OCIO IT Dashboard Activities: Timeline, April 2019 to January 2020

Summary

The OCIO IT dashboard timeline runs from an April 2019 conference to an October 2019-January 2020 build and go-live, with a contract signed in September 2019. The slide puts the amount spent to date at $131,802.50 committed in the statement of work.

Summary drafted by a model from the document's text below and checked by script against that text before publication. It is a navigation aid, not a reading of what the document proves. Where AI is used

Cite this document

“OCIO IT Dashboard Activities: Timeline, April 2019 to January 2020.” Archived at Pandemic Darlings, https://pandemicdarlings.com/source-documents/2020-01-14-a26222-d208671-derek-puckett-ited-200114-2ec80a24de/, SHA-256 a6d2c8398197ca606650a59a12543cfbc2a8fa771727053b88b0c53c8fc430f8.

Full text

                      OCIO IT Dashboard Activities - Timeline
    April 2019 – Conference                 July-August 2019 - Onboarding            October 2019-January 2020 –
    Budget including Dashboard              and training agencies and projects       Dashboard build, design and
    and oversight requirements              on new oversight requirements,           go live.
    passed legislature                      draft RFQQ for dashboard support,
                                            release RFQQ.

                   May-June 2019 – Process
                   development for project data                     September 2019 – Contract
                   gathering, dashboard proof of                    signed, vendor on-boarded,
                   concept with existing contract.                  vendor discovery phase




1
                   Amount spent to date: $131,802.50 committed in SOW.




    Deliverables:
    Deliverables Certified: Vendor discovery, backend build, front end design and
    closeout documents.




                   Next steps: Prioritize product backlog and plan future development
                   activities.



2


File and source

File
2020-01-14_a26222_d208671_derek-puckett-ited-200114.pdf
Size
147,405 bytes
SHA-256
a6d2c8398197ca606650a59a12543cfbc2a8fa771727053b88b0c53c8fc430f8
Our copy
2020-01-14_a26222_d208671_derek-puckett-ited-200114.pdf
Original
No public link identified.
Back to top