Summary

This is written testimony in support of House Bill 372, dated 3/7/2022, to the House Commerce and Labor Committee from Tim Courtad, President and Partner of Pride One Construction in Medina, OH. The firm describes itself as a mid-sized general contracting, construction management and development company that has completed over $1.5 billion in construction value. It says the bill would allow certain building inspection decisions to be appealed expeditiously at the contractor's cost and discretion. The testimony lists problems the firm says it has experienced, including delays from code discrepancies, a failed inspection over draft stopping requirements, differing inspectors, and 4-6+ months to obtain a full permit. It encourages the committee to vote the bill out.

Summary drafted by a model from the document's text below and checked by script against that text before publication. It is a navigation aid, not a reading of what the document proves. Where AI is used

Cite this document

“HB 372 — Tim Courtad, Pride One Construction (3/7/2022).” Archived at Pandemic Darlings, https://pandemicdarlings.com/source-documents/2022-03-08-commerce-labor-testimony-hb372proprideonewritten-ca004172f2/, SHA-256 c1b18ab879fe682d4e1dbe735bbc5640ede2b4194821ea186649fee3e7f05276.

Full text

            3/7/2022

            House Commerce and Labor Committee

            RE: HB 372

            Chair Stein, Vice Chair Johnson, Ranking Member Lepore-Hagan and Members of the
            Committee:

            My name is Tim Courtad, writing on behalf of Pride One Construction in Medina, OH to show
            our collective support for House Bill 372.

            Pride One Construction is a mid-sized firm offering General Contracting, Construction
            Management, and Development services. Since our inception, we have completed over $1.5
            billion in construction value, supported hundreds of local subcontractors, and worked with many
            of the local building departments in the State of Ohio. Our support of House Bill 372 reflects
            over thirty years of experience in the construction industry and what we feel would be a
            tremendous opportunity to improve the lives of Contractors and Subcontractors amid increasing
            burdens of workforce shortage, material delays, and continuing scrutinization.

            House Bill 372 proposes a change to the building inspection process that would allow for certain
            decisions to be appealed expeditiously at the Contractor’s cost and discretion. Current Ohio law
            has a gap in the building inspection process that allows certain Ohio building departments to
            impact projects through a lengthy rejection delay, causing great expense and creating negative
            downstream effects on our Subcontractors with no ability to appeal such decisions in a timely
            manner.

            Specifically, we feel that House Bill 372 will help mitigate the following issues we have
            experienced in recent years:

               •   Project delays resulting from code discrepancies between the Ohio Building Code and a
                   fully Permitted set of drawings which could have been avoided through an expedited
                   appeal by having a review board verify that Work was performed per Code despite such
                   not being reflected on the Permit drawings.

               •   Increased costs because of a failed inspection due to a building inspector’s
                   misinterpretation the Code’s draft stopping requirements. While the code was clear in
                   our favor, the Project constraints did not include a long delay for an appeal and forced us
                   to take on extra cost to avoid the delay.

               •   Discrepancies in how the Local Building Department inspector, the Local Fire
                   Department, the State Fire Marshal, and/or the State Elevator inspector interpret the
                   Code. There are often situations where these parties are not in agreement on life safety
                   requirements and compromises need to be made that impact our time and budget because
                   of not being able to appeal their decisions in a timely manner.

2211 Medina Road, Suite 100 • Medina, Ohio 44256
Phone: 330.239.6100 • Fax: 330.239.6200                                                 www.prideoneconstruction.com
               •   Differing inspectors on a weekly, sometime daily, basis: One day an inspector would say
                   something was acceptable. The next day, a different inspector would come to the site and
                   red tag the same item that the previous inspector said was OK.

               •   Difficulties during the plan review process, including continuously addressing the same
                   comments with drawing revisions, having those items approved, but then receiving new
                   comments added on the review. This happened multiple times and even though we had a
                   conditional permit, we couldn’t achieve a full permit for 4-6+ months.

               •   Differing protocols from plan reviewers, including a lack of documentation. This can
                   cause confusion and delays for Contractors if conversations are not documented or
                   recorded properly.

            We are in support of this Bill and believe that an expedited appeal process will give Contractors
            the option of putting the fate of their Project in their own hands. We further believe that
            implementation of this Bill will have a compounding effect on building inspections, resulting in
            more accurate and timely inspections because of this check and balance on the current process.

            Pride One Construction offers its full support of this bill and encourages this committee vote
            House Bill 372 out of committee.

            Tim Courtad
            President and Partner
            Pride One Construction
            2211 Medina Rd. Suite 100
            Medina, Ohio 44256
            O: 330.485.0678
            C: 330.310.9849
            tcourtad@prideone.cc




2211 Medina Road, Suite 100 • Medina, Ohio 44256
Phone: 330.239.6100 • Fax: 330.239.6200                                                 www.prideoneconstruction.com


File and source

File
2022-03-08_commerce-labor_testimony_hb372proprideonewritten.pdf
Size
251,708 bytes
SHA-256
c1b18ab879fe682d4e1dbe735bbc5640ede2b4194821ea186649fee3e7f05276
Our copy
2022-03-08_commerce-labor_testimony_hb372proprideonewritten.pdf
Original
No public link identified.
Back to top