Summary

A quarterly report dated 3/31/2022 on the Facilities Broadband initiative of the Virginia Department of Health (VDH), funded through the American Rescue Plan Act (ARPA) State and Local Fiscal Recovery Fund (SLFRF). It states that VDH seeks to upgrade internet infrastructure at Local Health District offices to speeds of at least 100 Megabits per second (Mbps) download and 20 Mbps upload. It describes a pilot project for 17 sites and lists risks and activities planned for April through June 2022. The budget section gives a total appropriation of $8,000,000 and an FY22 appropriation of $1,840,000.

Summary drafted by a model from the document's text below and checked by script against that text before publication. It is a navigation aid, not a reading of what the document proves. Where AI is used

Cite this document

“Facilities Broadband ARPA SLFRF Quarterly Report (March 2022).” Archived at Pandemic Darlings, https://pandemicdarlings.com/source-documents/2022-rd186-f69f731192/, SHA-256 75fcb2df100f3983e5496b2dbc4000694094a16e28dfe16997a9accb6fd7c175.

Full text

                      FACILITIES BROADBAND
American Rescue Plan Act (ARPA) State and Local Fiscal Recovery Fund (SLFRF)




                                3/31/2022
Facilities Broadband
ARPA SLFRF Quarterly Report
March 2022
Page 2 of 8


Table of Contents
Report Mandate                                                                                      3
Context for ARPA Initiatives                                                                        3
Executive Summary                                                                                   3
Objective(s)                                                                                        4
Overview of Quarterly Progress (Jan – March 2021)                                                   4
  Comments on Alignment to plan submitted in September 2021                                         5
Anticipated Next Quarter Activities (April – June 2022)                                             5
Risks and Risk Management                                                                           6
Change Management Considerations                                                                    7
Project Budget                                                                                      8
  The project groups in the table below have been updated since the work plans submitted on 9/30/2021,
  due to the removal of wireline projects included in the initiative’s original scope.              8
  Total Appropriation                                                                               8
  Cumulative Actuals, Obligations, and Appropriations, through March 14, 2022                       8
Facilities Broadband
ARPA SLFRF Quarterly Report
March 2022
Page 3 of 8


Report Mandate
Chapter 1 Enactment Clause 1, paragraph B.2.P.4., of the amended 2021 Acts of Assembly states, “The
department shall communicate a detailed plan and implementation schedule to the Governor, the Chairs
of the House Appropriations and Senate Finance and Appropriations Committees, and the Director of the
Department of Planning and Budget by September 30, 2021. Additionally, the department shall report
quarterly to the Governor, the Chairs of the House Appropriations and Senate Finance and Appropriations
Committees, and the Director of the Department of Planning and Budget on progress made, with the first
progress report to be delivered not later than December 31, 2021.”



Context for ARPA Initiatives
The Virginia Department of Health (VDH) is excited about the opportunity presented by the appropriation
of ARPA State Fiscal Funds in the August 2021 Special Session II of the General Assembly to improve public
health in Virginia. VDH views this investment as a once in a generation opportunity and will work diligently
to maximize use of funds to initiate, implement and sustain these initiatives. Simultaneously, VDH is fully
engaged in responding to COVID-19 and protecting the health of Virginians. Currently, VDH is developing
project plans to minimize the impacts of the public health emergency on local health departments in the
first year and will be flexible in the implementation of these initiatives as dictated by the emergency
response. Modifications to VDH’s plans will be reflected in future quarterly reports.



Executive Summary
The Virginia Department of Health (VDH) seeks to upgrade the internet infrastructure of Local Health
District (LHD) offices and client service areas throughout the Commonwealth to enable the delivery of
broadband service at speeds of at least 100 Megabits per second (Mbps) download and 20 Mbps upload.
As millions of Virginians pivoted to remote work and life during the COVID-19 pandemic, it underscored
the importance of universally available, high-speed, reliable, and affordable broadband coverage for all
citizens. Individuals and families continue to rely on the internet to increase their awareness of COVID
variants, locate local healthcare resources, and request immunization records.

The COVID-19 pandemic exacerbated the demand for timely and accurate health data from VDH, which
is necessary for public health decision-making and transparency with the public. In addition, sufficient
broadband allows for timeliness and accuracy in the delivery of public health services that use web-based
services (where services are scheduled, documented, and reported via those web-based systems and are
reported to multiple different sources – such as vaccinations to Virginia Immunization Information
System, VIIS).

With nearly 96% of assessed VDH buildings currently unserved or underserved by broadband (speeds less
than 25 Mbps download and 3 Mbps upload), significant internet infrastructure upgrades are imperative
for VDH to adequately serve Virginians post- COVID-19. The ARPA SLFRF funding will be used to upgrade
unserved and underserved VDH facilities via fiber optic broadband connection, wireless 5G broadband
connection, or reliable wireline connection.
Facilities Broadband
ARPA SLFRF Quarterly Report
March 2022
Page 4 of 8


Over the last three months, VDH has launched a pilot project to deliver broadband to 17 sites across the
Commonwealth. The pilot is intended to test the quality of the selected vendors, better understand the
end-to-end process for implementing broadband, and collect lessons learned to apply when implementing
broadband at the remaining VDH sites.

Objective(s)
The objective of this initiative is to add a broadband connection to unserved and underserved VDH
buildings that will reliably deliver speeds of 100 Mbps download and 20-100 Mpbs upload, to:

   •    Enable internet speeds for the operation of an Electronic Health Records (EHR) system, digitized
        records storage, and increasingly automated administrative systems at each location

   •    Enable adequate bandwidth for employees to support day to day operations for the department

    •   Provide speeds adequate for two-way video conferencing between VDH and other stakeholders
        or patients who are unable to visit in person due to COVID-19

   •    Increase the capacity of each office to access online systems and resources to more efficiently
        complete daily operations and serve clients



Overview of Quarterly Progress (Jan – March 2021)
Since the submission of the December 31, 2021 quarterly report, VDH has completed the below activities
associated with the Facilities Broadband Initiative. These accomplishments have positioned VDH to begin
broadband service upgrades at VDH facilities in the coming months:

    •   Pilot Program

            o   Selected 3 VITA approved Broadband service providers. The selection process was based
                on price, schedule, and experience in the Commonwealth. It included 20+ coordinated
                calls to better understand quotes and VITA contract constraints

            o   Submitted work orders to begin work on each of the 17 pilot sites with the 3 selected
                vendors. 4 of the 17 sites have completed site assessments. Vendors expect sites to be
                complete between May 2022 and August 2022 depending on the complexity of the
                construction

            o   Developed schedule of logically sequenced activities for VDH facilities broadband
                upgrades, from planning to implementation to closeout.

            o   Scheduled weekly project management meetings with each of the three vendors to
                actively track projects and mitigate issues that arise

    •   Internal Engagement
Facilities Broadband
ARPA SLFRF Quarterly Report
March 2022
Page 5 of 8


            o   Met regularly with department leadership team to report on progress of the project.
                Additionally, met regularly on agency-wide forums to report on progress and answer
                questions

    •   External Engagement

            o   Met with the VA Department of Housing and Community Development (DHCD) to
                determine how the VDH Broadband project could best collaborate within the
                Commonwealth’s overall Broadband strategy. DHCD has agreed to leverage existing GIS
                maps to help inform VDH on sequencing of future site batches

            o   Met with VITA Broadband contacts multiple times to resolve questions on Broadband
                contracts

            o   Continued coordination with Department of Social Services on broadband and SD WAN
                efforts

Comments on Alignment to plan submitted in September 2021

The activities completed since the September 30, 2021 submission of the initial workplan have been
important components of the Discovery & Facility Assessment project phase that, as outlined in the
September workplan, was scheduled to continue through March 2022. The implementation of a fiber
broadband pilot program prior to conducting site assessments for all facilities was not explicitly outlined
as a step in the initial workplan but was identified as an important phase that will allow VDH to refine the
facility upgrade process and gain efficiencies in the future. VDH will first focus on completing pilot site
upgrades upon completion of the Discovery & Assessment phase. VDH then plans to use lessons learned
to optimize the upgrade process before initiating the full implementation of site upgrades across the
Commonwealth.



Anticipated Next Quarter Activities (April – June 2022)
The following outlines the activities and tasks planned from April through June 2022:

    •   Pilot Program

            o   Complete at least 50% of the pilot sites with new broadband service

            o   Document the lessons learned and apply to planning for the implementation of
                broadband at the remaining sites

            o   Continue to monitor the remaining sites in the pilot program

    •   Full Implementation
Facilities Broadband
ARPA SLFRF Quarterly Report
March 2022
Page 6 of 8


           o   Utilize the sequencing tool to generate a project sequence for the remaining facility
               upgrades. Sites will be upgraded in batches, beginning with locations with the greatest
               need.

           o   Begin the process to identify and select vendors to implement the next batch of site
               upgrades. Lessons learned from the pilot program will be leveraged to minimize risk and
               exposure to unforeseen changes.

           o   Begin construction with Phase 1 sites



Risks and Risk Management
   •   Risk 1: EHR, Records Management, and Administrative Systems are all successor initiatives to
       the Facilities Broadband initiative and could be drastically impacted by communication or
       coordination shortcomings between the respective initiatives and the Broadband initiative.
            o Mitigation Strategy: The Broadband team will continue to collaborate closely with the
                EHR, Records Management, and Administrative Systems Initiative teams to confirm that
                VDH facilities are being scheduled for broadband upgrades prior to broadband-reliant
                system implementations.
   •   Risk 2: Sites are unique with varying access to broadband service. The initial plan assumes some
       degree of uniformity across all sites to identify likely candidates for fiber, wireless, or wireline
       broadband and the associated implementation complexity and costs; however, until individual
       site assessments are completed the exact needs at each site will not be known.

           o   Mitigation Strategy: The initial site estimates will include high and low estimates of
               expenses, resources use, and time to complete to “plan for the worst” and build in
               contingency for unexpected outcomes from site assessments.

   •   Risk 3: VDH’s reliance on broadband vendors for material and equipment procurement and
       installation exposes the agency to a variety of potential risks, such as contractor’s experiencing
       unforeseen labor shortages, contractor’s inaccurately estimating the schedule or cost of a
       project, or contractor’s incorrectly installing upgrades, resulting in activation delays. These risks
       are outlined below for each service type:

           o   Wireline Broadband – these upgrades require significant coordination with VITA/Verizon
               supplier and site to perform site assessments, Verizon local phone carriers, localities, and
               state agencies for major construction and VDH sourced providers upgrade for minor site
               improvements to include cabling and conduit.

           o   Fiber Broadband – these upgrades will require coordination with local broadband
               engineers to bring fiber optic cable from the nearest network to the premises and to
               install the necessary hardware within the facility. Finally, the service provider will be
               engaged to activate the service.
Facilities Broadband
ARPA SLFRF Quarterly Report
March 2022
Page 7 of 8


            o   Wireless Broadband – these upgrades require the least outside dependency, relying only
                on hardware installation and remote service activation.

            o   Mitigation Strategy: Based on the results of the initial site assessment, the initiative team
                will coordinate with contractors to establish the scope and realistic timelines to complete
                the work with the available resources.

    •   Risk 4: There is another dependency on the availability of the hardware that is necessary to make
        the broadband upgrades at each site – if there are supply chain delays on inventory, then the
        Broadband project could be delayed.

            o   Mitigation Strategy: The impacts of procurement delays to critical equipment and
                material deliveries can be mitigated through comprehensive planning and scheduling
                efforts through collaboration with vendors. These measures will empower the VDH-IT
                team to confidently sequence projects and enable broadband technicians and engineers
                to assess site and facility conditions and order necessary equipment and materials with
                sufficient lead time between material ordering and the scheduled start date for
                installation.

    •   Risk 5: If VDH does not receive additional funds to support broadband service charges after the
        ARPA funds expire, the sites may lose service

            o   Mitigation Strategy: VDH is beginning to assess ongoing service fees to request additional
                funds for when ARPA funds expire. If additional funds are not available, VDH will remove
                the wireline service and use those savings to pay for the Broadband service. This will result
                in no failover (backup) connectivity if Broadband service is disrupted.

Change Management Considerations
VDH understands that successful transformation initiatives rely on more than just the right technology,
processes, and resources. They also depend on effective change management, communications, and
engagement strategies to ensure stakeholders are equipped with the information and guidance that they
need to support the changes. For the Broadband initiative, the successful implementation of critical
upgrades will depend on ongoing two-way communication and engagement with a variety of local
contacts.

These activities have been outlined in a communications plan that maps key internal and external
stakeholders, assesses how they may be impacted and/or their role in supporting the effort, and establish
strong feedback loops and channels for information-sharing. The primary objective of the strategy is to
convey and ensure VDH-IT's transparency through regular updates to all impacted groups. Core
communications channels will include monthly status updates via email and an intranet site to house
content for internal stakeholders. Feedback loops will include monthly surveys and office hours, as well
as an initiative-specific email inbox for two-way communication.
Facilities Broadband
ARPA SLFRF Quarterly Report
March 2022
Page 8 of 8


Project Budget
The project groups in the table below have been updated since the work plans submitted on 9/30/2021,
due to the removal of wireline projects included in the initiative’s original scope.

Total Appropriation: $8,000,000
FY22 Appropriation: $1,840,000


Cumulative Actuals, Obligations, and Appropriations, through March 14, 2022

 Project Group                    Current Period       FY22 YTD         FY22 YTD                   FY22
                                         Actuals         Actuals       Obligations        Appropriations
 Service Charge                              $0                 $0                $0             $54,000
 Construction Costs                          $0                 $0                $0             $54,000
 Other Initiative Needs                $276,000           $276,000          $504,000          $1,732,000
 Totals                                $276,000           $276,000          $504,000          $1,840,000
*Actuals represent transactions that have posted in Cardinal Web F&A as of 3/14/2022


File and source

File
2022-RD186.pdf
Size
247,670 bytes
SHA-256
75fcb2df100f3983e5496b2dbc4000694094a16e28dfe16997a9accb6fd7c175
Our copy
2022-RD186.pdf
Original
No public link identified.
Back to top