Summary

The 2022 Impact Fee Deferral Report, an annual report to the Legislature per RCW 43.31.980 by the Washington State Department of Commerce, Growth Management Services, dated December 19, 2022. The introduction explains the deferral program established by Chapter 241, Laws of 2015 (SB 5923), under which builders may defer impact fees for up to 18 months, and describes this as the fifth annual report. Commerce surveyed 179 counties, cities and towns in October 2022 and received 51 responses, a 28.5% response rate. Tables report 1,394 deferrals requested and issued across fire protection, parks, schools and transportation fees, with 410 not paid fully or on time, broken out by jurisdiction such as Kitsap County, Ridgefield and Olympia.

Summary drafted by a model from the document's text below and checked by script against that text before publication. It is a navigation aid, not a reading of what the document proves. Where AI is used

Cite this document

“2022 Impact Fee Deferral Report.” Original at app.leg.wa.gov. Archived at Pandemic Darlings, https://pandemicdarlings.com/source-documents/2022-commercereports-2022-impact-fee-deferral-report-a5b61f85-b5c2-41e1-914/, SHA-256 d091c53207c7bbe364df593398a5f0ab5376231715e0ae50478fdfea0336ddf7.

Full text

 2022 Impact Fee Deferral
 Report



   Annual report per RCW 43.31.980




                                     December 19, 2022
       LOCAL GOVERNMENT DIVISION
       GROWTH MANAGEMENT
       SERVICES                      Report to the Legislature

                                     Director Lisa Brown
V3.1
Acknowledgments

Washington State Department of Commerce
Mark K. Barkley, Assistant Director,
Local Government Division

Growth Management Services
Dave Andersen, AICP, Managing Director

Valerie Smith, Deputy Managing Director

Paul Johnson, Operations Manager

Matt Ojennus, Senior Planner

GROWTH MANAGEMENT SERVICES
Dave Andersen, AICP, Managing Director
dave.andersen@commerce.wa.gov
Phone: 409-434-4491

1011 Plum St. SE
P.O. Box 42525
Olympia, WA 98504-2525

www.commerce.wa.gov

For people with disabilities, this report is available on
request in other formats. To submit a request, please
call 360-725-4000 (TTY 360-586-0772)




 2022 IMPACT FEE DEFERRAL REPORT
Table of Contents
Introduction ................................................................................................................................................. 2

Deferral data................................................................................................................................................ 3




  2022 IMPACT FEE DEFERRAL REPORT                                                                                                                           1
Introduction
Authorizing legislation
Per RCW 43.31.980, the Department of Commerce (Commerce) must annually report on the deferral process
for impact fees as follows:

1) Beginning December 1, 2018, and each year thereafter, the department of commerce must prepare an
   annual report on the impact fee deferral process establish in RCW 82.02.050(3). The report must include
   (a) The number of deferrals requested of and issued by counties, cities, and towns; (b) the number of
   deferrals that were not fully and timely paid; and (c) other information as deemed appropriate.

2) The report required by this section must, in accordance with RCW 43.01.036, be submitted to the
   appropriate committees of the house of representatives and the senate.

Commerce published its first report in 2018. This is the fifth annual report.

Background
During the 2015 session, the Washington State Legislature passed Chapter 241, Laws of 2015 (SB 5923),
which in part established a deferral program for impact fees. Local governments fully planning under RCW
36.70A (the Growth Management Act) can collect impact fees for fire protection facilities, transportation
facilities, parks and schools. Local governments can choose to charge different rates for different classes of
construction, such as residential, commercial and retail. Local governments can also choose to collect impact
fees on only a single type of construction. Except under specific circumstances, a local government must
refund fees not expended or dedicated within 10 years of collection.

All local governments imposing impact fees were required to establish an impact fee deferral program by
September 1, 2016.

The deferral program applies to builders. Local governments can allow for a minimum of 20 deferrals of single-
family homes built per year by a builder, and have the option to permit more. The deferral can last no longer
than 18 months. At minimum, the local government must offer builders at least one of the following options to
defer collection of the impact fee payment:

      Payment of the final property inspection
      Issuance of a certificate of occupancy or similar certificate
      Closing of the first sale of the property occurring after issuance of the applicable building permit

Report methodology
Commerce collected data for this report using SurveyMonkey in October 2022. There were 17 questions.
Planning directors, permitting departments and city administrators were notified of the survey by email.

Survey responses
Commerce sent the survey to 179 counties, cities and towns. Of those, 51 responded (28.5% response rate).
Twenty-six respondents required impact fees and 24 reported issuing deferrals. All deferral requests were
granted and only two communities did not have deferrals fully paid or on time.



 2022 IMPACT FEE DEFERRAL REPORT                                                                              2
Deferral data
Table 1: Total deferral by type of impact fee
                                                                       Deferrals not paid fully
 Type of impact fee           Deferrals requested   Deferrals issued   or on time

   Fire protection facility             1                     1                   0

           Parks                       463                   463                 136

          Schools                      461                   461                 136

      Transportation                   469                   469                 138

     Total impact fees
                                       1,394                 1,394               410




Table 2: Fire protection facility impact fee deferrals
                                                                       Deferrals not paid fully
Jurisdiction                  Deferrals requested   Deferrals issued   or on time
          Auburn                        1                     1                   0
     Total impact fees                  1                     1                   0




Table 3: Park deferrals
                                                                       Deferrals not paid fully
 Jurisdiction                 Deferrals requested   Deferrals issued   or on time

           Auburn                       1                     1                   0

          Buckley                       10                    10                  0

          Ferndale                      27                    27                  0

       Kitsap County                   267                   267                  0

          Olympia                       20                    20                  0

         Ridgefield                    136                   136                 136

      University Place                  2                     2                   0

     Total impact fees                 463                   463                 136


 2022 IMPACT FEE DEFERRAL REPORT                                                              3
Table 4: School facility deferrals
                                                                  Deferrals not paid fully
 Jurisdiction            Deferrals requested   Deferrals issued   or on time

         Auburn                    1                     1                   0

         Buckley                   10                    10                  0

         Ferndale                  27                    27                  0

       King County                 2                     2                   0

      Kitsap County                267                  267                  0

         Olympia                   18                    18                  0

        Ridgefield                 136                  136                 136

     Total impact fees             461                  461                 136




Table 5: Transportation deferrals
                                                                  Deferrals not paid fully
 Jurisdiction            Deferrals requested   Deferrals issued   or on time

         Auburn                    1                     1                   0

         Buckley                   10                    10                  0

         Ferndale                  27                    27                  0

      Kitsap County                267                  267                  0

         Olympia                   22                    22                  0

        Ridgefield                 136                  136                 136

     University Place              6                     6                   2

     Total impact fees             469                  469                 138




 2022 IMPACT FEE DEFERRAL REPORT                                                        4


File and source

File
2022_commercereports-2022-impact-fee-deferral-report-a5b61f85-b5c2-41e1-914.pdf
Size
320,905 bytes
SHA-256
d091c53207c7bbe364df593398a5f0ab5376231715e0ae50478fdfea0336ddf7
Our copy
2022_commercereports-2022-impact-fee-deferral-report-a5b61f85-b5c2-41e1-914.pdf
Original
app.leg.wa.gov
Back to top