Facilities Broadband ARPA SLFRF Quarterly Report (June 2022)
Summary
A quarterly report dated 6/30/2022 on the Facilities Broadband initiative of the Virginia Department of Health (VDH), funded through the American Rescue Plan Act (ARPA) State and Local Fiscal Recovery Fund (SLFRF). It states that VDH seeks to upgrade the internet infrastructure of Local Health District offices and client service areas, and that VDH launched a pilot project to deliver broadband and used lessons learned to begin rollout to remaining sites. It lists activities planned for July through September 2022 and risks, including the need for a security solution to be live at sites before installed services launch. The budget section gives a total appropriation of $8,000,000 and an FY22 appropriation of $1,840,000.
Summary drafted by a model from the document's text below and checked by script against that text before publication. It is a navigation aid, not a reading of what the document proves. Where AI is used
Cite this document
“Facilities Broadband ARPA SLFRF Quarterly Report (June 2022).”
Archived at Pandemic Darlings, https://pandemicdarlings.com/source-documents/2022-rd313-5bf8a19294/
, SHA-256 5fc07aaec6ce24a9cea7f2ec242f3e75217d133e1b04c662afa29c6ab8bffbcc.Full text
FACILITIES BROADBAND
American Rescue Plan Act (ARPA) State and Local Fiscal Recovery Fund (SLFRF)
6/30/2022
Facilities Broadband
ARPA SLFRF Quarterly Report
June 2022
Page 2 of 7
Table of Contents
Report Mandate 3
Context for ARPA Initiatives 3
Executive Summary 3
Objective(s) 4
Overview of Quarterly Progress (April – June 2022) 4
Anticipated Next Quarter Activities (July – September 2022) 5
Risks and Risk Management 6
Change Management Considerations 7
Project Budget 7
Facilities Broadband
ARPA SLFRF Quarterly Report
June 2022
Page 3 of 7
Report Mandate
Chapter 1 Enactment Clause 1, paragraph B.2.P.4., of the amended 2021 Acts of Assembly states, “The
department shall communicate a detailed plan and implementation schedule to the Governor, the Chairs
of the House Appropriations and Senate Finance and Appropriations Committees, and the Director of the
Department of Planning and Budget by September 30, 2021. Additionally, the department shall report
quarterly to the Governor, the Chairs of the House Appropriations and Senate Finance and Appropriations
Committees, and the Director of the Department of Planning and Budget on progress made, with the first
progress report to be delivered not later than December 31, 2021.”
Context for ARPA Initiatives
The Virginia Department of Health (VDH) is excited about the opportunity presented by the appropriation
of ARPA State Fiscal Funds in the August 2021 Special Session II of the General Assembly to improve public
health in Virginia. VDH views this investment as a once in a generation opportunity and will work diligently
to maximize use of funds to initiate, implement and sustain these initiatives. Modifications to VDH’s plans
will be reflected in future quarterly reports.
Executive Summary
The Virginia Department of Health (VDH) seeks to upgrade the internet infrastructure of Local Health
District (LHD) offices and client service areas throughout the Commonwealth to enable the delivery of
broadband service at speeds of at least 100 Megabits per second (Mbps) download and 20 Mbps upload.
As millions of Virginians pivoted to remote work and life during the COVID-19 pandemic, it underscored
the importance of universally available, high-speed, reliable, and affordable broadband coverage for all
citizens. Individuals and families continue to rely on the internet to increase their awareness of COVID
variants, locate local healthcare resources, and request immunization records.
The COVID-19 pandemic exacerbated the demand for timely and accurate health data from VDH, which
is necessary for public health decision-making and transparency with the public. In addition, sufficient
broadband allows for timeliness and accuracy in the delivery of public health resources that use web-
based services (where services are scheduled, documented, and reported via those web-based systems
and are reported to multiple different sources – such as vaccinations to Virginia Immunization Information
System, VIIS).
With nearly 96% of assessed VDH buildings currently unserved by broadband (speeds less than 25 Mbps
download and 3 Mbps upload), significant internet infrastructure upgrades are imperative for VDH to
adequately serve Virginians post- COVID-19. The ARPA SLFRF funding will be used to upgrade unserved
and underserved VDH facilities via fiber optic broadband connection, wireless 5G broadband connection,
or reliable wireline connection.
Over the last three months, VDH has launched a pilot project to deliver broadband to 17 sites across the
Commonwealth. VDH selected 3 vendors capable of servicing the sites and utilized the pilot to test the
quality of these vendors, better understand the end-to-end process for implementing broadband, and
collect lessons learned to apply when implementing broadband at the remaining VDH sites. While the
pilot project is still ongoing, VDH has used lessons learned from the pilot to kick-off Phase 1 of 3 at an
additional 37 sites across the Commonwealth.
Facilities Broadband
ARPA SLFRF Quarterly Report
June 2022
Page 4 of 7
Objective(s)
The objective of this initiative is to add a broadband connection to unserved and underserved VDH
buildings that will reliably deliver speeds of 100 Mbps download and 20-100 Mpbs upload, to:
• Enable internet speeds for the operation of an Electronic Health Records (EHR) system, digitized
records storage, and increasingly automated administrative systems at each location
• Enable adequate bandwidth for employees to support day-to-day operations for the department
• Provide speeds adequate for two-way video conferencing between VDH and other stakeholders
or patients who are unable to visit in person due to COVID-19
• Increase the capacity of each office to access online systems and resources to more efficiently
complete daily operations and serve clients
Overview of Quarterly Progress (April – June 2022)
Since the submission of the March 31, 2022 quarterly report, VDH has completed the below activities
associated with the Facilities Broadband Initiative. These accomplishments allow VDH to incorporate
lessons learned from the ongoing Pilot Project to start Phase 1:
Key Activities and Accomplishments
• Pilot Project
o Completed broadband vendor construction at 10 sites, including laying new fiber lines,
where needed. However, all sites will require additional security upgrades to meet VITA
requirements before upgraded service is experienced by LHD staff.
o Managed broadband upgrades at 7 remaining pilot sites via management check-ins with
vendors: resolved challenges faced by the LHDs and vendors, as needed. Two of these
sites have ongoing construction that will be completed in mid-summer. The 5 remaining
sites have met challenges that have slowed progress (e.g., local permitting challenges or
additional preparedness upgrades needed on sites) and will not be completed until late
summer.
• Rollout to Remaining Sites: Phase 1 of 3
o Received quotes and assigned vendors to Phase 1 sites. Vendor quotes and Pilot Project
successes confirmed decision to utilize the same 3 VITA-approved Broadband service
providers that are servicing the Pilot sites. Vendors continue to offer competitive pricing
including steeper discounts for Phase 1 than provided during the Pilot Project.
o Submitted work orders to begin upgrades at Phase 1 sites. Notified LHDs and hosted kick-
off meetings with point of contact from sites to explain the implementation process, LHD
responsibilities, and other lessons learned.
Facilities Broadband
ARPA SLFRF Quarterly Report
June 2022
Page 5 of 7
• Internal Engagement
o Created live tracking document to track site status, updates from vendors, and next steps
at sites in real-time. Used agency-wide forums to share site status and answer LHDs
stakeholders’ questions about rollout.
o Defined procurement and invoicing process to track costs related to supplemental
construction / room readiness upgrades that are required at some sites before broadband
vendor construction can begin.
• External Engagement
o Continued to work with the VA Department of Housing and Community Development
(DHCD) and included Department of Social Services (DSS) to determine how the agencies’
projects can collaborate across the Commonwealth’s overall Broadband strategy. The
agencies are currently in discussions with VITA around updating VITA policy to allow for
shared services, avoiding duplicative costs to the Commonwealth.
Anticipated Next Quarter Activities (July – September 2022)
The following outlines the activities and tasks planned from July through September 2022:
• Pilot Project
o Finish broadband vendor construction at remaining Pilot sites
o Install required security features before activating upgraded broadband services at LHD
sites
• Full Broadband Rollout: Phases 1-3
o Manage rollout of broadband upgrades at 37 Phase 1 sites using lessons learned from the
pilot program to minimize risk and exposure to unforeseen changes
o Survey all sites to understand wireless capabilities. Plan and implement wireless upgrades
at sites, as needed, to ensure that sites can fully utilize their new broadband services and
that future VDH needs (e.g., electronic health records) will be fully supported
o Support joint DHCD-DSS-VDH efforts to align broadband expansion across the
Commonwealth and find opportunities for collaboration, cost savings, and efficiency
through shared broadband services
Facilities Broadband
ARPA SLFRF Quarterly Report
June 2022
Page 6 of 7
Risks and Risk Management
• Risk 1: In order to launch the broadband services that have been installed, it is necessary for a
security solution (SD-WAN or Secure Gateway) to be live at the sites
o Mitigation Strategy: Secure Gateway will be used as an initial security solution, while
the use of SD-WAN is evaluated as a longer-term solution. The evaluation of SD-WAN
will be completed prior to the EHR implementation.
• Risk 2: The overall cost of the Broadband project could be exceeded if the actual costs exceed the
estimated project cost
o Mitigation Strategy: Conduct a pilot project to better understand the cost across the
timeline of the project to create a total cost projection to better estimate the overall cost
of the state-wide rollout. This will then be used to research opportunities to advocate for
cost reductions to centrally purchased tools (e.g., security features) or find cost savings
with vendors.
• Risk 3: The level of effort required to manage the Broadband project may exceed the available
resources within the VDH team, which would result in timeline delays. Additionally, the recently
announced departure of a key VDH-OIM team member may increase the severity of this risk.
o Mitigation Strategy: Use the pilot project to better estimate the necessary resources to
manage the state-wide rollout. VDH has subsequently brought on two additional
contractor resources for both project management and network engineering support.
• Risk 4: VDH funding to support broadband services charges funds may be insufficient once the
ARPA funds expire, resulting in the sites losing service
o Mitigation Strategy: VDH is beginning to assess ongoing service fees to request additional
funds for when ARPA funds expire. If additional funds are not available, VDH will remove
the wireline service and use those savings to pay for the Broadband service. This will result
in no failover (backup) connectivity if Broadband service is disrupted.
• Risk 5: There is a dependency on the availability of the hardware that is necessary to make the
broadband upgrades at each site – if there are supply chain delays on inventory, then the
Broadband project could be delayed
o Mitigation Strategy: The impacts of procurement delays to critical equipment and
material deliveries can be mitigated through comprehensive planning and scheduling
efforts through collaboration with vendors. These measures will empower the VDH-IT
team to confidently sequence projects and enable broadband technicians and engineers
to assess site and facility conditions and order necessary equipment and materials with
sufficient lead time between material ordering and the scheduled start date for
installation.
Facilities Broadband
ARPA SLFRF Quarterly Report
June 2022
Page 7 of 7
Change Management Considerations
VDH understands that successful transformation initiatives rely on more than just the right technology,
processes, and resources. They also depend on effective change management, communications, and
engagement strategies to ensure stakeholders are equipped with the information and guidance that they
need to support the changes. For the Broadband initiative, the successful implementation of critical
upgrades will depend on ongoing two-way communication and engagement with a variety of local
contacts.
These activities have been outlined in a communications plan that maps key internal and external
stakeholders, assesses how they may be impacted and/or their role in supporting the effort, and establish
strong feedback loops and channels for information-sharing. The primary objective of the strategy is to
convey and ensure VDH-IT's transparency through regular updates to all impacted groups. Core
communications channels include regular status updates to stakeholders via email, an intranet site to
house content for internal stakeholders, an initiative-specific email inbox for two-way communication,
and regular briefings to Central Office and LHD stakeholders across a variety of VDH forums.
Project Budget
The project groups in the table below have been updated since the work plans submitted on 9/30/2021,
due to the removal of wireline projects included in the initiative’s original scope.
Total Appropriation: $8,000,000
FY22 Appropriation: $1,840,000
Budget, Obligations, Actuals, and Remaining Spend as of June 15,2022
Project FY22 FY22 YTD FY22 YTD Current Period FY22 Remaining
Category Budget Obligations Actuals* Expenditures* Spend
Service Charge $ 609,667 $ 545,000 $ - $ - $ 609,667
Construction Costs $ 582,667 $ 90,000 $ - $ - $ 582,667
Other Initiative Needs $ 647,667 $ 583,500 $ 337,150 $ 63,550 $ 310,517
Total $ 1,840,000 $ 1,218,500 $ 337,150 $ 63,550 $ 1,502,850
* Expenditures represent transactions that have posted in Cardinal F&A as of 6/15/2022
File and source
- File
- 2022-RD313.pdf
- Size
- 245,324 bytes
- SHA-256
- 5fc07aaec6ce24a9cea7f2ec242f3e75217d133e1b04c662afa29c6ab8bffbcc
- Our copy
- 2022-RD313.pdf
- Original
- No public link identified.