip-program. (last visited May 31, 2024).
87
   Fact Sheet: Building for the Future Through Electric Regional Transmission Planning and Cost Allocation,
FEDERAL ENERGY REGULATORY COMMISSION (May 13, 2024), https://www.ferc.gov/news-events/news/fact-sheet-
building-future-through-electric-regional-transmission-planning-and.

                                                       45
        B.       State Permitting Reforms

        Several states with aggressive decarbonization timelines like those adopted in

Washington have recently enacted permitting reforms aimed at speeding the development of

renewable energy and other infrastructure projects necessary to achieve these states’

decarbonization goals. We here briefly describe the legislation, as well as proposed legislation

that is worthy of notice.

        Several states have adopted processes similar to Washington’s EFSEC process. The

following chart summarizes the laws governing those states’ processes:

 STATE                  Agency          Standard for       Preemption of          Other            Time Limit
                                           Action              Local             Permits           for Action?
                                                            Ordinances?        Required?
 California          State Energy         Yes (PRC           Yes (PRC         Possibly (PRC         Certification
                      Resources           25545.8,          25545.1(b))       25545.1(b)(2))       process must
                     Conservation         25545.9)                                                  be complete
                          and                                                                         within 270
                     Development                                                                        days of
                     Commission88                                                                     complete
                                                                                                     application
                                                                                                         (PRC
                                                                                                     25545.4(e))
 Connecticut          Connecticut       Yes (R.C.S.A.        No (Conn.              Yes           One year after
                        Siting           § 16-50j-59)        Gen. Stat. §                             complete
                       Council89                             16-50t(b))                           application for
                                                                                                    transmission
                                                                                                  lines, 180 days
                                                                                                     for all other
                                                                                                       facilities
                                                                                                    (Conn. Gen.
                                                                                                  Stat. § 16-50p)




88
   Cal. Public Resources Code (“PRC”) § 25545, available at https://leginfo.legislature.ca.gov/faces/codes_
displayText.xhtml?lawCode=PRC&division=15.&title=&part=&chapter=6.2.&article=.
89
   Connecticut General Statutes (“Conn. Gen. Stat”) chapter 277a, available at https://www.cga.ct.gov/current/pub/
chap_277a.htm#sec_16-50j; Regulations of Connecticut State Agencies (“R.C.S.A.”) title 16, available at
https://eregulations.ct.gov/eRegsPortal/Browse/getDocument?guid={409EE155-0200-C014-8F51-
8588DD14E405}.

                                                        46
 Massachusetts      Energy                 Yes (980             Yes (164        No (164 MGL           Six months
                    Facilities            CMR 6.03;            MGL 69K)             69K)             from date of
                    Siting Board90        164 MGL                                                      complete
                                            69O)                                                      application
                                                                                                      (980 CMR
                                                                                                        6.05(1))
 Michigan              Michigan           Yes (MCL             Yes (MCL          Potentially       One year after
                     Public Service      460.1226(7))          460.1231)           (MCL               a complete
                     Commission91                                               460.1231(5))        application is
                                                                                                      filed (MCL
                                                                                                    460.1226(5))
 Minnesota            Minnesota           Yes (Minn.           Yes (Minn.        Yes (Minn.        Final decision
                    Public Utilities        Stat. §              Stat. §           Stat. §         on application
                    Commission92          216E.03(7))          216E.10(1)        216E.10(2))       within 60 days
                                                                                                    of ALJ report
                                                                                                    (Minn. Stat. §
                                                                                                     216E.03(9))
 New                Site Evaluation       Yes (RSA §               No               Yes,              Within one
 Hampshire           Committee93           162-H:16;                             application           year after
                                         N.H.A.R. Site                          must contain           receipt of
                                            301.03)                             evidence of            complete
                                                                                    other             application
                                                                                 applicable        (N.H.A.R. Site
                                                                               permits (RSA              301.12)
                                                                                § 162-H:7-a,
                                                                                 162-H:16;
                                                                               N.H.A.R. Site
                                                                               301.03(c)(6)b)
 New York             Office of          Several (N.Y.          Yes (N.Y.         No (N.Y.         Six months to
                     Renewable            Exec. Law §          Exec. Law §      Exec. Law §          one year,
                    Energy Siting94      94-c[3](b); 19          94-c[6])       94-c[4], [6])      depending on
                                                                                                    project (19

90
   Massachusetts General Laws (“MGL”) chapter 164 § 69H, available at https://malegislature.gov/Laws/
GeneralLaws/PartI/TitleXXII/Chapter164; Code of Massachusetts Regulations (“CMR”) title 980, available at
https://www.mass.gov/law-library/980-cmr.
91
   Michigan Compiled Laws (“MCL”) Chapter 460.1221–32, available at https://www.legislature.mi.gov/Laws/
MCL?objectName=MCL-460-1226-ADDED.
92
   Minnesota Statutes (“Minn. Stat.”) § 216E, available at https://www.revisor.mn.gov/statutes/cite/216E; Minnesota
Administrative Rules (“Minn. R.”) chapter 7854, available at https://www.revisor.mn.gov/rules/7854/. On March 7,
2024, Minnesota introduced HF 4700, which requires the state to transition to a carbon-free electric grid by 2040. If
adopted, the statute would replace Minnesota’s existing permitting system with expedited processes under “major”,
“minor”, and “local” review standards. The statute also provides for expedited review of permits for minor
alterations and exempts certain smaller projects. The current version of the bill is available at https://www.
revisor.mn.gov/bills/bill.php?f=HF4700&y=2024&ssn=0&b=house.
93
   New Hampshire Revised Statutes Annotated (“RSA”) § 162-H, available at https://www.gencourt.state.nh.
us/rsa/html/XII/162-H/162-H-mrg.htm; New Hampshire Administrative Rules (“N.H.A.R.”) Site 100, available at
https://www.gencourt.state.nh.us/rules/state_agencies/site100-300.html.
94
   New York Executive Law (“N.Y. Exec. Law”) § 94-c, available at https://www.nysenate.gov/legislation/
laws/EXC/94-C; 19 New York Codes, Rules and Regulations (“N.Y.C.R.R.”) Part 900, available at https://ores.ny.
gov/system/files/documents/2020/09/draft-regulations-chapter-xviii-title-19-subparts-900-1-900-5-900-7-900-
14.pdf.

                                                          47
                                         N.Y.C.R.R. §                                              N.Y.C.R.R. §
                                            900-2)                                                    900-9.1)
 Ohio                 Ohio Power          Yes (ORC            Yes (ORC            No (ORC            Ninety days
                     Siting Board95        4906.10)           4906.13)           4906.13(B))       after receipt of
                                                                                                      complete
                                                                                                     application
                                                                                                        (ORC
                                                                                                    4906.03(E))
 Oregon             Energy Facility     Several (ORS           Effectively        No (ORS             Varies by
                        Siting          469.501; ORS        (ORS 469.401;        469.401(1))        project (ORS
                      Council96         469.503; OAR           “applicable                           469.370(9))
                                        345-022-0000           substantive
                                        through 0120;            criteria”
                                        OAR 345-025-             include
                                         0500, 0580;         ordinances in
                                        OAR 345-023-         effect on date
                                            0000)           of application.
                                                            OAR 345-022-
                                                                  0030)
 Rhode Island       Energy Facility        Yes, and            Effectively       No, agencies      Final decision
                    Siting Board97       decision sent          (advisory          provide           within sixty
                                         to legislature      opinions sent        advisory             days of
                                        to be affirmed       by other state     opinions (R.I.     conclusion of
                                        (R.I.G.L. § 42-        agencies or       Gen. Laws §        final hearing
                                           98-11(c))         zoning boards      42-98-7(a)(2))        (R.I. Gen.
                                                             do not need to                        Laws § 42-98-
                                                              be followed,                              11(c))
                                                            R.I. Gen. Laws
                                                            § 42-98-11(c))
 Vermont              Vermont               Yes (30           Yes (City of      No (24 V.S.A          No stated
                    Public Utilities        V.S.A. §              South          § 4413(b))           timeline
                    Commission98            248(b))          Burlington v.
                                                            Vermont Elec.
                                                               Power Co.,
                                                              Inc., 133 Vt.
                                                            438, 344 A.2d
                                                             19 (1975); 24
                                                              VSA § 4413
                                                                   (b))
 Washington         Energy Facility        None –                  Yes                No           One year from
                        Siting          Recommendati                                                 receipt of

95
   Ohio Revised Code (“ORC”) Chapter 4906, available at https://codes.ohio.gov/ohio-revised-code/chapter-4906.
96
   Oregon Revised Statutes (“ORS”) Chapter 469, available at https://www.oregonlegislature.gov/bills_laws/ors/
ors469.html; Oregon Administrative Rules (“OAR”) Chapter 345, available at https://secure.sos.state.or.us/oard/
displayChapterRules.action?selectedChapter=79.
97
   Rhode Island General Laws (“R.I.G.L.”) § 42, available at http://webserver.rilin.state.ri.us/Statutes/TITLE42/42-
98/INDEX.HTM; Rhode Island Code of Regulations (“R.I.C.R.”) title 445, available at https://ripuc.ri.gov/sites/g/
files/xkgbur841/files/efsb/EFSB2/SB2018_05_Rule_Practice.pdf.
98
   Title 30 Vermont Statutes Annotated (“V.S.A.”) § 248, available at https://legislature.vermont.gov/statutes/
section/30/005/00248.

                                                         48
                     Evaluation            on to            (RCW               (RCW             complete
                     Council99          Governor          80.50.110)         80.50.120)        application
                                          (RCW                                               (80.50.100(1)(
                                        80.50.100)                                                 a))


         We now describe permitting reforms adopted in several states we view as particularly

useful models, involving both EFSEC-style processes and other processes.

           1.       California

         Recognizing the need to expedite permitting of renewable energy facilities and

supporting infrastructure, California in 2022 adopted AB 205, which includes provisions that

centralize permitting of critical facilities and subject the permitting process to specific deadlines.

         California’s expedited permitting process has the following features:

        Eligible facilities: The new permitting process is available to:

         o Solar and wind generation with a capacity of 50 MW or more and appurtenant
           facilities, as well as facilities with a capacity of 50 MW or more using any source of
           thermal generation other than fossil fuels or nuclear power.

         o Energy storage systems with a capacity of 200 MWh or more.

         o “Discretionary projects,” which are those requiring a capital investment of at least
           $250 million and that will manufacture or produce components or specialized
           products used in renewable generators or energy storge projects.

         o Electrical transmission lines carrying power from a covered renewable generator or
           storage project to a point of interconnection with the existing electric transmission
           system.

        Centralized Authority: Developers of eligible projects may submit an application to the
         State Energy Resources Conservation and Development Commission, more commonly
         referred to as the California Energy Commission (“CEC”), to have their application
         treated in accordance with AB 205. Certain small renewable projects may also seek CEC
         certification. The CEC is empowered to permit construction of such facilities, and the
         permit is “in lieu of any permit, certificate or similar document required by any state,
         local, or regional agency, or federal agency to the extent permitted by federal law,”100

99
   Chapter 80.50 Revised Code of Washington (“RCW”), available at https://app.leg.wa.gov/RCW/default.aspx?
cite=80.50&full=true.
100
    Cal. Public Resources Code § 25545.1(b)(1).

                                                     49
           although the authority of regional water quality and air quality boards remain, as does the
           permitting authority of certain agencies regulating coastal development. Projects subject
           to the CEC process must also pay lease fees to the State Lands Commission if their
           projects occupy state lands.

          Specific timelines: AB 205 imposes a number of specific deadlines on the CEC. The CEC
           must, within 30 days of receiving an application, determine whether the application is
           complete and, if not, notify the project developer of any deficiency. The project
           developer must respond within thirty days and the application is considered complete
           immediately upon receipt of the requested information. The certification process must be
           completed within 270 days after the application is deemed complete, although the
           deadline may be extended under limited circumstances. For example, the timeline can be
           extended if the project developer proposes substantial changes to the project, new
           information comes to light that could not have been known when the project application
           was accepted, or additional time is necessary to conduct required surveys.

                   Within the 270-day period, the CEC is required to conduct a public outreach
           process. It must conduct an initial public information meeting between ten and thirty days
           after the application is deemed complete, and a public workshop in the community
           nearest the project must be conducted within 60 days. A meeting to scope the project’s
           environmental impact analysis must be conducted within 30 days of when the project
           application is complete, and a hearing must be held 30 to 60 days after notice that the
           draft environmental report is complete. Some of these meetings can be combined. The
           CEC must certify the environmental report within 30 days after it is finalized.

                   Native American Tribes that are “culturally and traditionally associated with” the
           project’s geographic location must be notified and a tribal consultation process must
           follow. In addition, the CEC “shall take feasible measures to avoid or minimize adverse
           impacts to tribal cultural resources.”101

          Protections for Local Interests: AB 205 declares eligible projects to be projects of
           statewide significance and the state interest is sufficiently strong to justify preemption of
           local regulation. Nonetheless, several protections for local interests are built into the law.
           First, as noted above, the CEC is required to notify local governments in the project area,
           and they may participate in the CEC process. Second, the CEC may not approve a project
           unless it determines that the project will produce “an overall net positive economic
           benefit to the local government.”102 In addition, the project developer is required to enter
           into a community benefits agreement that will provide benefits to the local community,
           that must include job training and other economic benefits, and may also address benefits
           to local amenities such as parks.




101
      Cal. Public Resources Code § 25545.9
102
      Id.

                                                    50
         Labor Protections: The project developer must also enter into an agreement with a
          relevant organization to assure that prevailing wages are paid, that an apprenticeship
          program is in place, and that other labor protections are observed.

         Appeals: AB 205 requires the California Judicial Council to adopt court rules requiring
          appeals of CEC decisions under that law to be completed within 270 days of the filing of
          the CEC’s certified administrative record with the reviewing court.

            2.      New York

          In 2020, the State of New York enacted the Accelerated Renewable Energy Growth and

Community Benefit Act,103 which created an Office of Renewable Energy Siting (“ORES”) to

provide a consolidated permitting process for renewable energy projects in the state. ORES is

charged with developing uniform standards and conditions for each category of renewable

energy project within its purview that are designed to “avoid or minimize, to the maximum

extent practicable, any potential significant adverse environmental impacts related to the siting,

design, construction and operation of” large renewable generators.104 These uniform standards

and conditions are intended to identify the environmental impacts of each major source of

renewable energy (e.g., solar, wind, geothermal, energy storage) and to provide generic standards

for the developers of each type of project to meet.

          In addition, once an application is received from project developer, ORES is required to

review the site-specific environmental impacts of the project and, to the extent possible,

condition the project to avoid those impacts or, if the impacts cannot be avoided, to mitigate

them through established programs for off-site mitigation. This includes a requirement to achieve

“a net conservation benefit to any impacted endangered or threatened species,” which can be

achieved by off-site mitigation.105



103
    The Act was included as Part JJJ of SB 9508-B.
104
    N.Y. Exec. Law § 94-c(3)(c), replaced by Section 138 of the RAPID Act.
105
    N.Y. State Fin. Law § 99-hh(3), replaced by Section 138 of the RAPID Act.

                                                       51
          On April 20, 2024, New York further clarified ORES’s responsibilities through adoption

of the RAPID Act.106 The RAPID Act moves ORES to the New York Department of Public

Service and replaces much of the language discussed above with new statutory text clarifying

ORES’s various responsibilities.

          Other key elements of New York’s program include:

         Eligible Projects: Renewable energy projects, including appurtenant facilities and
          transmission tie lines up to ten miles in length, are required to go through the ORES
          process if they have a capacity of 25 MW or more. Projects of between 20 and 25 MW
          may voluntarily seek to use the ORES process. Projects that are subject to a federal
          licensing scheme (primarily hydroelectric power projects) are exempt, and the New York
          State Department of Environmental Conservation retains its authority to issue permits
          where it has been authorized to do so under a federal environmental law such as the
          Clean Air Act or Clean Water Act.

         Deadlines: ORES has 60 days to determine if an application is complete and, if it is not,
          it must notify the project developer in writing within 60 days of any deficiency. If it fails
          to meet this deadline, the application is deemed completed. Within 60 days after the
          application is complete, ORES must initiate a public hearing process that includes
          notification of relevant local agencies and newspapers and publication of the notice on
          ORES’s website. ORES has one year from the date the application is deemed complete to
          issue or deny a permit for construction, with the deadline reduce to six months if the
          project is proposed for a brownfield, landfill, abandoned energy generation site, or former
          commercial or industrial site. A parallel provision of the statute requires the New York
          Public Service Commission to complete its review of major utility-developed
          transmission projects within one year of receiving a complete application, subject to
          limited exceptions allowing an extension of the one-year period. The period is reduced to
          nine months for transmission constructed within existing rights of way, including
          transportation and canal rights of way as well as transmission and distribution rights of
          way, subject to expansion of the right of way if necessary to meet regulatory
          requirements.

         Local Regulation: As part of the ORES process, ORES examines whether the project
          complies with relevant local laws and regulations. After receiving notification, a local
          agency may submit a statement addressing whether the proposed project complies with
          local laws and regulations. ORES may hold a hearing to decide that question. If the
          project meets local requirements, ORES may approve the project. If it does not, ORES
          may exempt the project from local requirements if it concludes that the local
          requirements are unreasonably burdensome and are inconsistent with New York’s

106
  The RAPID Act was enacted as part of budget legislation. The statute is contained in Article VII, Part O, of the
budget enactment.

                                                        52
        decarbonization goals, which are similar to Washington’s. ORES must require the project
        developer to enter into a community benefit agreement with the host community.

       Fee: Applicants are required to pay fees to support processing of their applications, with
        the size of the fee based on the size and type of project. Fees are deposited in an account
        dedicated to fund local agencies who wish to intervene in the ORES process.

       Development Incentives: The New York law authorizes the New York State Energy
        Research & Development Authority (“NYSERDA”) to develop a program aimed at
        providing incentives for development of renewable energy facilities on previously-used
        land and on sites that are difficult to develop consistent with applicable law. Under this
        program, NYSERDA can undertake the process of permitting projects on such sites, then
        sell the site, along with permits and other necessary land and transmission rights, in
        “shovel ready” condition to private developers. NYSERDA can also provide incentives to
        local communities and property owners to encourage them to accept renewable energy
        developments.

       Environmental Mitigation: The legislation establishes a mitigation bank fund for
        threatened and endangered species, funded by ORES applicants with a relevant
        mitigation requirement included in their permit to construct. The fund is intended to
        provide a readily-accessible mitigation alternative for project developers whose projects
        may affect threatened or endangered species and those impacts cannot be avoided
        through conditions on the project.

       Agricultural Lands: The RAPID Act adds a requirement for several state agencies, along
        with local governments, agricultural groups, and interested parties to, within one year,
        develop recommendations for the protection and minimization of impacts to agricultural
        lands in the ORES process.

           3.      Illinois

        In early 2023, Illinois enacted legislation aimed at limiting overly restrictive local zoning

ordinances on development of renewable energy in the state. The Illinois legislation, HB 4412,

takes a much different approach than the bills in New York or California. Rather than

centralizing the permitting process in a single state authority, the Illinois bill places limitations

on how local agencies can regulate wind or solar energy development.

        HB 4412 amends Illinois’s Counties Code, which is the statute providing regulatory

authority to county governments, to define the maximum limits of their authority to regulate

commercial-scale wind and solar projects. For solar projects, counties are permitted to establish a

                                                  53
setback of 150 feet from occupied dwellings and 50 feet from public rights of way, but may not

establish more restrictive setbacks. Counties may require the solar farm to be surrounding by a

fence of between six and 25 feet and may require vegetative screening of the solar site, but may

not require earthen berms.

        For wind energy, the permitted setbacks are based on the wind generators’ maximum

blade height. Setbacks from occupied buildings and wildlife areas are limited to 2.1 times blade

height, and setbacks from homes of residents that have contracted with the project developer for

an easement or other land right are 1.1 times blade height. Counties may limit shadow flicker in

occupied buildings to 30 hours per year. Blade height restrictions may not be more restrictive

than those established by the FAA.

        Counties are barred from prohibiting renewable energy through moratoria, and may not

prohibit development on agricultural lands, although they may require solar developers to follow

guidelines for pollinator preservation and other standard agrovoltaic practices. Counties may

charge fees and impose construction conditions on renewable energy developers only if the fees

and conditions are consistent with fees and conditions that are imposed on other types of

development in the county.

        Counties must hold a hearing on a renewable energy project within 45 days after

receiving a complete application and must make a determination on the application within 30

days after the hearing. The County may require wildlife mitigation if consistent with

recommendations made by state and federal wildlife officials based on standard mapping

protocols.107


107
   On May 21, 2024, Colorado Gov Polis signed SB 24-212, which provides technical assistance to Colorado Tribes
and counties by providing model codes and similar resources to govern renewable energy and transmission
development. In 2023, Colorado passed legislation easing permitting barriers to rooftop and behind-the-meter solar
generation. See Colorado HB23-1234 (signed May 11, 2023).

                                                       54
          4.     Michigan

       In November 2023, to be effective on November 29, 2024, Michigan enacted HB 5120.

The new statute creates a process by which the Michigan Public Service Commission (“MPSC”)

may preempt local laws and regulations that unduly restrict renewable energy development.

      Eligible Facilities. The Michigan statute applies to solar facilities with a nameplate
       capacity of 50 MW or more, wind facilities with a nameplate capacity of 100 MW or
       more, and energy storage facilities with a nameplate capacity of 50 MW or more and an
       energy discharge capacity of 200 MWh or more. In each case, the facility is defined to
       include all appurtenant facilities, including generation tie lines, access roads, wires,
       foundations, and the like.

      Local Government Consultation: A project developer may voluntarily seek local
       government approval using the following process: the project developer, with at least 30
       days advance notice which must include the facility site plan, holds a public meeting in
       the relevant locality. At least 60 days before the public meeting, the project developer
       must offer to meet with the chief elected official of the relevant local authority. If the
       elected official notifies the project developer that it has a compatible ordinance, the
       project developer may file for approval with that ordinance. The local government
       agency must approve or deny the application within 120 days after receipt, which may be
       extended up to an additional 120 days if both the project developer and the local
       government agree.

                The applicant may file an application with the MPSC if: (a) the local government
       fails to act within the 120-day deadline; (b) if the proposal meets defined setbacks and
       other requirements specified in the statute (which are very similar to the standards
       specified in Illinois) but the local government denies the application anyway, which
       makes the statutory standards the most restrictive that can be adopted by the local agency;
       or, (c) the local government amends the applicable ordinance after the local government
       has notified the project developer that a compatible local ordinance is available.

      MPSC Application: As an alternative to the local consultation process (although MPSC
       may order the project developer to go through the local consultation process), the project
       developer may submit an application to the MPSC. The application must include
       information covering a broad range of issues, including efforts the project developer has
       undertaken to consult with local agencies and environmental regulators, evidence of the
       project’s impact on telecommunications signals, stormwater management plans,
       emergency response plans, and decommissioning plans, including minimum financial
       assurances.

      Deadlines. The MSPC has 60 days to determine if the application is complete and, if it
       fails to notify the applicant in writing of any deficiencies within the 60-day window, the


                                               55
       application is considered complete by default. The MPSC must make a final decision
       within one year of receiving the final application.

      Deposits. The project developer must make a one-time grant of up to $75,000 per
       affected local government, not to exceed $150,000 in total, to allow affected local
       governments to participate in the required administrative hearing before the MPSC.

      Granting the Application: The MPSC “shall grant the application and issue a certificate”
       if it determines that seven specific criteria are met. These are:

           o That the public benefits of the project, to include tax benefits, community
             benefits, job creation, and energy benefits, justify construction.

           o That the project complies with Michigan’s Natural Resources and Environmental
             Protection Act.

           o That the applicant has considered and addressed impacts to environmental
             concerns, including sensitive habitats and waterways, wetlands, floodplains,
             parks, historic sites, and threatened and endangered species.

           o The applicant has entered into required community benefits agreements and labor
             agreements.

           o The applicant will meet U.S. Department of Labor apprenticeship requirements,
             will pay prevailing wages, and, to the extent permitted by law, will enter into a
             project labor agreement or collective bargaining agreement.

           o The project will not “unreasonably diminish” farmland, including prime farmland.

           o The project does not present an unreasonable threat to health and safety. This
             requirement is met if the project meets the setback and other requirements set
             forth in the statute.

      If the MPSC issues a certificate, local zoning ordinances are preempted.

          5.      Minnesota

       Minnesota passed, and Governor Walz signed, a sweeping package of climate laws in

2023, including requiring the state to generate 100 percent of its electricity from carbon-free

sources by 2040. In May of 2024, Governor Walz signed the Minnesota Energy Infrastructure




                                                56
Permitting Act.108 The act reduces procedural requirements, consolidates environmental review

authority for energy projects to the Minnesota Public Utilities Commission, limits certain

contested case hearings, and exempts all wind and solar projects and some transmission lines

from the requirement to obtain a certificate of public convenience and necessity, which is

otherwise required for electricity infrastructure.

        Site and Route Permit Process: The act divides site and route permitting into “major” and

“standard” review processes. At least 30 days prior to submitting an application, an applicant

must notify affected local governments, affected Tribal governments, and state technical

resource agencies and seek preapplication feedback. The commission must determine whether an

application is complete within ten working days of its receipt and hold public hearings and

receive comments thereafter. Under Major Review, the commission must make a final decision

on an application within one year of the date it determines an application is complete, and within

six months of a complete application determination under standard review. Standard review is

available for projects less than 80 MW, natural gas facilities, certain high voltage transmission

lines, solar facilities, wind facilities, and energy storage facilities.

        Certificates of Need: Minnesota requires a certificate of need issued by the public utility

commission prior to the construction of large energy facilities. The act modifies the definition of

“large energy facility” with respect to transmission lines. A certificate of need is required for

lines with a capacity of 300 kV or more and greater than one mile in length in Minnesota, or with

a capacity of 100 kV or more and greater than ten miles of length or that crosses a state line. The

act also retains certificate of need exemptions for wind and solar facilities and adds exemptions




108
   Available at https://www.revisor.mn.gov/bills/text.php?number=SF4942&type=bill&version=4&session=ls93&
session_year=2024&session_number=0.

                                                    57
for energy storage systems and transmission lines that directly interconnect wind or solar

facilities.

              6.     State Energy Authorities

          Three Western states have recently created energy authorities that are aimed at promoting

new and renewable technologies such as carbon capture and advanced nuclear generation,

improving transmission planning, identifying transmission corridors, and providing information

to project developers aimed at reducing conflicts that might otherwise slow or halt project

permitting. New Mexico established its Renewable Energy Transmission Authority in 2007,109

Wyoming created the Wyoming Energy Authority in 2020,110 and Colorado created the Colorado

Electric Transmission Authority in 2021.111 While each of these authorities have unique

characteristics, they were all formed to promote the development of electric transmission and to

encourage the development of renewable energy resources.

          These state authorities each:

         Engage in transmission planning activities aimed at promoting renewable energy and
          economic development and increasing grid reliability.

         Identify and establish electric transmission corridors within the relevant state, working
          with other states and the federal government to coordinate development of transmission
          corridors.

         Promote non-wires alternatives and new transmission technology to maximize the
          efficient use of the existing transmission system, including in at least one case the use of
          energy storage to reduce transmission loads.

         May issue government bonds to support transmission and other projects and may collect
          fees and other charges from operating or leasing facilities in order to finance future
          projects.




109
    NM Stat. Chapter 62, Art. 16A; https://nmreta.com/.
110
    See Wyo. Stat. Ann. § 37-5-502 et seq.; https://wyoenergy.org/.
111
    Colo. Stat. Ann. Title 40, Art. 42.; https://www.cotransmissionauthority.com/.

                                                         58
         May exercise the power of eminent domain to acquire property for rights of way
          necessary for the construction of linear facilities like transmission lines.

         May enter into partnerships with public or private entities to develop projects. The
          Colorado Transmission Authority is considered a “provider of last resort,” which steps in
          to build priority transmission projects when no other developer is willing to step in.

         Provide information to developers, landowners, and other interested parties. The
          Wyoming Energy Authority, for example, provides guides to the permitting process for
          wind and solar developers. The Wyoming authority also provides studies and other
          support for alternative technologies like geothermal power and for new technologies like
          hydrogen.

            7.      Track Record to Date

          Because these laws are recent, none have an extensive track record. However, a recent

study concluded that the New York process has worked well, with the eight renewable energy

projects reviewed through ORES taking less than eight months on average to receive a permit,

with only one taking a full year.112 On the other hand, a recent report from New York’s

Comptroller, which reviewed 15 projects reviewed by ORES found that, while the time to review

completed applications took one year or less, the time from initial application until an application

is deemed complete was generally much longer, an average of three years. The Comptroller

recommended that the time from initial application to issuance of a permit, as well as the time

from final application to permit, be tracked.113 We have been unable to locate any quantitative

analyses of the other state laws we discuss above, but anecdotal evidence gathered through our

interviews suggests that the processes in Illinois and California have improved permitting

timelines significantly.




112
    J. Arnold & M. Beck, Canadian Climate Institute, Permitting reform for clean energy projects in New York and
California Promising changes at the state level may hold useful lessons for Canada (Nov. 14, 2023)
113
    Office of the New York State Comptroller, Office of Renewable Energy Siting: Application Review and Site
Permitting for Major Energy Projects, Report No. 2023-S-52 (April 2024).

                                                       59
            8.       A Negative Example: Ohio

        Major energy facilities in Ohio obtain permits through the Ohio Power Siting Board

(“OPSB”), a body similar to EFSEC. Like EFSEC, an OPSB permit preempts any local laws or

ordinances that would interfere with construction of an energy facility that is supported by a

demonstration of statewide need. Before 2021, OPSB’s authority extended to permitting utility-

scale wind and solar generators. In 2021, Ohio enacted SB 52, which requires the proponent of a

wind or solar facility to submit an application to the county or counties where the facility will be

located and provides the counties an opportunity to respond by declaring all or parts of their

counties off-limits to renewable energy development. Notably, SB 52 does not apply to other

types of energy facilities, such as fossil-fired generators and petroleum pipelines.

        The result has been a near-total elimination of utility-scale renewable generation in Ohio.

Many counties have declared all or large parts of their counties off limits to renewables

development, which has slowed renewable energy development to a crawl. In 2022, only five

applications for utility-scale renewable projects were filed in Ohio and, in 2023 that number

dropped to four.114 Notably, a number of these projects filed applications with the OPSB before

SB 52 was enacted, so were not subject to the same local restrictions that applied to applications

for projects submitted after SB 52’s effective date.




114
   B&D has represented the Allen-Auglaize Coalition for Reasonable Energy, a local citizens group supporting
renewable energy development in Ohio, on a pro bono basis. We assisted the Coalition in proceedings before the
OPSB and now the Ohio Supreme Court concerning the Birch Solar project, a utility-scale solar generator. Although
the OPSB concluded that Birch Solar met every substantive statutory requirement for, for example, protection of the
environment and historical resources, the OPSB nonetheless rejected Birch Solar’s application solely on the basis of
local opposition. The OPSB’s decision has been challenged in the Ohio Supreme Court, and the Allen-Auglaize
Coalition, along with a diverse group of amicus curiae including the Ohio Chamber of Commerce, the Ohio
Manufacturer’s Association, and the Ohio Environmental Council, have filed briefs supporting reversal of the
OPSB’s decision.

                                                        60
       C.      European Union Renewable Energy Directive

       The European Union’s Renewable Energy Directive (“Directive”), entered on November

20, 2023, is a legal framework developed with the overall goal of obtaining 42.5% of energy in

the European Union from renewable sources by 2030.

       While the Directive includes a variety of requirements and tools to achieve this goal,

most relevant to permitting is developing a framework for expediting permitting of renewable

energy projects. The Directive highlights a need to streamline administrative procedures and

develop staffing and expertise so as to facilitate relationships between governments and

developers.

       The directive targets “Renewables Acceleration Areas” (“RAAs”), areas particularly

suited for renewable energy development, which are eligible for streamlined permitting. The

Directive requires Member States to develop plans for the development of specific types of

renewable energy projects, with the aim of minimizing environmental impact. These areas,

which should avoid protected regions and incorporate restoration and mitigation measures, are

tailored to the requirements of the renewable technologies they host, with the combined size of

these areas being sufficient to meet the needs of the chosen technologies.

       The Directive also focuses on the procedures for projects that are not part of these

renewable acceleration areas. It directs member states to adopt permitting procedures that do not

exceed two years, except in cases of offshore renewable energy projects. It also directs member

states to adopt a single procedure that combines all relevant assessments for any particular

renewable energy project. The Directive also directs member states to adopt similar streamlining

procedures for solar energy projects, associated storage, and heat pumps.




                                                61
                         PERMITTING REFORM RECOMMENDATIONS

          Based on the recommendations contained in the Low-Carbon Siting Report, legislation

from other jurisdictions discussed in Section IV, the many studies we have reviewed,115

interviews we have conducted,116 and the recommendations contained in previous reports issued

by Washington agencies, we recommend the following reforms to Washington’s permitting

processes.

          At the outset, however, we note that we do not recommend changes to the basic structure

of Washington’s permitting system: that is, the three options currently available to entities

seeking to permit clean energy infrastructure and clean energy product manufacturing facilities

in Washington should remain: EFSEC, Ecology’s Coordinated Permitting Process, and the local

county/city process. Project developers should remain free to choose the permitting path that best

fits their project. Further, the legislation recently adopted in Washington, discussed in Section

III, contains many desirable features and we propose retaining those but building on them.

          Our specific recommendations are:

          A.      Across-the-Board Reforms

          Several reforms are recommended for all permitting processes.

         Personnel: We heard from project developers, permitting consultants, and permitting
          agencies alike that permitting agencies lack sufficient personnel to address the volume of
          project applications they are expected to process. In addition, project developers and
          permitting consultants consistently criticized permitting agencies for lack of expertise in
          project management and energy project development, resulting in uncoordinated and
          unnecessarily lengthy permitting processes. To address this concern, all permitting
          agencies should:

               o Hire Sufficient Personnel. Agency staffing should be optimized by hiring
                 sufficient personnel to address the volume of project applications reasonably
                 expected to be received by that agency. To the extent agencies experience spikes

115
  A list of studies we have reviewed for this report is provided in Appendix F.
116
  A list of the entities whose employees or representatives we have interviewed for this report is provided in
Appendix G.

                                                         62
                 in applications, they should be authorized to retain consultants to assist in
                 processing those application spikes, with the option for applicants to pay for the
                 necessary consultants.

             o Hire/Train Project Managers. To coordinate permitting processes by ensuring
               that all involved agencies are working in tandem and according to schedule,
               employees with expertise in project management should be hired and salaries
               should be high enough to retain these individuals. In addition, the state should
               consider project management training programs that would allow current
               employees, who often have deep expertise in areas related to clean energy project
               permitting, to acquire project management expertise.

             o Hire/Train Consultation Specialists. In light of emerging federal and state
               policies related to environmental justice and reducing environmental and
               economic burdens on overburdened communities, most notably the HEAL Act,
               the state should encourage hiring of individuals with experience and cultural
               understanding to engage Tribal, people of color and overburdened communities.
               In addition, the State should provide training to existing staff on best practices for
               engaging these communities.117

             o Budget Line Item. Agencies with permitting responsibilities should submit
               budget line items for their permitting functions. This helps assure policy-makers
               that the agencies have adequate resources to carry out permitting responsibilities
               and also ensures that permitting budgets are not raided to pay for other agency
               priorities.

             o Shared understanding of costs and resourcing adequately. Agencies with
               permitting responsibilities should have clear, up-to-date, and justifiable budgeting
               documentation for their permitting functions and should submit budget requests to
               meet demand as needed. Policy-makers and agencies should have a shared
               understanding of the costs and resource needs to enact permit policies; and the
               legislature should allocate adequate resources for agencies to carry out permitting
               responsibilities.

         SEPA Reforms. To ensure that the SEPA process is as efficient as possible while still
          attaining SEPA’s goals, all SEPA processes should:

             o Lead Agency. The lead agency for SEPA purposes should be identified within
               fourteen days of submission of the SEPA checklist.

             o Acceptance of SEPA Checklist. The lead agency should, within 30 days after
               receipt of the SEPA checklist, identify deficiencies and any additional
               information that is required and notify the project proponent of those deficiencies.

117
   See, e.g., Community Engagement Values and Guidance Adopted by the Environmental Justice Council (August
25, 2023).

                                                    63
                  Within 7 days of receiving the additional information, the lead agency should
                  determine whether the information is sufficient and inform the project proponent.
                  Additional information submissions should follow the same 7-day process. To
                  coordinate HEAL Act requirements with SEPA, environmental justice concerns
                  should also be addressed in the checklist.

             o Determination of Significance. Within 60 days of receiving a complete SEPA
               checklist, the lead agency should inform the project proponent of its
               determination whether the project threatens significant environmental impacts that
               require a full EIS. With the information in hand, the project proponent should be
               permitted to revise its proposal to avoid the identified impacts, either through
               project redesign or mitigation, so that the project can receive a determination of
               non-significance or mitigated determination of non-significance.118

             o EIS Deadlines and Length Limitations. If a project requires an EIS, the EIS
               process, including any required environmental justice assessment, should be
               completed in all cases in no more than 24 months.119 For projects employing a
               technology or system for which a nonproject environmental review has been
               performed, the EIS process should be limited to site-specific impacts that have not
               been addressed in the non-project review, and should be completed in no more
               than six months and limited to no more than 150 pages plus appendices. Similar
               time and page limits should apply to projects constructed on brownfields, existing
               rights of way, or other areas that are already significantly disturbed. These
               deadlines may be extended with the project proponent’s agreement, which allows
               the proponent to, for example, account for delays in obtaining transmission
               interconnection rights and also to ensure that a record is developed that will pass
               muster in an appeal of a permit decision.

             o Upfront Disclosure. Building on existing pre-application processes, project
               proponents and permitting agencies should be required to engage Tribes,
               localities, and overburdened communities through disclosure of proposals and
               potential impacts. Agencies, Tribes, and non-governmental organizations or
               individuals with concerns about a project, in turn, should be encouraged to
               identify those concerns as early as possible in the process. All such concerns
               should be identified in the pre-application process and scoping process. Concerns
               that are not identified in those stages should not be considered in later stages of
               analysis unless the party attempting to raise a new issue or facts demonstrates that



118
    Currently, RCW 43.21.033 requires the threshold determination to be made within 90 days, subject to certain
exceptions. For “clean energy projects,” RCW 43.21C,530(2)(a), requires that, prior to making its determination of
significance, the lead agency provide the applicant with a written statement anticipating its significance
determination and allow the applicant to withdraw and revise its application. The lead agency has thirty days after
the resubmission to revise its significance determination unless the applicant has substantially changed its project.
119
    HB 1216 added a deadline of twenty-four months from the determination of significance for completion of the
EIS for clean energy projects, with an additional extension of up to 24 months if the applicant agrees and the revised
schedule is publicly posted. RCW 43.21C.530(3)

                                                         64
                 the concerns could not reasonably have been discovered and identified in the pre-
                 application or scoping process.

             o Social Cost of Carbon. To ensure that the value of GHG reductions is accurately
               reflected in SEPA processes, all SEPA and environmental justice analyses (and
               other analyses involving GHGs such as utility integrated resource planning)
               should incorporate the Social Cost of Carbon if the analysis involves a project that
               could either significantly reduce or significantly increase GHG reductions. The
               Social Cost of Carbon is a science-based metric that identifies the per-ton cost of
               GHG emissions arising from climate impacts like sea level rise, increasingly
               violent weather, and droughts. To ensure uniformity, the Social Cost of Carbon as
               determined by the federal Interagency Working Group on the Social Cost of
               Carbon should be used in all SEPA analyses.

             o Nonproject Environmental Reviews. In addition to those already mandated by
               HB 1216, responsible agencies should continue to conduct non-project
               environmental reviews for renewable energy technologies or clean technologies
               that are likely to be deployed at multiple sites across the state. Such technologies
               might include, for example, electric generation fueled by biomass or biogas and
               emerging carbon capture technologies, such as the geological storage technology
               developed by the Pacific Northwest National Laboratory that sequesters carbon
               deep in basalt formations, which are common across much of Washington.120

          The timelines suggested above are already included in the Coordinated Permitting

Process via HB 1216, except for the six-month time limit for brownfield sites, which is borrowed

from New York’s legislation. Shorter timelines for completion of the environmental assessment

process are included in legislation from several other states discussed above and the 24-month

limit has been adopted here in Washington in HB 1216, in federal NEPA reform legislation, and

in the European Union. In addition, the suggested page limits mirror the page limits adopted in

recent federal legislation reforming NEPA.

         Standardized Mitigation. For projects with unavoidable impacts, standardized mitigation
          requirements should be developed for both environmental and environmental justice
          impacts. For example, mitigation for loss of wetlands through wetlands mitigation banks
          – that is, where the project causes the loss of some wetlands, the project proponent pays
          for specified acreage to be added to a wetlands restoration project – is a well-recognized
          form of mitigation. Where possible, the responsible Washington agencies should develop
120
   See Courtney Flatt, Could the Northwest’s basalt rocks help slow climate change? Oregon Public Broadcasting
(June 4, 2023) (available at: https://www.opb.org/article/2023/06/04/could-the-northwests-basalt-rocks-help-slow-
climate-change/).

                                                        65
          standard mitigation measures based on the best available science and in consultation with
          all interested communities. For example, New York provides a mechanism for project
          developers to fund wildlife protection measures where impacts to threatened or
          endangered species cannot be avoided. In Washington, mitigation for renewable energy
          development in the Columbia Basin could take the form of purchasing marginal farmland
          or degraded sage steppe habitat,121 that would then be restored to support ecosystem
          functions, with a specific acreage ratio (for example, two acres of restoration for each
          acre disturbed, similar to common wetlands mitigation requirements) required. Other
          examples might include: (1) mitigation measures for farmland used for solar
          developments based on agrivoltaics,122 as appropriate for growing conditions in our state,
          and newly-adopted legislation123 encouraging pollinator habitat in landscaped areas; and,
          (2) for unavoidable impacts on anadromous fish habitat, mitigation through support of
          restoration of riparian areas, which are critical habitat for juvenile fish.

         Expanded Use of Standardized Permits and Categorical Exclusions. The USFWS
          recently issued nationwide permits governing protection of raptors under the BGEPA and
          allied legislation, as discussed above. WDFW should adopt these, or similar standard
          permits, because they allow renewable energy projects to proceed without further
          permitting if the projects meet the conditions specified in the permit and the conditions
          are supported by NEPA analysis. Those conditions are developed to assure protection of
          the species if the specified conditions are met. Similarly, the U.S. Department of Energy
          recently revised its list of categorical exclusions, which exempt the excluded activities
          from environmental review, to address new technologies like energy storage and
          advanced technologies that allow existing transmission lines to carry increased power
          flows. Similar categorical exclusions should be adopted under SEPA to allow deployment
          of these kinds of technologies.

         Standards and Protocols for Environmental and Cultural Surveys. One complaint we
          have heard from a number of developers and consultants is that expectations for how
          field surveys are to be conducted are unclear, resulting in repeated redos of surveys, with
          attendant expense and delay. To address this, responsible Washington agencies should set
          forth and abide by clear standards and protocols for field surveys and environmental
          justice analyses. One example of such guidance recommended to us by a project
          developer is the Minnesota Department of Natural Resources’ recently-issued
          Commercial Solar Siting Guidance document.

         Consolidated Permits. The Legislature has directed the ICESCC to pursue development
          of consolidated clean energy permits similar to the Joint Aquatic Resource Application

121
    As discussed above, the Biden Administration’s recent public lands initiative would allow conservation leasing
on BLM lands. Because significant portions of the sage steppe ecosystem in Washington are located on BLM lands,
this offers a new opportunity for developers to lease and preserve sage steppe habitat, or to restore degraded habitat
on leased public lands.
122
    See, e.g., U.S. Department of Energy, Solar Energy Technologies Office, The Potential of Agrivoltaics for the
U.S. Solar Industry, Farmers, and Communities (April 17, 2023) (available at: https://www.energy.gov/eere/solar/
articles/potential-agrivoltaics-us-solar-industry-farmers-and-communities).
123
    SSB 5934, signed by Gov. Inslee on March 28, 2024.

                                                         66
           and also to explore consolidated clean energy permits.124 We generally believe such
           consolidated permitting processes increase the speed and efficiency of permitting, but we
           have not further analyzed these options because they are outside the scope of this report.

           B.      Permitting Oversight and Information Clearinghouse

           We recommend the adoption of several measures that are aimed at improving the

permitting process at all levels. These functions could reasonably be housed in Governor’s

Office for Regulatory Innovation and Assistance (“ORIA”) or in the ICESCC, if those bodies are

provided with any necessary legislative authorization and are given sufficient personnel and

resources to carry out these functions. We refer to the agency that would be assigned these

project oversight functions as the “permitting oversight body.” Another alternative worthy of

consideration would be the creation of a cabinet-level Department of Energy, Climate, and the

Environment, that would house this and other agencies with responsibilities relevant to energy

and climate.

           The functions assigned to the permitting oversight body are aimed at improving pre-

application and other upfront processes to surface potential problems as much as possible before

a final permit application is filed, and to support Tribes, local government agencies, and

interested individuals by providing information and technical support related to clean energy

projects.

           The specific functions performed by the permitting oversight body would include:

           (a) Washington Permitting Dashboard

           Implement a Washington State permitting dashboard based on the federal FAST-41

model. The dashboard would:

           o Track the progress of all proposed clean energy projects through the permitting
             process, with the possible exception of smaller generators (under 20 MW capacity,

124
      RCW 43.394.020(3)(b)-(c).

                                                   67
                for example) moving through local permitting processes. A state permitting
                dashboard establishes deadlines and provides transparency to the public, stakeholders,
                and lawmakers that keeps agencies accountable and assists the legislature in
                identifying areas of improvement for permitting. In addition, the dashboard will
                reveal agencies that are chronically late in meeting permitting deadlines and
                corrective action, such as assigning management personnel to ensure timely action or
                providing additional resources, can be taken.

           o Require state agencies involved in a project subject to the FAST-41 process to
             participate in the federal dashboard applicable to such projects. Currently, state
             agencies are allowed to participate in the FAST-41 process, but are not required to do
             so.

           o Guided by a project management expert, include specific deadlines for each involved
             agency to act, coordinate agency actions involving studies to avoid duplication and
             minimize the time required for studies, and designate individuals from each involved
             agency to be responsible for that agency’s involvement in a particular project. If an
             agency anticipates that it will not meet a deadline, it may seek an extension but must
             do so at least thirty days prior to the deadline. Deadlines would include: a specific
             date by which an agency must declare an application complete or else seek additional
             information from the applicant, deadlines to complete all required environmental
             analysis consistent with other deadlines recommended below, coordinate with state
             and federal agencies involved in environmental analysis to ensure the maximum use
             of existing information (notably including information developed in ongoing non-
             project environmental analyses) and minimize duplication of information
             requirements, and final deadlines for each agency to act.

           (b) Information Clearinghouse

           To assist project developers, local governments, Tribes, and the public in understanding

the technical aspects of clean energy infrastructure, to help identify sites that are most likely to

be free of conflicts, and to maximize the value of pre-application procedures, the permitting

oversight body would provide the following services:

           i.      Mapping. A great deal of mapping information already exists, including, for

           example, DNR’s clean energy screening function,125 Washington State University’s work




125
      DNR Clean Energy Parcel Screening website, https://www.dnr.wa.gov/cleanenergymap.

                                                       68
        on the least-conflict solar process,126 similar work done by federal agencies,127 and maps

        identifying protected lands, private lands, lands with high potential for renewable energy

        development, existing transmission lines, etc. In addition, both the state and federal

        governments have published maps identifying environmental justice communities.128

        This information should be gathered in one place to create a one-stop shop to help project

        developers identify sites that will present the lowest potential for conflict, and to assist

        state and local agencies, Tribes and other interested parties to identify areas of concern

        and suggest measures to avoid or mitigate those concerns as early in the process as

        possible, and to identify overburdened communities that must be taken into account in

        project planning and assessment, as well as assisting developers to address environmental

        justice requirements. Of course, appropriate measures will need to be in place to protect

        confidential information (locations of sensitive Tribal cultural resources, for example). In

        addition, to the extent conflicting maps exist – we have heard from developers that

        habitat maps for sensitive species, for example, sometimes conflict – the permitting

        oversight body would work to resolve these conflicts and provide definitive maps.

        ii.      Least-Conflict Process. Building on the least-conflict work already carried out by

        Washington State University with respect to solar development on the Columbia

        Plateau,129 the permitting oversight body should convene appropriate sets of stakeholders




126
    Washington State University Energy Program, Report to the Washington Legislature: Least-Conflict Solar Siting
on the Columbia Plateau (June 2023);
127
    See, e.g., BLM Solar Energy Zones website: https://blmsolar.anl.gov/competitive/other-procedures/sez/
128
    See, e.g., Washington Environmental Health Disparities Map website: https://doh.wa.gov/data-and-statistical-
reports/washington-tracking-network-wtn/washington-environmental-health-disparities-map.
129
    See note 123, supra.

                                                       69
         and Tribes to identify least-conflict areas for other clean energy technologies and in other

         parts of the state if those technologies are likely to be deployed widely across the state.130

         iii.     Renewable Energy Zones. Using maps, areas that have been identified by state

         and federal land management agencies for priority renewable energy development, input

         from interested Tribes and stakeholders, and the results of the mapping and least-conflict

         processes recommended above, the permitting oversight body would identify Renewable

         Energy Zones, areas characterized by strong solar, wind or other renewable resources,

         that can be linked to existing transmission infrastructure with relatively modest effort,

         and that have the least potential for conflict in the permitting process. The permitting

         oversight body could be delegated authority to name Renewable Energy Zones or it could

         recommend to the Legislature new Renewable Energy Zones beyond those that the

         Legislature may designate in response to recommendations required from the ICESCC by

         Section 302(7) of HB 1216. Renewable energy development would then be prioritized in

         these zones by, for example, transmission development facilitated by the Washington

         Renewable Energy Authority (discussed below), preparation of non-project

         environmental analyses covering the zones, and other measures to expedite permitting in

         these zones.

         iv.      Technical Assistance. Many local governments, members of the public (including

         members of overburdened communities), and Tribes have expressed concerns that they

         lack expertise and understanding of renewable energy and clean economy technologies.

         The permitting oversight body would collect information on technologies that are most




130
   The Legislature recently mandated a similar process to help identify desirable sites for geothermal energy
development. See SB 6039, signed by Gov. Inslee on March 28, 2024.

                                                         70
commonly being sited in Washington, including information gleaned from non-project

environmental reviews, and provide that information to interested parties through its

website, with assistance provided to understand the information where needed. The

permitting oversight body would also provide expert advice to local governments and

Tribes concerning these technologies, including potential environmental impacts and

common mitigation measures.

v.     Pre-Application Roundtable. For projects in the planning and pre-application

phase of development, the oversight body should provide contact information for key

government bodies, Tribes, community-based organizations, non-governmental

organizations, and other interested parties, to facilitate early resolution of potential

disputes. For Tribes that prefer government-to-government contact rather than direct

contact with project developers, a mechanism is needed to ensure that there is a

consistent and reliable conduit for communications with the Tribe that are relevant to a

proposed project. In addition, the oversight body should assist willing developers by

identifying known issues in the proposed project area that might create permitting

problems, and by facilitating meetings with the project developer and all interested

parties to identify and seek mutually agreeable solutions to objections that might

otherwise slow or derail the permitting process. Early, voluntary resolution of disputes is

much preferred by all parties as a way to avoid, for example, formal EFSEC

adjudications on disputed issues, which are expensive and time consuming, and can

create unpredictable outcomes.




                                          71
          vi.    Community Engagement.

                 (a) Community Benefits and Labor Agreements. The permitting oversight body,

          with assistance from interested organizations and individuals, would also provide

          guidance to project developers and overburdened communities by developing a database

          of standardized community benefits agreements and labor agreements, as well as tracking

          the costs to project developers and consumers, and benefits of these agreements, and

          determining whether benefits are reaching the intended beneficiaries. The oversight body

          would also provide mediation services where necessary to facilitate agreements between

          project developers and community representatives.

                 (b)     Facilitation Services: The oversight body would provide project

          proponents and agencies with guidance on best practices for engagement with Tribes,

          overburdened communities, and local agencies. Where necessary, the oversight body

          would provide translation services to ensure that immigrant communities and other

          communities with a substantial number of non-native English speakers can be fully

          represented in the permitting process.

          C.     EFSEC Reforms

          Building on the changes to EFSEC enacted in SB 1812,131 we recommend the following

additional changes to RCW Chapter 80.50:

         Standard for Project Approval: To set a clear statutory standard that developers must
          meet and for when EFSEC must approve a project, we recommend new language, based
          on language contained in the statutes for EFSEC equivalents in several states (Michigan,
          California, New York) and the Legislature’s statement of intent in RCW 80.50.010. The
          following language would be added to RCW 80.50.100 as a new subsection 3:


131
   Section 1 of SB 1812 added language to the Legislature’s statement of intent for EFSEC (RCW 80.50.010) that
EFSEC should, for example, “encourage the development and integration of clean energy sources” in Washington.
But intent language is merely precatory and we recommend mandatory language clarifying how EFSEC should
exercise its authority.

                                                      72
       The Council shall recommend that the Governor approve an application for an alternative
       energy resource, a clean energy manufacturing facility, or an electric transmission facility
       if:

       (a) The public benefits of the applicant’s project, including the benefits of greenhouse
       gas reductions (as measured using the social cost of carbon as determined by the federal
       Interagency Working Group on the Social Cost of Carbon), tax benefits, community
       benefits, job creation, and energy benefits, justify construction;

       (b) The applicant’s project avoids, minimizes, or mitigates, to the maximum extent
       practicable, any potential significant adverse environmental impacts related to the siting,
       design, construction and operation of the project;

       (c) The applicant’s project avoids or minimizes to the maximum extent practicable, any
       potential significant adverse impacts on historical, archaeological, and cultural resources;

       (d) The project, including mitigation measures, provides a net positive impact with
       respect to threatened and endangered species that are reasonably expected to be affected
       by the project;

       (d) The applicant has entered into community benefit or labor agreements, or has
       otherwise taken measures, to assure that the project minimizes impacts to overburdened
       communities and vulnerable populations, as those terms are defined in RCW 70A.02.010,
       and that a reasonable share of the project’s environmental and economic benefits are
       provided to overburdened communities and vulnerable populations in the vicinity of the
       project;

       (e) The applicant’s project does not present an unreasonable threat to health and safety,
       which standard shall be met if the project meets the requirements of the local standards
       specified [RCW cite to legislation discussed below – proposal to limit local discretion on
       renewable projects]; and,

       (f) The applicant has agreed to reasonable requirements for project decommissioning that
       ensure, to the maximum extent practicable, that project components are reused,
       refurbished, or disposed of in a manner consistent with state and federal requirements for
       waste disposal or recycling, and that lands affected by the project are restored to their
       pre-project condition to the maximum extent practicable.

Additional recommendations include:

      Reformulate EFSEC Governing Body: As noted, EFSEC is governed by a group of
       agencies with specific missions. Many observers believe that, because the agency lacks
       an independent director body charged with balancing the state’s overarching goals with
       respect to clean energy against the goals of the agencies, EFSEC tends to pursue the
       statutory missions of these agencies to the maximum extent, without adequate
       counterbalance for statewide goals such as clean energy development. This balancing

                                                73
          function should be assigned to a specific individual or body within EFSEC that is
          independent of both the agencies involved in regulating proposed projects and the
          developers seeking to permit projects. We recommend that this function be assigned to
          one to three paid directors with significant experience in the energy industry and with
          related permitting issues, to be appointed by the Governor with the advice and consent of
          the Senate. The requirements would be similar to those governing the Pollution Control
          Hearings Board. RCW 43.21B.020. The director(s) would be tasked with making the
          final decision under the standard set forth above, based on input from all agencies,
          Tribes, local governments, individuals, and other interested parties involved in a
          particular application.

         Adopt Clear Standards: A common complaint about the EFSEC process is that it lacks
          clear standards and instead relies on a drawn-out SEPA process to develop permit
          conditions that are often arrived at on an ad hoc basis, creating great uncertainty for
          project developers. To address this problem, in addition to the statutory language set forth
          above, we recommend that EFSEC develop technology-specific standards that spell out
          specific requirements for, for example, wind energy projects, battery storage projects, and
          pumped storage projects. The Oregon Energy Facilities Council has adopted such
          standards,132 which may serve as a template for revised EFSEC standards.133 In addition,
          EFSEC should adopt standardized mitigation measures, as discussed above.

         Standard Reforms: EFSEC should adopt the time limits, page limits, and other reforms
          to the SEPA process discussed above. It should also employ standardized “nationwide”
          permits (like those recently adopted for raptors by the USFWS), standard mitigation
          procedures, and standardized survey protocols to the greatest extent possible. Finally, all
          EFSEC projects should be included in the Washington Permitting Dashboard.

         Minimize Contested Adjudications: A common denominator in EFSEC processes that
          have been successful in issuing recommendations within the one-year statutory timeline
          appear to be successful upfront resolution of disputes through, for example, revisions to
          project proposals to avoid a SEPA determination of significance or informal resolution of
          disputes. To encourage this approach, we propose two changes to the EFSEC statute.
          First, the current statute requires that, before the Council issues its recommendation to the
          Governor, it hold a public hearing “conducted as an adjudicative proceeding under
          chapter 34.05 RCW, the administrative procedure act.” Given that the record has already
          been developed at this stage, in many cases there is no good reason to require a formal
          adjudication, which involves formal briefing, judicial-style procedural rules, formal
          testimony, cross-examination, and other procedures typical of a court trial. The statute
          should be amended to allow EFSEC to make its determination based on a non-
          adjudicative public hearing. Any amendment should, of course, allow EFSEC the
          discretion to conduct adjudicative hearings where necessary to resolve legal or other

132
   See OAR Chapter 345, Title 24.
133
   As noted above, EFSEC recently developed a standard application for solar facilities that may serve as a useful
model that can be expanded to other clean energy technologies. However, we have been unable to access sufficient
information about the solar application to make any specific recommendation about it.

                                                        74
       disputes that require quasi-adjudicative processes. Second, EFSEC should offer
       mediation services employing a trained mediator to encourage opposing parties to come
       to agreement on specific concerns so as to minimize the use of formal adjudications to
       resolve disputes. Adjudications were generally disfavored by both applicants and others
       involved in EFSEC processes because they are expensive and time-consuming, with
       unpredictable outcomes since disputes are resolved by a hearing officer’s opinion.
       EFSEC could either retain its own trained mediation staff, similar to the model used at
       FERC and other federal agencies with similar quasi-adjudicative processes, where a
       mediation staff is available to help parties voluntarily resolve disputes. Another
       alternative would be for a dedicated and trained mediation staff to be developed through
       the Office of Administrative Hearings that could be available to other agencies, as well as
       EFSEC.

       D.     Local Government Reforms

      Based on recent legislation adopted in Illinois, Michigan and other states, we recommend

that the Legislature enact limits on the burdens local governments can impose on renewable

energy developments, that would include:

       Maximum Setbacks/Buffers. Local governments would be permitted to require
        setbacks or buffers up to a maximum but no more. For example, counties would be
        permitted to establish a setback for solar projects of up to 150 feet from occupied
        dwellings and for wind projects, require a setback of up to two times maximum blade
        height from occupied dwellings, but no more. Similarly, local governments would be
        permitted to impose the same buffers on such facilities as it imposes on other
        developments to protect critical areas such as wetlands, but would not be permitted to
        impose larger buffers.

       No Moratorium. Except for specific technologies that are not addressed through
        legislation, local governments would not be permitted to establish moratoriums on
        renewable energy projects, electric transmission projects, or clean energy product
        manufacturing facilities, but could require those projects to pay impact fees, obtain
        construction and grading permits, and impose other requirements on the same basis as
        the local government treats other developments. Local governments would also be
        required to allow meteorological towers and other equipment and processes necessary
        for identifying sites with strong renewable energy potential, with conditions imposed
        on these activities no more restrictive than conditions imposed on other similar
        activities. For technologies that are not addressed specifically by legislation, moratoria
        would be limited to the time reasonably necessary for local governments to gather
        necessary information to address the proposals, but in no case more than one year.

       Agricultural Lands. Local governments would not be permitted to bar energy
        developments on all agricultural lands, but could limit development on the highest-
        value agricultural lands. In addition, local governments would be permitted to require

                                                75
            mitigation measures consistent with statewide requirements for, for example,
            agrivoltaics and preservation of pollinators,134 and for decommissioning and restoration
            of farmlands after a project reaches the end of its useful life.

           Time Limits. Local governments would be required to process permits for smaller
            renewable energy projects (25 MW capacity or below) within 60 days and within 120
            days for larger projects.135

           Transmission Corridors. Local governments would be required to permit construction
            and operation of electric transmission facilities, lines to carry renewable natural gas,
            and other linear facilities necessary for clean energy projects on corridors identified by
            the Washington Renewable Energy Authority. Local governments would be permitted
            to impose conditions on transmission, including construction of generator tie lines, that
            are no more restrictive than conditions imposed on similar kinds of construction.

          E.      Washington Renewable Energy Authority

      Based on models from New York, New Mexico, Wyoming, and Colorado, we recommend

that Washington create a Renewable Energy Authority (“WREA”) with the following powers:

         Transmission Planning & Coordination: WREA would work with other states, the
          Bonneville Power Administration, regional transmission planning bodies, Canadian
          authorities, and relevant federal agencies to identify planned transmission projects that
          may reach Washington or support transmission of renewable energy into Washington,
          and to participate in the process of developing National Interest Electric Transmission
          Corridors (“NIETCs”) 136 in the Pacific Northwest. WREA would work with these other
          agencies and bodies to ensure that transmission corridors developed in Washington will
          connect with these regional transmission lines in a manner that best serves Washington
          electricity consumers. WREA would be empowered to enter into Memorandums of
          Understanding or other appropriate contracts with these entities to promote development
          of a cohesive transmission network. WREA should particularly focus on ensuring that
          adequate transmission is available to import renewable energy from regions outside the
          state that are likely to be important renewable energy sources. This would include, for
          example, areas slated for development of offshore wind in California and Oregon (which
          are likely to develop these resources several years before they may be developed on

134
    See SB 5934 (signed March 28, 2024) (providing for protection of pollinators),
135
    As noted above, the Illinois legislation we have used as a model includes much shorter timelines. We recommend
longer timelines based on our experience with Washington permitting processes taking into account the fact that the
legislation we recommend would foreshorten the time necessary to consider setbacks and other mitigation measures.
136
    On January 8, 2024, the U.S. Department of Energy issued Guidance laying out a four-step process it will use to
define NIETCs and on May 8, 2024, issued its preliminary list of ten NIETCs, including a NIETC running from
southern Nevada to north-central Oregon that is designed to allow importation of renewable energy from the
southwest that will help the Pacific Northwest meet expected needs for carbon-free energy. It also includes a
corridor running from eastern Montana to the Great Plains, which may provide a conduit for electric customers in
the Pacific Northwest to access the strong wind and solar resources available in the Wyoming, Montana, and the
Dakotas.

                                                        76
          Washington’s outer continental shelf), and areas with strong wind and solar resources in
          Wyoming and Montana. The Legislature should consider either transferring these
          authorities to WREA or else requiring WREA to work with EFSEC on issues where
          EFSEC has assigned duties.137

         Development of Transmission Corridors: WREA would be empowered to identify,
          obtain rights of way or easements for, and obtain permits for transmission to be
          constructed on key corridors. Key transmission corridors would connect Renewable
          Energy Zones (discussed above) with population centers and/or existing transmission
          infrastructure and would focus on new transmission corridors and on existing
          transmission that requires major upgrades to accommodate the energy anticipated to be
          generated in the Renewable Energy Zone. WREA would be provided with eminent
          domain authority to assemble transmission corridors and with authority to enter into
          Memoranda of Understanding and other documents necessary to formalize cooperative
          arrangements. Once a transmission corridor is identified and permits are obtained,
          WREA would sell the rights to develop to parties interested in constructing transmission.
          WREA would focus on Renewable Energy Zones to help ensure that the new
          transmission will be highly valuable and it therefore can recover its costs for identifying
          and developing the corridor and obtain the permits necessary to construct transmission.
          Corridors should also be available for other linear facilities that support GHG reductions,
          including pipelines transporting biogas or landfill gas, carbon dioxide bound for carbon
          sequestration facilities, green electrolytic hydrogen, and tie lines that connect renewable
          generators with the existing or planned transmission grid.

         Build-Ready Renewable Energy Development: WREA would be empowered to
          identify sites with high renewable energy potential and obtain land rights (generally
          option agreements), transmission rights, and permits for those sites, then sell the site to
          project developers when the project is “build-ready,” with permitting completed and land
          and transmission rights secured. WREA would focus on brownfields development (for
          example, energy development on abandoned mines or industrial sites) and on other sites
          likely to have minimal environmental impacts, such as highly degraded farmland,
          degraded sage steppe habitat that could be allowed to recover while occupied by a
          renewable energy facility, and industrial forest lands that have been subject to repeated
          cycles of logging. In addition, WREA would be empowered to obtain development rights
          on state and federal lands.



137
   The Legislature has designated EFSEC as the authority to “consult with” federal and state agencies and Tribes
“regarding appropriate limits on federal authority” for siting of transmission corridors in Washington, designates
EFSEC as the “state authority” for purposes of the NIETC process, permits EFSEC to approve transmission
facilities on NIETCs, and to coordinate the state’s participation on NEPA analysis for electric transmission projects
“proposed or sited by a federal agency.” RCW 80.50.045. We note that Washington’s utilities and joint operating
agencies (Energy Northwest) have authority to build and operate transmission facilities, including the power of
condemnation. See, e.g., RCW 43.56.300(1)-(2) (joint operating agencies); RCW 54.16.020 & .040 (public utility
districts). Our recommendation essentially combines these authorities and adds the duty to develop transmission
corridors and to enter into MOUs with other entities involved in transmission planning and permitting, transmission
corridor development, and transmission construction.

                                                         77
                                        CONCLUSION

       Washington policymakers can gain significant insights from the approaches taken in

other jurisdictions facing a dilemma similar to Washington’s – the need to rapidly build out clean

energy infrastructure to address climate change without undermining laws aimed at protecting

the environment, cultural and historical resources, and other values, while at the same time

reducing burdens on overburdened communities. We believe the reforms laid out in this report

can build on significant reforms already adopted by Washington lawmakers and agencies to

achieve these goals.




                                                78
                                              APPENDIX A

                           WASHINGTON CLIMATE LEGISLATION

The major legislative pillars of Washington’s efforts to reduce its GHG emissions are:

         GHG Reduction Targets: In 2008, the Washington Legislature adopted a policy to limit

          the state’s GHG emissions to 1990 levels by 2020, to 25% below 1990 levels by 2035,

          and to 50% below 1990 levels by 2050.138 In 2020, the Legislature strengthened those

          goals. It specified that the 1990 level of GHG emissions was 95.5 million metric tons,

          and now requires the state to limit its GHG emissions to 45% below 1990 levels (50

          million metric tons) by 2035, 75% below 1990 levels (27 million metric tons) by 2040,

          and 95% below 1990 levels (5 million metric tons) by 2050 and thereafter.139 The 2008

          legislation did not include legal mechanisms to achieve these goals, but directed the

          Department of Ecology (“Ecology”) to promulgate rules requiring the reporting of GHG

          emissions and also directed Ecology and other state agencies to recommend legislation

          that would achieve these goals.140

         Decarbonization of the Electricity Sector: In 2019, Washington adopted the Clean

          Energy Transformation Act,141 which requires electric utilities to phase out all coal-fired

          electric generators serving consumers in Washington by 2025 and requires utilities to

          provide Washington electricity consumers with carbon-neutral electricity by 2030. It also

          commits Washington to 100% non-emitting electricity sector by 2045.

         Building Decarbonization: In 2019, Washington enacted energy performance and

          benchmarking standards for large commercial buildings, aimed at reducing the GHG


138
    Chap. 14, Wash. Laws of 2008 § 3.
139
    Chap. 79, Wash. Laws of 2020 § 2, codified at RCW 70A.45.020.
140
    Chap. 14, Wash. Laws of 2008 §§ 4-5.
141
    RCW Chap. 19.405.

                                                    A-1
          emissions from both existing and future buildings.142 These were significantly amended

          in 2022 and again in 2023.143 As amended, the law requires buildings with a floor area of

          20,000 square feet or more to benchmark their GHG emissions and to meet GHG

          intensity targets set by Ecology that become effective in 2026 for large buildings and in

          2027 or 2028 for smaller buildings. The GHG intensity targets are set based on the

          average energy use for specific building uses, with incentives provided for building

          owners that exceed those targets by 15% or more.144 In late 2023, the City of Seattle,

          Washington’s largest city, enacted a Building Efficiency Performance Standard that

          creates more stringent requirements for buildings to reduce GHG generation.145

         Methane and Hydrofluorocarbons (“HFCs”): In 2019, Washington enacted

          legislation, which complements federal legislation with the same aim, intended to reduce

          the state’s emissions of HFCs, a refrigerant that is also a powerful GHG.146 Legislation

          has been enacted to address the state’s emissions of methane, another powerful GHG.

          These include a requirement that Washington natural gas utilities offer a program where

          consumers may purchase renewable natural gas,147 which is natural gas produced by

          biological processes like decomposition of waste at landfills or from anaerobic digestion

          of animal waste, as opposed to fossil natural gas. Legislation has also been enacted to

          limit methane emissions from landfills148 and to facilitate the use of biogas and landfill

          gas in Washington’s climate and clean energy programs.149


142
    Chap. 285, Wash. Laws of 2019.
143
    Chap. 177, Wash. Laws of 2022; Chap. 291, Wash. Laws of 2023.
144
    RCW 19.27A.200-270.
145
    SMC Chapter 22.295.
146
    RCW Chapter 70A.60.
147
    RCW 80.28.385-390.
148
    RCW Chapter 70A.540.
149
    See, e.g., RCW 19.285.030(21); RCW 70.65A.080.

                                                   A-2
         Reduction of GHGs from Transportation: Washington has adopted legislation to

          reduce GHG emissions from transportation, which is the state’s largest source of GHG

          emissions. The legislation works in two ways. First, the legislature has adopted several

          measures to encourage the electrification of transportation or the use of alternative fuels.

          2019 legislation authorizes electric utilities regulated by the UTC, which serve roughly

          half of Washington’s citizens, to submit transportation electrification plans to the UTC

          for approval,150 and to receive an incentive rate of return for construction of electric

          vehicle charging equipment.151 Public Utility Districts (publicly-owned utilities that serve

          the other half) are also authorized to adopt plans for the electrification of

          transportation.152 The legislation also includes tax incentives and other measures to

          encourage the electrification of the state’s vehicle fleet and ferries, and to encourage

          alternative transportation fuels such as hydrogen and sustainable aviation fuel.153

                 To complement vehicle electrification, in 2021, the Legislature enacted and

          Governor Inslee signed the Clean Fuel Standard,154 which requires motor fuels sold in

          Washington to meet increasingly stringent limits on the GHG intensity of those fuels,

          culminated in a requirement that such fuels in Washington have a carbon intensity 20%

          below 2017 levels by 2038, with the limit decreasing yearly between 2022 and 2038.155

          The program also includes a mechanism by which sellers of fuel with a low carbon

          intensity, such as biofuels, that are below the required GHG intensity level can sell

          credits to fuel sellers whose products are above the applicable limit as a means for the


150
    RCW 80.28.365.
151
    RCW 80.28.360.
152
    RCW 54.16.430.
153
    RCW 82.04.4496; 82.08.816.
154
    RCW Chapter 70A.535.
155
    RCW 70A.535,025.

                                                  A-3
          latter to achieve compliance.156 Notably, credits can be earned for vehicle

          electrification.157 The program includes incentives aimed at encouraging the expansion

          of biofuel production capacity in Washington.158

                 In November 2023, the Washington State Department of Transportation finalized

          a Statewide Transportation Carbon Reduction Strategy (TCRS) as a requirement by

          USDOT for state recipients of federal Carbon Reduction Program funds. The TCRS

          builds on the State Energy Strategy, and describes the policy framework necessary to

          reduce future transportation carbon emissions to meet state GHG reduction goals. The

          strategy focuses on two categories that work together to reduce transportation emissions:

          move people and goods more efficiently and equitably; and, electrify vehicles and switch

          to low-carbon fuels. Together, the State Energy Strategy and TCRS create a statewide

          plan for transportation carbon reduction.

         Economy-Wide Cap-and-Invest Program: In 2022, Washington enacted the Climate

          Commitment Act (CCA),159 which sets an economy-wide cap on the state’s GHG

          emissions and requires all facilities that emit more than 25,000 metric tons of carbon

          dioxide-equivalent to obtain credits to cover all their GHG emissions. The cap declines

          over time so that statewide emissions are 95% below 1990 levels by 2050. Allowances

          are purchased at quarterly auctions and the revenues from the auctions are to be directed

          toward programs approved by the Legislature in the CAA, which are generally aimed at

          improving the state’s climate resiliency, addressing problems in overburdened




156
    RCW 70A.535,050.
157
    RCW 70A.535,050(1)(c) & (d).
158
    RCW 70A.535,025(6); RCW 70A.535,050(1)(b).
159
    RCW Chapter 70A.45.

                                                 A-4
communities, and improving access to vehicle charging stations and otherwise supporting

electrification of the state’s transportation sector.




                                         A-5
                                         APPENDIX B

    SUMMARY OF MAJOR STATE AND FEDERAL ENVIRONMENTAL LAWS




Subject Matter of    Citation to Law      Description of Key             Notable Recent
Law                                       Requirements                   Developments

Environmental        National             Requires federal agencies      Congress included
Protection –         Environmental        to produce detailed            NEPA Reforms in the
Federal              Policy Act - 42      documentation concerning       Fiscal Responsibility
                     U.S.C. §§ 4321 et    major Federal actions that     Act of 2023. The new
                     seq                  significantly affect the       statute largely codifies
                                          quality of the human           practices that have been
                                          environment. Also requires     developed since
                                          analysis of the                NEPAs inception in
                                          environmental impact of        1969, including a
                                          the proposed action,           requirement that a lead
                                          alternatives to the proposed   agency be designated
                                          action, and any irreversible   where two or more
                                          damage to resources in the     federal agencies are
                                          event the proposed action      involved.
                                          is implemented. If             The new statute also
                                          triggered, the agency must     imposed two important
                                          conduct an Environmental       requirements. First, that
                                          Assessment (“EA”), and if      EISs are required to be
                                          appropriate, an                completed within 2
                                          Environmental Impact           years after an agency
                                          Statement(“EIS”), which is     determines that a
                                          a more intensive, lengthy      federal action can have
                                          process.                       major environmental
                                                                         impacts. Second, that
                                                                         EAs and EISs are
                                                                         limited to 75 and 150
                                                                         pages, respectively,
                                                                         with limited exceptions
                                                                         for complex projects
                                                                         and appendices.
Environmental        Washington State     Covers any government
Protection – State   Environmental        action defined in the
                     Policy Act –         statute’s rules that is not
                     Chapter 43.21C       categorically exempt.
                     RCW                  When an applicable action
                                          is proposed, the lead

                                            B-1
                                    agency then evaluates
                                    whether there will be a
                                    significant environmental
                                    impact and then issues a
                                    determination of non-
                                    significance, mitigated
                                    determination of non-
                                    significance, or
                                    determination of
                                    significance. Should the
                                    agency issue a
                                    determination of
                                    significance, it must then
                                    prepare a full
                                    environmental impact
                                    statement.
Clean Water –   Clean Water Act     Section 402 of the CWA          On May 25th, the
Federal         – 33 U.S.C. §§      governs discharges of           Supreme Court issued
                1251 et seq         pollutants into waters of       its decision in Sackett
                                    the United States from          v. EPA holding that the
                                    point sources. Facilities       Clean Water Act
                                    discharging pollutants          extends to wetlands
                                    covered by Section 402          only if they have a
                                    must obtain a NPDES             continuous surface
                                    Permit that sets forth          connection to relatively
                                    specific limits on the          permanent bodies of
                                    amounts of particular           water. EPA has since
                                    pollutants the facility is      adopted regulations
                                    allowed to discharge.           that mirror this
                                    Section 404 establishes a       decision.
                                    program to regulate the
                                    discharge of dredged and
                                    fill materials into waters of
                                    the United States and is the
                                    primary federal program
                                    for wetlands protection. If
                                    a project impacts wetlands
                                    subject to federal
                                    jurisdiction, it must obtain
                                    a permit which limits the
                                    amount of wetlands that
                                    may be disturbed.
Clean Water –   Water Pollution     Regulates any discharges        In September 2023,
State           Control Act – Ch.   of pollutants into waters       EPA issued new rules
                90.48 RCW           that are not subject to         governing state
                                    federal regulation. The         certifications under

                                       B-2
                                      Department of Ecology           CWA Section 401.
                                      also exercises authority        Among other changes,
                                      under Section 401 of the        the new rules provide
                                      CWA to provide water            procedures for
                                      quality certifications to any   establishing a
                                      federally permitted projects    “reasonable time” for a
                                      that discharge pollutants       state agency to process
                                      into state waters.              a request for
                                                                      certification, which (by
                                                                      statute) may not exceed
                                                                      one year.
Coastal          Coastal Zone         Governs shorelines
Management –     Management Act       abutting saltwater.
Federal          – 16 U.S.C. §§
                 1451 et seq
Coastal          Shoreline            Requires all counties and
Management –     Management Act       most towns and cities to
State            – Ch. 90.58 RCW      develop shoreline
                                      management programs
                                      with a focus on local
                                      development and focus.
Historic and     Antiquities Act of   Provides for general legal
Archaeological   1906 – 16 U.S.C      protection of cultural and
Resources –      § 431 et seq         natural resources of
Federal                               historic or scientific
                                      interest on federal lands.
Historic and     National Historic    Created permanent
Archaeological   Preservation Act     institutions and creates a
Resources –      of 1966, 16          clearly defined process for
Federal          U.S.C. §§ 470a et    historic preservation. Also
                 seq.                 requires states to take on
                                      more responsibility for
                                      historic sites. Section 106
                                      requires federal agencies to
                                      consider the impact of their
                                      actions on historic
                                      properties and provide an
                                      opportunity for comment
                                      on projects prior to
                                      implementation.
Historic and     Archeological        Requires federal agencies
Archaeological   and Historic         to preserve historic and
Resources –      Preservation Act     archaeological objects and
Federal          of 1974 – 16         materials that would
                 U.S.C.§§ 469 et      otherwise be lost or
                 seq.                 destroyed as a result of

                                         B-3
                                        their projects or licensed
                                        activities or programs.
Historic and        Native American     Requires any entity that
Archaeological      Graves Protection   receives federal funding to
Resources -         and Repatriation    abide by certain
Federal             Act – 25 U.S.C.     requirements related to
                    §§ 3001 et seq.     preservation and
                                        repatriation when Native
                                        American human remains
                                        or cultural items are
                                        located. Failure to comply
                                        with the requirements can
                                        result in civil or criminal
                                        penalties.
Historic and        American Indian     Protects the rights of
Archaeological      Religious           Native Americans to
Resources -         Freedom Act – 42    exercise traditional
Federal             U.S.C. § 1996       religions by ensuring
                                        access to sites, use and
                                        possession of sacred
                                        objects, and the freedom to
                                        worship through
                                        ceremonies and traditional
                                        rites.
Wildlife Protection Endangered          Governs protection of          On March 28, 2024 the
- Federal           Species Act – 16    threatened and endangered      Federal Government
                    U.S.C. §1531 et     species and their critical     released three final
                    seq                 habitats. Once listed, the     rules that significantly
                                        ESA generally prohibits        change the existing
                                        the “take” of an               legal landscape. First, it
                                        endangered species. If a       revised regulations for
                                        government action,             listing species and
                                        including approval of a        designated critical
                                        permit, may affect a listed    habitat to bolster
                                        species or designated          environmental
                                        habitat, it must undertake a   protections. Second, it
                                        biological assessment. If      revised consultation
                                        this assessment shows          requirements triggered
                                        there is an adverse effect     under Section 7,
                                        on species or habitat, then    expanding and
                                        agency must obtain a           clarifying the scope of
                                        biological opinion that        these requirements.
                                        includes an incidental take    Third, the government
                                        statement, which can           reinstated a rule that
                                        authorize the take of the      increases protections
                                        species.                       for threatened species

                                           B-4
                                                                         and granted a new
                                                                         exception for Tribes
                                                                         related to the take of
                                                                         threatened species.
Wildlife Protection Migratory Bird      Implements four
– Federal           Treaty Act of       international conservation
                    1918 – 16 U.S.C.    treaties that the U.S.
                    § 703 et seq.       entered and is intended to
                                        ensure the sustainability of
                                        populations of all protected
                                        migratory bird species.
                                        Prohibits the take of any
                                        protected migratory bird
                                        species without prior
                                        authorization by the
                                        Department of Interior and
                                        U.S. Fish and Wildlife
                                        Service.
Wildlife Protection Marine Mammal       Sets forth a national policy
– Federal           Protection Act –    to prevent marine mammal
                    16 U.S.C. §1361     species and population
                    et seq              stocks from diminishing as
                                        a result of human activities.
                                        Imposes a general
                                        prohibition on the taking
                                        and importing of marine
                                        mammals, subject to some
                                        exceptions.
Wildlife Protection Bald and Golden     Prohibits anyone without a       On February 12, 2024,
– Federal           Eagle Protection    permit issued by the             the United States Fish
                    Act - § 16 U.S.C.   Secretary of the Interior        & Wildlife Service
                    668 et seq          from taking bald or golden       published a final rule
                                        eagles, including things         that created several
                                        like feathers, nests, or eggs.   general permits under
                                                                         this Act, most aimed at
                                                                         reducing regulatory
                                                                         barriers to wind energy
                                                                         generation. The new
                                                                         permits provide an
                                                                         expedited permitting
                                                                         process and
                                                                         standardized permit
                                                                         condition for projects
                                                                         that pose a low risk of
                                                                         raptor take.


                                           B-5
Air Permitting –    Clean Air Act –     Establishes national air
Federal             42 U.S.C. §§        quality standards and
                    4701 et seq         regulates emissions
                                        including a variety of
                                        pollutants. Functions
                                        primarily through Title V
                                        operating permits and the
                                        Prevention of Significant
                                        Deterioration Program.
                                        Generally, if a project
                                        emits pollutants, it must
                                        obtain a permit that
                                        regulates those emissions.
Air Permitting –    Washington          Establishes a statewide
State               Clean Air Act -     program of air pollution
                    Chapter 70A.15      prevention and control.
                    RCW                 Seeks to encourage
                                        coordination and
                                        cooperation between state,
                                        regional, local and federal
                                        government.
Hazardous           Federal Resource    Provides federal authority
Materials - Federal Conservation and    to control over the
                    Recovery Act –      generation, transportation,
                    42 U.S.C. § 6901    treatment, storage, and
                    et seq              disposal of solid and
                                        hazardous wastes. Also
                                        grants federal authority
                                        over underground storage
                                        tanks.
Hazardous           Hazardous Waste     Establishes a
Materials -State    Management Act      comprehensive statewide
                    - Chapter           framework for the
                    70A.300 RCW         planning, regulation,
                                        control, and management
                                        of hazardous waste to
                                        prevent pollution from
                                        hazardous substances.
Hazardous Waste     Comprehensive       Provides for liability for
Cleanup – Federal   Environmental       the release of hazardous
                    Response,           substances at hazardous
                    Compensation,       waste sites by imposing
                    and Liability Act   strict liability and joint and
                    – 42 U.S.C. §       several liability on any
                    9601 et seq.        parties who are responsible
                                        for the hazardous waste.

                                           B-6
Hazardous Waste   Model Toxics      Provides for liability for
Cleanup - State   Control Act –     the release of hazardous
                  Chapter 70A.305   substances at hazardous
                  RCW               waste sites by imposing
                                    strict liability and joint and
                                    several liability on any
                                    parties who are responsible
                                    for the hazardous waste.
Noise, Light, &   Noise Control Act Provides for limited
Glare - Federal   - 42 U.S.C. §     regulation, but establishes
                  4901 et seq       effective coordination of
                                    Federal research activities
                                    and noise control.




                                         B-7
                                           APPENDIX C

                  SUMMARY OF STATE AND FEDERAL ENERGY LAW

        The nation’s complex system of regulation of electric and natural gas utilities plays an

important role in regulation of energy markets and intersects with federal, state, and local

permitting processes at multiple points. Policy-makers seeking to decarbonize the energy sector

need to understand at least the basics of this system.

        At least traditionally, utility regulation has been thought of as a matter of economic

regulation rather than environmental regulation although the lines between economic and

environmental regulation are increasingly blurred. Washington still largely hews to a traditional

regulatory structure where federal regulators govern rates and terms of service for high-voltage

electric transmission and wholesale electric power sales, while state regulators govern the

distribution of power to end-use consumers and the rates those consumers pay for retail sales in

territories served by investor-owned utilities, while local distribution and rates for consumer-

owned utilities (like PUDs and municipal utilities like Seattle City Light and Tacoma Power) are

governed by elected representatives of the PUD or City. A similar division of responsibility has

also governed in natural gas regulation, where the federal government regulates natural gas

transmission through interstate pipelines and the wholesale market for natural gas while states

regulate retail distribution and sales.

        The aspects of this regulator system relevant to Washington’s goals for decarbonization

of the energy sector are discussed here.

                  FEDERAL ENERGY REGULATION – TRANSMISSION

        A.      The Federal Energy Regulatory Commission (“FERC”) and Electric
                Transmission




                                               C-1
           Any attempt to improve the process of transmission siting and permitting undertaken by

the State of Washington must recognize the constraints on state authority that arise from federal

law. These constraints arise both from the FERC’s exclusive jurisdiction over the economic

aspects to interstate transmission and the involvement of many other federal agencies in the

siting and permitting of electric transmission facilities.

              1.      FERC Regulation of Interstate Transmission Facilities

           The Federal Power Act (“FPA”) requires FERC to ensure that any “rate, charge, or

classification” for any “public utility” for “any transmission or sale subject to the jurisdiction of

the Commission” is “just and reasonable.”160 The FPA assigns FERC jurisdiction over “the

transmission of electric energy in interstate commerce and to the sale of electric energy at

wholesale in interstate commerce” and “over all facilities for such transmission or sale of electric

energy,” but specifies that FERC “shall not have jurisdiction. . . over facilities used for the

generation of electric energy or over facilities used in local distribution or only for the

transmission of electric energy in intrastate commerce, or over facilities for the transmission of

electric energy consumed wholly by the transmitter.”161

           These provisions give FERC jurisdiction over the economic aspects of interstate

transmission facilities, including utility rates and charges for interstate transmission service, and

access to those facilities. States retain at least two important roles over transmission: (1)

transmission projects are subject to state siting and permitting processes, so a transmission

developer must obtain all required federal, state and local permits before transmission can be




160
      16 USC § 824e.
161
      16 USC § 824(b)(1).

                                                 C-2
constructed; and (2) local distribution facilities and intrastate transmission facilities are subject to

state jurisdiction and FERC is prohibited from asserting jurisdiction over those facilities.162

        FERC has exercised its authority over interstate transmission facilities in several ways

that are relevant to the development of renewable energy resources. Of particular importance is

FERC’s “open access” transmission regime. Since 1996, when it adopted its landmark Order No.

888,163 FERC has required jurisdictional transmission utilities to provide access to the nation’s

transmission system to all generation owners, a reform which was intended to encourage a

competitive market for electric generation, open to all interested parties. Prior to Order No. 888,

construction of new generation had largely been the province of vertically-integrated utilities,

who could use their monopoly control of transmission assets to block competitors in the

generation market from accessing retail purchasers served by the utility incumbents.

        A few years later, recognizing that the lack of standard interconnection procedures was

creating unnecessary barriers to entry for non-utility generators, FERC implemented a uniform

system for new generation to interconnect with FERC-jurisdictional interconnection facilities.164

Under current rules, FERC requires generators to file an application for transmission service, to

go through a series of studies of the impact of their facilities on the transmission system, and to




162
    See, e.g., FERC v. Electric Power Supply Ass’n, 577 U.S. 260, 266 (2016) (Section 201 of the FPA “maintains a
zone of exclusive state jurisdiction” over functions assigned to states); New York v. FERC, 535 U.S. 1, 22-23 (2001)
(noting that FPA’s legislative history is “replete with statements describing Congress’ intent to preserve state
jurisdiction over local facilities”); LSP Transmission Holdings LLC v. Sieben, 954 F.3d 1018, 1023-24 (8th Cir.
2020) (describing state and federal jurisdiction under FPA, noting that states retain jurisdiction over siting,
permitting and construction of transmission).
163
    Order No. 888, Promoting Wholesale Competition Through Open Access Non-Discriminatory Transmission
Servs. by Pub. Utils., FERC Stats. & Regs. ¶ 31,036 (1996), aff'd sub nom. N. Y. v. FERC, 535 U.S. 1 (2002).
164
    Standardization of Generator Interconnection Agreements and Procedures, Order No. 2003, FERC Stats. and
Regs. ¶ 31,146 (2003), order on reh’g, Order No. 2003-A, FERC Stats. & Regs. ¶ 31,160 at P 744, order on reh’g,
Order No. 2003-B, FERC Stats. & Regs. ¶ 31,171 (2004), order on reh’g, Order No. 2003-C, FERC Stats. & Regs. ¶
31,190 (2005), aff’d sub nom. NARUC v. FERC, 475 F.3d 1277 (D.C. Cir 2007); Order No. 2006, Small Generator
Interconnection Procedures, 111 FERC ¶ 61,220, at P 8, order on reh'g, Order No. 2006-A, 113 FERC ¶ 61,195
(2005), order granting clarification, Order No. 2006-B, 116 FERC ¶ 61,046 (2006).

                                                       C-3
pay for the interconnection facilities identified by those studies. For “Network Upgrades” – the

upgrades to the shared transmission grid that must be constructed to accommodate the new

generator – FERC follows a “crediting policy.” The generator must fund the Network Upgrades

upfront, but, because Network Upgrades benefit all transmission customers generally, the

transmission utility is required to refund the Network Upgrade costs to the generator in the form

of transmission credits and to include the Network Upgrades in its rate base so that they are paid

for by the transmission customers who ultimately benefit from the transmission upgrades.

        FERC’s interconnection policy was developed in the early 2000s, when natural gas

generation was the preferred technology for new generation and generation was generally added

to the system in large and discrete bundles. Unfortunately, FERC’s interconnection policy has

proved ill-suited to transition to GHG-free resources, and the interconnection process has been

overwhelmed by applications for new renewable generation, resulting in hundreds of thousands

of MW of renewable generation capacity waiting in queues for transmission service. Often it

takes five years or more for generation projects to move through the queue to obtain transmission

service.165

        It is increasingly clear that limitations on access to the nation’s electric transmission

system is the most significant barrier to constructing new renewable generation that will permit

attainment of critical decarbonization goals. According to an analysis from Princeton University,

the Inflation Reduction Act (“IRA”) could cut U.S. emissions 40 percent by 2030 compared to




165
   E.g., Lawrence-Berkeley Labs, Energy Markets & Policy, Queued Up: Characteristics of Power Plants Seeking
Transmission Interconnection (Apr. 2023) (available at: https://emp.lbl.gov/sites/default/files/queued_up_2022_04-
06-2023.pdf).

                                                      C-4
2005 levels,166 nearly reaching the Biden Administration’s goal of a 50% reduction by 2030.167

But to achieve the full benefits of the Inflation Reduction Act, the nation’s electric transmission

capacity must expand at a rate of approximately 2.3% per year, more than double its recent

annual average. If transmission expands at its historical pace of about 1% per year, 80% of the

benefits of the IRA will be lost. Roughly 25% of the IRA’s benefits will be lost if transmission

expands at a rate of 1.5% per year.168

         Recognizing that transmission expansion remains a serious problem, FERC in 2021

issued an Advanced Notice of Proposed Rulemaking proposing reforms to both transmission

planning and interconnection procedures of new generation. In 2023, FERC issued Order No.

2023, which adopted a number of reforms to the interconnection process, including changes

aimed at speeding the study process, setting time limits on engineering studies, and adopting

requirements aimed at reducing barriers to the use of advanced transmission technology.169

However, the new rules retain the crediting policy and the basic structure of the interconnection

process.

         A second FERC order aimed at reforming processes for interregional transmission was

adopted on May 13, 2024.170 Order No. 1920 significantly reforms regional transmission


166
    Jesse D. Jenkins, The Inflation Reduction Act and the Path to a Net-Zero America, Princeton University Zero
Carbon Research and Laboratory, Sept. 12, 2022 (available at:
https://cpree.princeton.edu/sites/g/files/toruqf651/files/documents/2022-09-12%20-
%20Inflation%20Reduction%20Act%20and%20Path%20to%20Net-Zero.pdf).
167
    See White House Fact Sheet: President Biden Sets 2030 Greenhouse Gas Pollution Reduction Target Aimed at
Creating Good-Paying Union Jobs and Securing U.S. Leadership on Clean Energy Technologies (April 22, 2021)
(available at: https://www.whitehouse.gov/briefing-room/statements-releases/2021/04/22/fact-sheet-president-biden-
sets-2030-greenhouse-gas-pollution-reduction-target-aimed-at-creating-good-paying-union-jobs-and-securing-u-s-
leadership-on-clean-energy-technologies/).
168
    Jesse D. Jenkins et al., Electric Transmission is the Key to Unlock the Full Potential of the Inflation Reduction
Act, Princeton University Zero Carbon Research and Laboratory, Sept. 22, 2022 (available at:
https://repeatproject.org/docs/REPEAT_IRA_Transmission_2022-09-22.pdf).
169
    Order No. 2023, Improvements to Generator Interconnection Procs. & Agreements, 184 FERC ¶ 61,054 (2023),
order on reh’g, 186 FERC ¶ 61,199 (2024).
170
    Order No. 1920, Building for the Future Through Electric Regional Transmission Planning and Cost Allocation,
187 FERC ¶ 61,068 (2024).

                                                       C-5
planning and cost allocation requirements. The order arrives more than ten years after Order No.

1000, FERC’s last significant transmission planning order, and almost thirty years after the

introduction of Open Access Transmission Tariffs (“OATTs”) in Order No. 888. Whereas Order

No. 1000 focused on the process of regional transmission planning and cost allocation, Order

No. 1920 shifts focus to the desired outcomes.

        The order requires transmission providers to participate in long-term regional

transmission planning covering at least a 20-year planning horizon. The order also requires

transmission providers to revise their OATTs to include one or more cost allocation methods

based off Order No. 1000 regional cost allocation principles, primarily the principle that the

beneficiaries of electric infrastructure should bear the costs of that infrastructure.

            2.      Federal Transmission Jurisdiction in the Pacific Northwest

        The Bonneville Power Administration (“BPA”) plays a major, and unique, role in electric

transmission in the Pacific Northwest. BPA owns about 75% of the region’s high-voltage

transmission system. Although BPA is exempt from FERC regulation, it has voluntarily

complied with FERC’s open access policies, although it has adopted its own policy for

transmission interconnections.171 BPA owns or co-owns several key transmission corridors that

are likely to play a critical role in decarbonization of Washington’s electricity sector, including

the Eastern Intertie, a high-voltage transmission line originally constructed to support the

Colstrip coal-fired plant that links areas of Montana with excellent wind and solar energy

potential to load centers in the Northwest. Similarly, BPA owns or co-owns interties that link

California and the southwest to the Pacific Northwest.




171
   Documents concerning Bonneville’s interconnection process, known as the TSR Study and Expansion Process
(“TSEP”), are available here: https://www.bpa.gov/energy-and-services/transmission/acquiring-transmission/tsep.

                                                      C-6
           3.      Federal Transmission Permitting Reforms

        While states and local governments have traditionally been responsible for permitting

electric transmission infrastructure, Congress has expanded the federal role in constructing

transmission for “National Interest Electric Transmission Corridors” or “NIETCs.” Under

amendments to the FPA adopted in the 2021 Infrastructure Investment and Jobs Act (IIJA, also

often referred to as the “Bipartisan Infrastructure Law”), which were aimed at overcoming

judicial decisions that effectively nullified Congress’s initial efforts to establish NIETCs in 2005,

Congress has provided FERC with “backstop authority” to permit high-voltage transmission

lines in NIETCs. NIETCs are established based on a triennial study of transmission congestion

conducted by the DOE that identifies the need for major inter-regional transmission lines based

on an analysis of transmission system congestion and establishes NIETCs where major inter-

regional transmission facilities are needed to reduce consumer prices and to address national

security and similar national interest.

        Developers of transmission projects in a NIETC must initially apply for permits from the

relevant states but if the state permitting authorities fail to act within a year or deny the facility,

then FERC can step in and issue a federal permit that overrides the state’s authority. FERC also

may grant eminent domain authority to NIETC projects, which facilitates the project developer’s

ability to obtain property rights necessary to build large linear facilities.

        In October 2023, DOE issued its National Transmission Needs Study, the first step in

designating NIETCs. On December 19, 2023, DOE issued a guidance document setting forth a

four-step process it intends to use to designate NIETCs. On May 8, 2024, issued its preliminary

list of ten NIETCs, including a NIETC running from southern Nevada to north-central Oregon

that is designed to allow importation of renewable energy from the southwest that will help the


                                                  C-7
Pacific Northwest meet expected needs for carbon-free energy and a line in the upper Midwest

that could link strong solar and wind resources in that region to the existing transmission system

that moves power from Eastern Montana into the Pacific Northwest.

        The BLM and U.S. Forest Service are also engaged in designating “Westwide Energy

Corridors,” as authorized by Section 368 of the Energy Policy Act of 2005. In 2009, the agencies

designated approximately 6,000 miles of Westwide Energy Corridors.” In response to litigation

over those designations, the agencies are modifying designations for approximately 673 miles of

corridors. That process is now in its final stages and, barring litigation, should be completed in

2024.

        The IIJA also included several additional programs aimed at accelerating the construction

of electric transmission. These include:

               The “Transmission Facilitation Program,” which authorizes the DOE to act as an

                “anchor tenant” for construction of high-voltage transmission lines, entering into

                long-term contracts for up to 50% of the capacity of the new lines, which it can

                then either sell to private entities or sell under a public-private partnership. The

                program is supported by a $2.5 billion revolving loan fund.

               An increase in BPA’s borrowing authority to $10 billion to support transmission

                expansion in the Pacific Northwest.

               Authorization to construct transmission facilities to increase the transfer of

                renewable power between Canada and United States under the Columbia River

                Treaty.

               A $3 billion matching grant program to support the use of advanced technology

                to improve the operation of the nation’s transmission grid. This fund supports a


                                                C-8
                variety of new transmission technologies that can expand transmission capacity

                or improve operation of the system quickly and without major construction.

               A $100 million authorization for BPA to upgrade the pumped storage

                hydroelectric facilities (a form of energy storage) at the Grand Coulee Dam.

       On April 25, 2024, the U.S. Department of Energy announced the Coordinated

Interagency Transmission Authorization and Permits Program (CITAP). Under CITAP,

transmission developers will have access to a centralized portal, operated by the DOE, which

will allow them to file a single application, following a coordinated pre-application process, with

the aim of reducing the time for federal permitting of transmission to two years. Thus, the DOE’s

role under CITAP will be similar to the role of the Federal Permit Improvement Steering

Council, in that it will oversee and manage the federal permitting process for transmission

projects. CITAP grows out of a 2023 Memorandum of Understanding among nine federal

agencies that implements Section 216p(h) of the Federal Power Act (added in the Energy Policy

Act of 2005), in which Congress authorized DOE to be the lead federal agency for the

authorization and environmental review of transmission projects and set specific deadlines for

those processes.

       Finally, on May 13, 2024, FERC issued Order No. 1977, which implements its “backstop

authority” for transmission siting in NIETCs.

       B.       FERC and Regulation of Wholesale Electricity Sales

       Under the FPA, FERC regulates the rates for wholesale sales of electric power. After

Order No. 888 ushered in the era of open transmission access and market competition in the

wholesale electricity markets, FERC authorized the creation of Regional Transmission

Organizations (“RTOs”) and Independent System Operators (“ISOs”), which control operation


                                                C-9
of the electric grid and wholesale markets in much of the country. To date, no RTO or ISO

operates in the Pacific Northwest, although the strong market and transmission linkages between

California and the Northwest mean that the California Independent System Operator (“CAISO”),

which operates the grid and wholesale markets in California, has an important influence on the

Pacific Northwest’s electricity system.

         In addition, the region’s utilities have been moving toward voluntary formation of a

regional market that would permit utilities to trade power in the short-term markets, thus

improving the region’s ability to integrate variable renewable resources like wind and solar.

These markets could substantially increase renewables penetration in the region and reduce the

costs of balancing resources, but require robust transmission connections to realize their full

value.

         C.      Federal Hydroelectric Licensing

         Under Part I of the Federal Power Act,172 anyone proposing to construct a hydroelectric

dam in the United States is required to obtain a permit from FERC.173 Licensing is intended to

ensure that construction of hydroelectric dams does not unduly interfere with river navigation, that

hydro development occurs in a manner that efficiently uses hydroelectric resources, and that dams

do not unduly harm the environment or other protected resources. Before a license can be issued,

FERC requires the licensee to demonstrate that it has obtained all federal, state, and local permits

necessary to allow construction of the dam. Licenses are generally issued for a term of 50 years.174

         Beginning in the 1980s, as the initial licenses for a large number of dams that were licensed

shortly after enactment of Part I in the 1930s, FERC struggled to effectively relicense dams using


172
    16 U.S.C. § 791 et seq.
173
    FERC’s jurisdiction includes any dam on navigable waters and any dam producing power that moves in interstate
commerce, so it covers essentially every dam other than small dams that are not connected to the grid.
174
    See FERC Hydroelectric Licensing page.

                                                    C - 10
the traditional process, where an application is filed, interested parties then intervene, and a lengthy

process of fact discovery and analysis follows. FERC struggled to integrate environmental laws,

particularly NEPA and the Clean Water Act, which were enacted decades after the Federal Power

Act, into the licensing process. FERC was dissatisfied with this process because it was often

extremely time-consuming and also in too many cases resulted in licenses being overturned in

litigation, often based on concerns that were not identified until late in the licensing process.

        In response, FERC first in 1997 adopted an Integrated Licensing Process, that emphasized

a pre-application process in which the applicant for a license meets with FERC staff and other

regulators prior to filing the license application, which was intended to identify problems in

advance and ensure that those problems did not derail the application. The process again proved

unsatisfactory, and FERC in 2003 therefore instituted a new Alternative Licensing Process, which

enhances the requirements for pre-application consultations and technical assistance to potential

licensees.175

        These events offer lessons for Washington as it struggles to improve its permitting

processes. Over time, FERC has relied increasingly on more robust pre-application processes to

flesh out concerns and conflicts in order that an applicant can, before filing, revise its proposal or

add mitigation measures that will make the application process flow more smoothly.

        D.       State Utility Regulation

        Washington’s landscape for retail electricity regulation is complicated by the mix of

state-regulated and locally-governed entities that provide electricity to retail customers, as well

as the significant role that BPA plays in generation and transmission of wholesale electricity.

About half of Washington’s residents are served by investor-owned utilities (“IOUs” – Puget


175
  For background and history, see Order No. 2002, Hydroelectric Licensing under the Federal Power Act, 104
FERC ¶ 61,109 (2003).

                                                   C - 11
Sound Energy, PacifiCorp, Avista). The other half are served by publicly-owned utilities,

primarily Public Utility Districts (“PUDs”) and municipally-owned utilities like Seattle City

Light and Tacoma Power. Finally, rural electric cooperatives served large areas of rural

Washington, although a relatively small proportion of the state’s population.

        Washington’s primary utility regulator is the Washington Utilities and Transportation

Commission (“UTC”). Although many other states have moved toward “retail access” – that is,

permitting consumers to choose their electricity supplier, with local utilities used only to deliver

that electricity – Washington continues to follow the traditional model of vertically-integrated,

regulated utility monopolies. That is, Washington’s IOUs are required to serve all retail

consumers within their service territories using electricity procured by the utility. In return, the

UTC allows the utilities a return on the investment needed to serve those customers. The amount

of the utilities’ investment is referred to as their “rate base,” and reflects all investments in

infrastructure, plus costs of personnel and equipment, made by the utilities to serve those retail

customers.

        The result of this traditional monopoly structure is that independent generators – non-

utility generators that compete in the wholesale electricity market – have no direct access to

Washington buyers. Instead, non-utility generators and customers who wish to purchase

renewable power rather than power from the IOUs (which continue to rely substantially on fossil

fuel generation) have only limited options. For example, customers may choose to obtain power

through “green tariffs.” When a retail customer signs up for a green tariff program, the utility

agrees to obtain sufficient renewable power to meet the needs of the customers who have entered

the program, but the utility continues to be the customer’s sole power provider. In addition, the




                                                C - 12
UTC has required regulated utilities to use competitive solicitation processes to obtain new

power supplies.

          There is one important exception to Washington’s general rule that independent

generators lack access to retail markets, the Public Utility Regulatory Policies Act of 1978

(“PURPA”). PURPA requires utilities to purchase the electric output from renewable energy

generators with 80 MW of capacity or less and from cogeneration facilities (“Qualifying

Facilities” in PURPA parlance) as the utility’s “avoided cost” rate. Avoided cost has been

understood to mean the cost the utility would incur to purchase or generate electricity in the

absence of the supply from the QF. In some states, PURPA has been used successfully to

encourage renewable energy generation by providing a meaningful right of access to retail

markets. However, PURPA delegates considerable authority to the states to administer and

enforce the statute, and Washington PURPA program has produced very little renewable energy

construction, particularly when compared to neighboring states like Oregon and Idaho.

          The UTC does not regulate Washington’s publicly-owned utilities. Instead, the rates and

terms of retail service for these utilities are established by elected representations. In the case of

PUDs, these are elected Commissioners. For municipally-owned utilities, elected city council

members ultimately control retail rates and terms of service. The COUs, like the IOUs, must

comply with carbon reduction requirements. In addition, in recent years, the Legislature has

provided explicit authority to the COUs to, for example, mitigate their greenhouse gas

emissions176 and to support electrification of the transportation system.177




176
      RCW 54.16.390.
177
      RCW 54.16.430.

                                                C - 13
           Washington has for many years required larger utilities to develop and publish Integrated

Resource Plans (“IRP”).178 The IRP process has proved to be a useful way for utilities to

systematically analyze their needs for power and transmission and anticipated load growth, and

to analyze the available alternatives to meet those loads. When it adopted CETA, the Legislature

piggy-backed on the success of the IRP process, requiring utilities to adopt Clean Energy

Implementation Plans to plan for decarbonization of their systems, and to provide periodic

reports on progress toward decarbonization goals. Most recently, in legislation aimed at allowing

combination gas-electric utilities such as Puget Sound Energy to decarbonize their natural gas

distribution systems, the Legislature directed that those utilities combine natural gas and electric

system planning in order to plan for conversion of many gas appliances and other applications to

electricity.179

           E.      Regulation of Natural Gas


           FERC regulates natural gas under the Natural Gas Act (“NGA”), which uses the same

statutory model as the Federal Power Act. FERC regulates interstate gas transmission lines and

the wholesale market for natural gas moved in interstate commerce, while retail sales and

regulation of local distribution systems are left to the states. One major difference between the

NGA and the FPA, however, is that an entity seeking to construct in interstate gas pipeline must

obtain a certificate of public convenience and necessity (“CPCN”) from FERC. This requires the

pipeline proponent to demonstrate that the pipeline is needed and otherwise would be in the

public interest, but if FERC approves the CPCN, this gives the pipeline eminent domain




178
      RCW Chap. 19,280.
179
      HB 1859 (signed by Gov. Inslee on March 28, 2024).

                                                      C - 14
authority. The result is that construction of interstate natural gas pipelines is significantly easier

from a legal perspective than construction of interstate electric transmission lines.

        In recent years, many states, including Washington, have recognized that renewable

natural gas (“RNG,” that is, methane derived from sources like livestock operations, landfills,

and sewage treatment plants) and have taken measures to encourage the use of RNG, including,

for example, establishing programs by which retail consumers can elect to be served with RNG,

providing that RNG pipelines can be placed on the rights of way for public roads, and providing

tax incentives and other measures to encourage the construction of dairy digesters and similar

facilities to capture RNG.




                                                C - 15
                                                 APPENDIX D

        NATIVE AMERICAN TRIBES IN WASHINGTON AND TREATY RIGHTS

         Twenty-nine federally-recognized Indian Tribes call Washington home.180 In addition,

certain Tribes in other states, including, for example, the Nez Perce, Umatilla, Grande Ronde,

and the Confederated Tribes of the Warm Springs Reservation, have interests in Washington, so

the total number of Tribes participating in permitting processes in Washington is approximately

36. The Tribes are independent sovereigns under both federal and state law, and development of

renewable energy and other resources to support decarbonization of Washington’s economy

must therefore respect Tribal rights. Tribal rights are governed by the Stevens Treaties, a series

of treaties negotiated by Territorial Governor Isaac Stevens in the 1850s.181 The Stevens Treaties

reserve land to the Tribes. Currently, Indian Reservations occupy about six million acres of

Washington land, much of it with excellent renewable energy resources. In addition, the Stevens

Treaties permits tribal members to hunt and fish in their “usual and accustomed places.”

Accordingly, Washington’s Tribes have rights that extend well beyond the boundaries of their

reservations.

         As further detailed in the Low-Carbon Siting Report,182 the State of Washington has

formalized tribal consultation requirements in several specific ways:




180
    This number does not include tribes that have not received federal recognition. Unrecognized tribes include, most
notably, the Duwamish Tribe, whose ancestral lands underlie the City of Seattle. See generally David M. Buerge,
Chief Seattle and the Town That Took His Name: The Change of Worlds for Native People and Settlers on Puget
Sound (2017).
181
    See Charles Wilkinson, Treaty Justice: The Northwest Tribes, the Boldt Decision and the Recognition of Fishing
Rights (Univ. of Washington Press 2024); WDFW, Treaty history with the Northwest Tribes (available at:
https://wdfw.wa.gov/hunting/management/tribal/history#:~:text=Stevens%20ultimately%20negotiated%20eight%20
treaties,lands%20beyond%20these%20reserved%20areas).
182
    Low-Carbon Siting Report at 38-40.

                                                       D-1
         Centennial Accord: The Centennial Accord183 provides a framework for government-to-

          government relations between the state and Tribes.

         RCW Chapter 43.376: Chapter 43.376 requires state agencies to make reasonable efforts

          to collaborate with Tribes when developing policies and programs that directly affect

          Tribes.

         Executive Order 21-02: This executive order directs state agencies to consult with

          affected Tribes and the Department of Archaeological and Historic Preservation if state-

          funded construction or acquisition projects will not otherwise undergo review under

          Section 106 of the NHPA.

         Statutory Commitments: The Climate Commitment Act184 and the HEAL Act185 both

          contain requirements for Tribal consultation.

         EFSEC: HB 1812 requires EFSEC to consult with Tribes with rights or resources in the

          area of a proposed project.

         SB 1717: In 2022, the Legislature adopted and Governor Inslee signed SB 1717,186 which

          amends the Growth Management Act by permitting federally recognized Tribes to opt

          into county or regional planning processes if their reservations lie within the county or

          region. If the tribe elects to participate and has its own planning process, the relevant

          county must enter into a memorandum setting forth the terms to coordinate the county’s

          planning process with the Tribe’s.




183
    Available at https://goia.wa.gov/relations/centennial-accord.
184
    RCW 70A.65.305.
185
    RCW 70A.02.100.
186
    Wash. Laws of 2022, Ch. 252,

                                                        D-2
         While we generally recommend providing information up front to project developers so

that they can avoid sensitive lands and identify development sites with minimal environmental

impacts, it is important to recognize that some Tribal resources, particularly sacred sites,

archaeological sites, burial grounds, and sites with historical significance such as traditional

village sites, should not be publicly disclosed without the explicit approval of the affected Tribe.

Protection of this kind of information is necessary because of the unfortunate history of looting

of Native American artifacts by “pot hunters” seeking to profit from the lucrative black market in

such artifacts.187 Measures such as the federal Archaeological Resources Protection Act188 have

proven inadequate to fully protect Tribal resources and artifacts from this kind of black market

profiteering. Accordingly, the disclosure requirements we recommend should be applied to

Tribes only with great care and in close consultation with the Tribes.




187
    See, e.g., K. Sharp, “An Exclusive Look at the Greatest Haul of Native American Artifacts, Ever,” Smithsonian
Magazine, Nov. 2015 (available at: https://www.smithsonianmag.com/history/exclusive-greatest-haul-native-
american-artifacts-looted-180956959/).
188
    See, e.g., U.S. Forest Service, Archaeological Resources Protection (https://www.fs.usda.gov/lei/archeological-
resources-protection.php#:~:text=The%20Archaeological%20Resources%20Protection%20Act,archaeological%
20collections%20from%20those%20sites.).

                                                       D-3
                                                APPENDIX E

                                   GOVERNMENT OWNED LANDS

          More than 12 million acres of land in Washington, more than 28% of the state’s total land

area, is owned by the federal government. Another 6.5 million acres is owned by the State of

Washington.189 Often, these government-owned lands are in areas of the state with high-quality

solar, wind, or other renewable resources. Both state and federal agencies are now taking

significant actions to promote the development of renewable energy resources. Further,

significant electric transmission lines in Washington will almost invariably require access to

government-owned lands. Accordingly, development of green energy and infrastructure in

Washington is intimately tied to these lands and the agencies that administer them. This section

briefly describes the various classifications of land, how those lands are administered, and how

different agencies are attempting to promote the development of renewable energy. Efforts to

promote electric transmission are discussed in the section below, where we discuss federal

energy regulation and regulation of transmission.

                                            FEDERAL LANDS

          Federal lands are governed by several different legal regimes that are administered by a

variety of agencies.190 Federal lands in Washington are governed as follows:

         Federally-Designated Wilderness: Washington boasts thirty-one federally-designated

          wilderness areas located in all parts of the state, which together cover about 4.3 million




189
    The University of Washington’s Spatial Informatics Group has inventoried Washington’s public lands and
provides extensive information concerning, for example, the forest and wetlands resources on those lands and a
variety of databases related to climate change. See https://nrsig.org/
190
    The Congressional Research Service publishes a useful high-level summary of various federal land designations
and the legal basis for those designations entitled “Federal Land Designations: A Brief Guide.” The most recent
version, updated on May 19, 2023, is available at: R45340 (1).pdf.

                                                      E-1
          acres. Under the Wilderness Act,191 these lands are preserved in their wild state and

          therefore are off limits to development.

         National Parks: Three major National Parks are located in Washington: Olympic, Mt.

          Rainier, and North Cascades.192 Together these parks occupy about 1.7 million acres.

          National Parks are administered to maximize their value as natural and recreational

          resources.193 Accordingly, while it is possible to construct certain facilities in National

          Parks, such as roads, campgrounds, and buildings, these facilities are generally aimed at

          serving National Park visitors. For purposes of this study, we assume that National Parks

          are effectively off limits to energy or green economy projects other than small projects

          serving Park infrastructure, such as solar panels on Park Service buildings.

         National Forests. Eight National Forests are located entirely or mostly in Washington.

          National Forests are administered by the U.S. Forest Service, which is part of the U.S.

          Department of Agriculture. National Forests are administered under several different

          statutes,194 but as a general matter the Forest Service manages for multiple uses and a

          sustained yield of forest products. Accordingly, it is possible to construct electric

          transmission, renewable generation, and other types of projects on National Forest lands,

          but any construction must be permitted by the Forest Service and is subject to legal

          restrictions arising from the statues governing the national forests as well as Forest Plans

          that are developed periodically by each forest.


191
    16 U.S.C. § 1131 et seq.
192
    The National Park Service administers a number of much smaller sites, such as the Whitman Mission National
Historical Park in the southeast corner of the state and Ebey’s Landing National Historic Reservation on Whidbey
Island. These reservations are generally small and therefore unlikely to be a significant barrier to the development of
green economy resources.
193
    54 U.S.C. § 100101 et seq.
194
    E.g., National Forest Management Act, 16 U.S.C. § 1600 et. seq.; Multiple Use-Sustained Yield Act, 16 U.S.C. §
528.

                                                        E-2
                 In the Pacific Northwest, significant restrictions on development in forests may

          arise from, for example, the Northwest Forest Plan, which is aimed at preserving the

          habitat of two endangered species, the northern spotted owl and the marbled murrelet.195

          In addition, the Forest Service administers a variety of lands that have been designated,

          either by Congress or by the agency itself, with special protections. For example, the

          Forest Service administers the Mount Saint Helens National Volcanic Monument under

          an act of Congress.196 Forest Managers can also designate areas for special management

          if they have significant scenic, recreational, historical, archaeological, paleontological, or

          biological resources.

         BLM Lands: The U.S. Bureau of Land Management (“BLM”), an agency within the U.S.

          Department of Interior, manages about 16 million acres in Washington and Oregon. In

          Washington, BLM administers lands that are scattered across much of Eastern

          Washington. On January 17, 2024, the BLM announced that it is updating its “solar road

          map,” which originally included only states in the southwest, to include Washington and

          four other northern states.197 The road map will guide solar development on BLM lands

          in Washington and includes a Programmatic Environmental Impact Statement that

          broadly assesses the impacts of solar development on BLM lands.198

         Department of Defense Lands: Several major defense installations are located in

          Washington. These include, for example, Joint Base Lewis-McChord, Whidbey Naval

          Air Station, and the Yakima Firing Range. The primary purposes of these military

          reservations is, of course, national defense. Accordingly, while development of green


195
    See https://www.fs.usda.gov/r6/reo/monitoring/northern-spotted-owl.php.
196
    96 Stat. 301 (1982).
197
    See https://www.blm.gov/press-release/blm-analysis-aims-optimize-solar-energy-development-throughout-west.
198
    See https://blmsolar.anl.gov/solar-peis-2023/.

                                                     E-3
           energy and green economy infrastructure is not off limits on these lands per se, any

           development must be compatible with the military mission of these facilities. The

           military impact on renewable energy development reaches beyond the boundaries of

           military reservations in one important way: wind generators may create barriers to low-

           level flight training missions and create interference with military radar system. Hence,

           wind energy developers must ensure that their developments do not interfere with

           military aviation facilities or missions.

          National Wildlife Refuges: Washington boasts twenty-four National Wildlife Refuges,

           including several large refuges like the Columbia Wildlife Refuge, at 30,000 acres, and

           Turnbull National Wildlife Refuge, at 23,000 acres, which are administered by the U.S.

           Fish & Wildlife Service, an agency of the Department of Interior. Areas protected as

           wildlife refuge are small compared to the acreage of other protected federal lands.

           However, these lands are generally located in areas of critical wildlife habitat, such as

           key stopovers for migratory birds. Hence, renewable energy developers must be

           cognizant of these refuges and recognize that development of, for example, wind energy

           near a refuge might present an unusually large risk to migrating birds because a

           disproportionately large number of birds may migrate through the refuge.

          Federal Offshore Lands: Washington owns all submerged lands lying within three miles

           of its coastline. Lands on the continental shelf beyond the three-mile limit, referred to as

           the Outer Continental Shelf (“OCS”), are owned by the federal government and

           administered under the Outer Continental Shelf Lands Act.199 Mineral and energy

           development on the OCS is administered by the Bureau of Ocean Energy and Mining


199
      43 U.S.C. §§ 1331 et seq.

                                                       E-4
(“BOEM”). BOEM’s jurisdiction extends to leasing the OCS for wind energy

development.

       Offshore wind technology has, until the last few years, been confined to shallow

waters off the coast of Europe and the U.S. East Coast. However, technology that allows

development in deeper waters like those off the West Coast has advanced rapidly and

BOEM is now moving to lease areas off the coasts of California and Oregon for wind

energy development. While BOEM has not yet moved to lease areas off Washington, it is

likely that BOEM will turn its attention to Washington waters in the next few years.

       Offshore wind energy is generally more expensive to develop than onshore wind,

but winds offshore are more steady and reliable than onshore winds, and developers

therefore generally view the extra expense associated with developing offshore wind

facilities to be justified by the ability to capture a resource with greater value. Far-sighted

legislators should be paying careful attention to offshore wind energy to ensure that

adequate transmission pathways are available to move energy from offshore wind to load

centers on land, that wind developers can lease state lands in the three-mile exclusive

economic zone to move power from offshore wind installations to the onshore

transmission system, and that the state has identified sensitive fisheries and other marine

resources that should be protected as wind energy is developed.

                                  STATE LANDS

       Most land owned by the State of Washington, about 5.6 million acres, is

administered by the Washington Department of Natural Resources (“DNR”). DNR

administers most of the submerged lands owned by the State of Washington, and




                                         E-5
        therefore will be a key player if the development of Washington’s offshore wind energy

        resources for the reasons described above.

                 DNR also administers Washington’s trust lands, which constitute the bulk of its

        holdings. These school trust lands were ceded by the federal government to Washington

        at statehood with the intent that resources from these lands would be used to support

        Washington’s public schools and other purposes like the state capitol.200 To further this

        mission, DNR has begun actively promoting renewable energy development on state and

        has set a goal of 500 MW of solar development on DNR lands by 2025. To achieve this

        goal, DNR has, for example, producing a map of clean energy resources on state lands

        that identified areas with the least risk for conflicts over environmental values. DNR

        currently leases 1,300 acres of state lands for solar projects.201 DNR has also begun to

        explore leasing state forest lands as a means of carbon sequestration to fight climate

        change.202

                 Most other state lands are administered by the Washington Department of Fish

        and Wildlife, which administers approximately one million acres of state lands or by

        Washington State Parks, which administers 140 properties across the state, although these

        cover only about 123,000 acres in total. In both cases, the primary mission of these

        agencies is to conserve the lands they administer, and to promote recreation and wildlife.

        Green energy development is not barred on these lands per se, but any development

        would have to be approved by the agency and reconciled with the restrictions on

        development for the lands administered by these agencies.


200
    See, e.g., Conservation Northwest v. Comm'r of Pub. Lands, 199 Wn.2d 813, 822, 514 P.3d 174, 179 (2022).
201
    See https://www.dnr.wa.gov/cleanenergymap.
202
    See https://www.dnr.wa.gov/CarbonProject (forest sequestration); https://www.dnr.wa.gov/geologic-carbon-
sequestration (geological sequestration).

                                                     E-6
                                        APPENDIX F

                            WA Clean Energy Permitting Reform
                                            -
                                      Bibliography

U.S. Department of Energy, RAPID Toolkit, Transmission Best Practices, Bulk Transmission
Toolkit, and Regulatory and Permitting Information Desktop Toolkit (undated)

M. Eisenson et al., Opposition to Renewable Energy in the United States: June 2024 Edition,
Sabin Center for Climate Change Law (June 2024).

S. Enterline & A. Valainis, Laws in Order: An Inventory of State Renewable Energy Siting
Policies, Regulatory Assistance Project (June 2024).

Electric Power Research Institute, White Paper, Powering Intelligence: Analyzing Artificial
Intelligence and Data Center Energy Consumption (May 2024)

J. Rand et al., Lawrence Berkeley National Laboratory, Queued Up, 2024 Edition:
Characteristics of Power Plants Seeking Transmission Interconnection As of the End of 2023
(April 2024).

K. Yazzie et al., Opportunities to Grow Tribal Clean Energy in the U.S.: Bold Action is Needed
to Address Unmanageable Time Scales, Limited Access to Information, and a Need to Build
Capacity, Science, April 11, 2024.

U.S. Department of Energy, Pathways to Commercial Liftoff: Innovative Grid Deployment
(April 2024)

Office of the New York State Comptroller, Office of Renewable Energy Siting: Application
Review and Site Permitting for Major Energy Projects, Report No. 2023-S-52 (April 2024)

M. O’Boyle et al., Supporting Advanced Conductor Deployment: Barriers and Policy Solutions,
GridLab & Goldman School of Public Policy, University of California at Berkeley (April 9,
2024)

J. Coleman, Permitting the Energy Transition, SMU Dedman School of Law Legal Research
Paper No. 638 (Mar 2024). 75 Case Western Reserve Law Review (forthcoming).

A. Lawson, Congressional Research Service, Electricity Transmission Permitting Reform
Proposals (Feb 2024)

Rhodium Group & MIT Center for Energy and Environmental Policy Research, Clean
Investment in 2023: Assessing Progress in Electricity and Transport (Feb. 29, 2024)

X. Fishman et al., Bipartisan Policy Center, Finding the Goldilocks Zone for Permitting Reform
(Jan 2024)

                                             F-1
R. Nilson et al., Lawrence Berkeley National Laboratory, Survey of Utility-Scale Wind and Solar
Developers (Jan. 2024)

I. Ko et al., Rural Backlash Could Impede Climate Ambition, Univ. of Penn. Regulatory Review
(Jan. 22, 2024)
C. Harper & D. Schulman, Evergreen Collaborative, Warp Speed Clean Energy – Expediting
Permitting and Equitable Grid Deployment Without Congress (Dec 2023)

J. Arnold & M. Beck, Canadian Climate Institute, Permitting reform for clean energy projects in
New York and California: Promising changes at the state level may hold useful lessons for
Canada (Nov. 14, 2023)

M. Brown & D. Wilson, Stanford Freeman Spogli Institute, NEPA Litigation Over Large Energy
and Transport Infrastructure Projects, 53 Environmental Law Reporter 10836 (October 2023)

Issue Brief, Natural Resources Defense Council, Down to the Wire: Progressive Permitting
Reforms Will Accelerate Renewable Energy and Transmission Buildout and Help Meet U.S.
Climate Targets (Sept. 2023)

The Nature Conservancy, Power of Place: National - Executive Summary (May 2023)

M. Eisenson, Sabin Center for Climate Change Law, Opposition to Renewable Energy Facilities
in the United States: May 2023 Edition (May 2023)

J. Rand et al., Lawrence Berkeley National Laboratory, Queued Up: Characteristics of Power
Plants Seeking Transmission Interconnection as of the End of 2022 (April 2023)

D. Steinberg , National Renewable Energy Laboratory, Evaluating Impacts of the Inflation
Reduction Act and Bipartisan Infrastructure Law on the U.S. Power System (Mar 2023)

R. Sud et al., Brookings Center on Regulation and Markets, How to Reform Federal Permitting
to Accelerate Clean Energy Infrastructure: A Nonpartisan Way Forward (Feb 2023)

P. Denholm et al., National Renewable Energy Laboratory, Examining Supply-Side Options to
Achieve 100% Clean Electricity By 2035 (2022)

G. Wu et al., Proceedings of the National Academy of Sciences, Minimizing Habitat Conflicts in
Meeting Net-Zero Energy Targets in The Western United States (Nov 2022)

J. Pleune, Environmental Law Reporter, Playing The Long Game: Expediting Permitting Without
Compromising Protections (Nov 2022)

P. Bledsoe and E. Sykes, Progressive Policy Institute, America’s Clean Energy Transition
Requires Permitting Reform: Policy Recommendations for Success (Sept 2022)


                                             F-2
The Nature Conservancy, The Power of Place: West – Executive Summary (Aug 2022)

The Nature Conservancy, Voices from the West: Findings from Interviews Regarding Energy On
Tribal Lands – Power of Place West Companion Report (Aug 2022)

D. Stokes, Renewable Energy Federalism, Minnesota Law Review (Apr 2022)
U. Outka, Review Renewable Energy Siting for the Critical Decade, 69 Kansas Law Review 857
(June 2021)

Business Roundtable, Smart Regulation for the Innovation Economy (May 2021)

Business Roundtable, Infrastructure Permitting Priorities (May 2021)

Americans for a Clean Energy Grid, Disconnected: The Need for a New Generator
Interconnection Policy (January 2021)

G. Wu et al., The Nature Conservancy, Power of Place Land Conservation and Clean Energy
Pathways for California (June 2019)

D. Cullenward & S. Welton, The Quiet Undoing: How Regional Electricity Market Reforms
Threaten State Clean Energy Goals, 36 Yale J. on Regulation 106 (2018)

A. Copping, Pacific Northwest National Laboratory, The State of Knowledge for Environmental
Effects Driving Consenting/Permitting for the Marine Renewable Energy Industry (Jan 2018)

D. Drugmand & V. Stori, Clean Energy States Alliance, Distributed Wind Energy Zoning and
Permitting: A Tool Kit for Local Governments (Nov 2017)

D. Mulvaney, Identifying the roots of Green Civil War over utility-scale solar energy projects on
public lands across the American Southwest, 12 Journal of Land Use Science 493 (Oct 2017)

D. Hess et al., Department of Sociology, Vanderbilt University, Red states, green laws: Ideology
and renewable energy legislation in the United States, 11 Energy Research & Social Science 19
(Jan. 2016)

J. Thaler, Fiddling as the World Floods and Burns: How Climate Change Urgently Requires a
Paradigm Shift in The Permitting of Renewable Energy Projects, 42 Environmental Law Journal
1101 (2012)

K.K. DuVivier, The Superagency Solution, 46 McGeorge Law Rev. 189 (2014)

J.. Holtkamp & M. Davidson, Transmission Siting in The Western United States: Getting Green
Electrons to Market, 6 Idaho Law Rev. 379 (2010)

L. Gillette et al., Using Collaboration to Address Renewable Energy Siting Challenges, The
Federal Lawyer (Jun 2009)

                                              F-3
Interlaboratory Working Group, Oak Ridge National Laboratory, Lawrence Berkeley National
Laboratory, National Renewable Energy Laboratory, Scenarios for a Clean Energy Future (Nov
2000)

M. O’Hare et al., Facility Siting and Public Opposition (1983)




                                             F-4
                                     APPENDIX G

                               Organizations Interviewed


The Audubon Society
Avangrid
ClearPath Energy
Enel Green Power North America
esVolta
White House Permitting Improvement Steering Council
NewSun Energy
Northwest & Intermountain Independent Power Producers Association
Puget Sound Energy
Stoel Rives law firm
SWCA Environmental Consultants
Tetra Tech
The Nature Conservancy
State of Washington Energy Facility Site Evaluation Council




                                          G-1
                                                 APPENDIX H

                                   RECENT LEGISLATION OF NOTE

           1.       HB 2039: Consolidated and Expedited Appeals

           On March 28, 2024, Gov. Inslee signed HB 2039, which simplifies and expedites the

process of appeals for clean energy permitting matters. HB 2039 provides that permitting

decisions involving a clean energy project, as defined in HB 1216, can be certified for appeal

directly to the Washington Courts of Appeals. In addition, where a clean energy project requires

multiple permits, appeals of the permits can be consolidated into a single appeal. HB 2039 is a

welcome development that helps reduce delays and legal conflicts where permits for a clean

energy project are appealed.

           2.       SB 5165: Transmission Siting

           In 2023, the Legislature passed SB 5165 to address concerns about transmission planning

and siting in Washington. SB 5165 builds on the Transmission Corridors Work Group, which

was created by Clean Energy Transformation Act and which resulted in the publication of a

report setting forth recommendations for planning, permitting and siting electric transmission

facilities which serves as the basis for some of the recommendations made in this report.203

           SB 5165 includes the following major provisions:

                   Adds transmission planning, including planning around advanced technology and

                    non-wires solutions, to Washington’s requirements for large utilities to produce

                    periodic Integrated Resource Plans.




203
      Final Report, Transmission Corridors Work Group (August 1, 2022).

                                                       H-1
               Adds large transmission facilities (greater than 500 kV AC/300 kV DC, crossing

                two or more counties and two or more utility service territories) to the list of

                facilities required to use the EFSEC process.

               Directs EFSEC to participate in the National Interest Electric Transmission

                Corridors process and to coordinate NEPA reviews with federal agencies

                undertaking reviews of interstate transmission projects.

               Directs EFSEC to undertake a non-project environmental review for transmission

                facilities with a capacity of 230 kV or more, which should identify environmental

                impacts and mitigation measures common to such facilities.

       3.       Transportation Rights of Way: HB 2134 § 214

       As part of the supplemental transportation budget signed by Gov. Inslee on March 28,

2024 the Legislature (in Section 214((7)(a)(i) & (iv)) directed the Department of Transportation

to review and recommend updates to its policy concerning use of state highway rights of way to

accommodate clean energy and connectivity projects, which at a minimum must include

renewable energy and electric transmission and distribution lines. We support this approach and

suggest that rights of way should be open to all types of linear facilities that support

decarbonization, including, for example, pipelines for renewable natural gas, carbon dioxide for

sequestration projects, and green electrolytic hydrogen.

       4.       Geothermal Energy: SB 6039

       Signed on March 28, 2024, SB 6039 aims to promote geothermal energy in Washington

by updating lease rates for geothermal development on state lands, by creating a cost-share

program to support exploration for geothermal resources in Washington, and by directing




                                                H-2
Washington agencies to engage in a collaborative process to identify locations with the greatest

opportunities and risks for geothermal development.

       5.      Carbon Market Linkage: SB 6058

       Also signed on March 28, SB 6058 makes a number of relatively minor corrections and

clarifications to the Climate Commitment Act to facilitate linkage of Washington’s carbon

market with existing markets in California and Quebec.

       6.      Decarbonization of Combined Natural Gas/Electric Utilities: SB 1589

       Another bill signed by Gov. Inslee at the end of the Legislature’s most recent session, SB

1589 adopts a number of measures aimed at facilitating the decarbonization of the natural gas

functions of combined natural gas/electric utilities (primarily Puget Sound Energy) through

electrification and other processes.




                                              H-3


File and source

File
2024_permitting-reform-beveridge-diamond-2024-07-23-1-b12c257d-88ee-457c-af.pdf
Size
998,975 bytes
SHA-256
28dcf2bd3d4636fec6bc571f22f1d519b00f1c2d4d3452c3c2333e9ebbb818c4