Facilities Broadband ARPA SLFRF Quarterly Report (December 2022)
Summary
The Facilities Broadband ARPA SLFRF Quarterly Report for December 2022 from the Virginia Department of Health (VDH), dated 12/31/2022. It states that over the last three months VDH launched a pilot project to deliver broadband to 17 sites across the Commonwealth, selected 3 vendors, and used lessons learned to kick off work at an additional 37 sites. The report covers October through December 2022, with anticipated activities for January through March 2023. Its budget table, as of December 2022, lists $8,000,000 for appropriation, $4,402,000 for commitments/obligations to date and $1,180,000 for expenditures to date.
Summary drafted by a model from the document's text below and checked by script against that text before publication. It is a navigation aid, not a reading of what the document proves. Where AI is used
Cite this document
“Facilities Broadband ARPA SLFRF Quarterly Report (December 2022).”
Archived at Pandemic Darlings, https://pandemicdarlings.com/source-documents/2022-rd904-17b4ce5c57/
, SHA-256 19f8a5a75a16f8a0f7ae0fea7a4c5bbda71948c1451b4bc4a28d4b39aa47df0b.Full text
FACILITIES BROADBAND
American Rescue Plan Act (ARPA) State and Local Fiscal Recovery Fund (SLFRF)
12/31/2022
Facilities Broadband
ARPA SLFRF Quarterly Report
December 2022
Page 2 of 6
Table of Contents
Report Mandate ............................................................................................................................................ 3
Context for ARPA Initiatives .......................................................................................................................... 3
Executive Summary....................................................................................................................................... 3
Objective(s) ................................................................................................................................................... 4
Overview of Quarterly Progress (October – December 2022)...................................................................... 4
Anticipated Next Quarter Activities (January – March 2023) ....................................................................... 5
Risks, Issues, and Management .................................................................................................................... 5
Change Management Considerations........................................................................................................... 6
Project Budget .............................................................................................................................................. 6
Facilities Broadband
ARPA SLFRF Quarterly Report
December 2022
Page 3 of 6
Report Mandate
Chapter 1 Enactment Clause 1, paragraph B.2.P.4., of the amended 2021 Acts of Assembly states, “The
department shall communicate a detailed plan and implementation schedule to the Governor, the Chairs
of the House Appropriations and Senate Finance and Appropriations Committees, and the Director of the
Department of Planning and Budget by September 30, 2021. Additionally, the department shall report
quarterly to the Governor, the Chairs of the House Appropriations and Senate Finance and Appropriations
Committees, and the Director of the Department of Planning and Budget on progress made, with the first
progress report to be delivered not later than December 31, 2021.”
Context for ARPA Initiatives
The Virginia Department of Health (VDH) is excited about the opportunity presented by the appropriation
of ARPA State Fiscal Funds in the August 2021 Special Session II of the General Assembly to improve public
health in Virginia. VDH views this investment as a once in a generation opportunity and will work diligently
to maximize use of funds to initiate, implement and sustain these initiatives. Modifications to VDH’s plans
will be reflected in future quarterly reports.
Executive Summary
The Virginia Department of Health (VDH) seeks to upgrade the internet infrastructure of Local Health
District (LHD) offices and client service areas throughout the Commonwealth to enable the delivery of
broadband service at speeds of at least 100 Megabits per second (Mbps) download and 20 Mbps upload.
As millions of Virginians pivoted to remote work and life during the COVID-19 pandemic, it underscored
the importance of universally available, high-speed, reliable, and affordable broadband coverage for all
citizens. Individuals and families continue to rely on the internet to increase their awareness of COVID
variants, locate local healthcare resources, and request immunization records.
The COVID-19 pandemic exacerbated the demand for timely and accurate health data from VDH, which
is necessary for public health decision-making and transparency with the public. In addition, sufficient
broadband allows for timeliness and accuracy in the delivery of public health resources that use web-
based services (where services are scheduled, documented, and reported via those web-based systems
and are reported to multiple different sources – such as vaccinations to Virginia Immunization Information
System, VIIS).
With nearly 96% of assessed VDH buildings currently unserved by broadband (speeds less than 25 Mbps
download and 3 Mbps upload), significant internet infrastructure upgrades are imperative for VDH to
adequately serve Virginians post-COVID-19. The ARPA SLFRF funding will be used to upgrade unserved
and underserved VDH facilities via fiber optic broadband connection, wireless 5G broadband connection,
or reliable wireline connection.
Over the last three months, VDH has launched a pilot project to deliver broadband to 17 sites across the
Commonwealth. VDH selected 3 vendors capable of servicing the sites and utilized the pilot to test the
quality of these vendors, better understand the end-to-end process for implementing broadband, and
collect lessons learned to apply when implementing broadband at the remaining VDH sites. While the
pilot project is still ongoing, VDH has used lessons learned from the pilot to kick-off Phase 1 of 3 at an
additional 37 sites across the Commonwealth.
Facilities Broadband
ARPA SLFRF Quarterly Report
December 2022
Page 4 of 6
Objective(s)
The objective of this initiative is to add a broadband connection to unserved and underserved VDH
buildings that will reliably deliver speeds of 100 Mbps download and 20-100 Mpbs upload, to:
• Enable internet speeds for the operation of an Electronic Health Records (EHR) system, digitized
records storage, and increasingly automated administrative systems at each location
• Enable adequate bandwidth for employees to support day-to-day operations for the Department
• Provide speeds adequate for two-way video conferencing between VDH and other stakeholders
or patients who are unable to visit in person due to COVID-19
• Increase the capacity of each office to access online systems and resources to more efficiently
complete daily operations and serve clients
Overview of Quarterly Progress (October – December 2022)
Since the submission of the September 2022 quarterly report, VDH has completed the below activities
associated with the Facilities Broadband Initiative. These accomplishments provide VDH a clearer path
forward for Phases 2 and 3 of rollout while finalizing the approach to close out upgrades at Pilot and Phase
1 sites post-SD-WAN upgrades:
Key Activities and Accomplishments
• Pilot Project:
o Completed broadband circuit installation at 16 of 17 sites, including construction to lay
new fiber lines, where needed. As a next step on the critical path, the Virginia IT Agency
(VITA) and Verizon will install Secured Software Designed Wide Area Network (SD-WAN)
before LHD staff experience upgraded service.
• Rollout to Remaining Sites: Phase 1 of 3:
o Completed broadband circuit installation at 21 of 40 Phase 1 sites, including construction
to lay new fiber lines, where needed. As the next step, SD-WAN will be installed at sites.
o Began construction for broadband upgrades at 13 additional Phase 1 sites. Finalized
vendor assignment to remaining 6 sites that are in locations that needed additional
vendor support to provide coverage.
• Rollout to Remaining Sites: Phase 2 of 3:
o Kicked-off broadband upgrades at 55 sites in Phase 2 and briefed local LHD contacts on
rollout process, LHD responsibilities, and lessons learned from the Pilot and Phase 1.
o Completed broadband circuit installation at 1 of 55 Phase 2 sites, including construction
to lay new fiber lines, where needed. As the next step, SD-WAN will be installed at the
site.
o Began construction for broadband upgrades at remaining 54 of 55 Phase 2 sites.
• Planning and Communications:
o Worked with VITA and Verizon leadership and technical teams to begin planning SD-WAN
rollout and provide all necessary data to complete upgrades. Tentative timeline is to start
these upgrades in January and finish SD-WAN upgrades at VDH sites in the first quarter of
2023
Facilities Broadband
ARPA SLFRF Quarterly Report
December 2022
Page 5 of 6
o Used agency-wide forums, the VDH intranet site, and leadership briefings to share site
status and answer stakeholders’ questions about rollout.
o Met with all vendors conducting upgrades in weekly check-ins to track construction status
and troubleshoot site-specific issues.
Anticipated Next Quarter Activities (January – March 2023)
The following outlines the activities and tasks planned from January through March 2023:
• Pilot Project:
o Finish broadband vendor construction at remaining Pilot site
o Work with VITA and Verizon to install SD-WAN at Pilot sites and align on any additional
steps needed before VDH employees can experience increased services
o Activate sites and test speeds so that upgraded services are experienced by VDH
employees. Capture “success stories” from employees to share with VDH leadership and
other stakeholders
o Conduct wireless site assessments and begin upgrading Wireless Access Points (WAPs) to
ensure upgraded speeds are user-friendly and available both hard-wired and over Wi-Fi
• Full Broadband Rollout: Phases 1-3:
o Continue monitoring upgrades at Phase 1-2 sites. Work with broadband vendors and local
site contacts to resolve any site-specific challenges that arise. Target is to complete Phase
1 sites in next quarter of 2023, with many Phase 2 sites expected to be completed
o Begin broadband upgrades at remaining Phase 3 sites in February
o Support VITA and Verizon installation of SD-WAN and as well as any needed Wireless
Access Point (WAP) upgrades needed at sites. Monitor progress and coordinate
broadband upgrade timeline to ensure minimal delay in services
Risks, Issues, and Management
• Risk 1: If there are supply chain delays on inventory, then the Broadband project could be
delayed
o Mitigation Strategy: Mitigate procurement delays for critical equipment and materials by
planning and scheduling in collaboration with vendors. These measures will empower the
VDH-IT team to confidently sequence projects and enable broadband technicians and
engineers to assess site and facility conditions and order necessary equipment and
materials with sufficient lead time between material ordering and the scheduled start
date for installation.
• Risk 2: If VDH funding to support broadband services charges are insufficient once the ARPA funds
expire, then sites will lose service
o Mitigation Strategy: Monitor budget projections to determine when current ARPA
funding will expire and when requests need to be submitted for additional funds. If
additional funds are not available, VDH will remove the wireline service and use those
Facilities Broadband
ARPA SLFRF Quarterly Report
December 2022
Page 6 of 6
savings to pay for the Broadband service. This will result in no failover (backup)
connectivity if broadband service is disrupted.
• Risk 3: If VITA SD-WAN installation does not occur by March 2023 and/or does not provide the
expected connection to services, then upgrade timeline may extend beyond FY23.
o Mitigation Strategy: VITA and VDH are beginning regular meetings as VITA/Verizon
rollout SD-WAN across sites. VDH has provided updated site lists and other requested
data to VITA. VITA planning to provide VDH-specific timeline in the coming weeks.
• Issue 1: VDH will be charged for sites where vendor construction is finished, but VDH employees
cannot access the faster speeds until VITA SD-WAN installation completes and testing and final
connection is finished.
o Mitigation Strategy: 6 sites have completed all broadband-related construction and are
being billed to VDH, while awaiting SD-WAN install and final site testing. All other sites
that have completed construction will not begin billing VDH until end December 2022 and
early January 2023.
Change Management Considerations
VDH understands that successful transformation initiatives rely on more than just the right technology,
processes, and resources. They also depend on effective communications and engagement strategies to
equip stakeholders with the information and guidance that they need to support the changes taking place.
For the Broadband initiative, the successful implementation of critical upgrades will depend on ongoing
two-way communication and engagement with a variety of local contacts.
These activities have been outlined in a communications plan that maps key internal and external
stakeholders, assesses how they may be impacted and/or their role in supporting the effort, and establish
strong feedback loops and channels for information-sharing. The primary objective of the strategy is to
demonstrate VDH’s transparency through regular updates to all impacted groups. Core communications
channels include regular status updates to stakeholders via email, an intranet site to house content for
internal stakeholders, an initiative-specific email inbox for two-way communication, and regular briefings
to Central Office and LHD stakeholders across a variety of VDH forums.
Project Budget
Budget, Obligations, and Actuals as of December 2022
Total
Total Total
$8,000,000 Commitments/ $4,402,000 Expenditures $1,180,000$
Appropriation Obligations (To Date)
(To Date)
File and source
- File
- 2022-RD904.pdf
- Size
- 196,782 bytes
- SHA-256
- 19f8a5a75a16f8a0f7ae0fea7a4c5bbda71948c1451b4bc4a28d4b39aa47df0b
- Our copy
- 2022-RD904.pdf
- Original
- No public link identified.