OCIO IT Dashboard Activities: Timeline, April 2019 to January 2020
Summary
The OCIO IT dashboard timeline runs from an April 2019 conference to an October 2019-January 2020 build and go-live, with a contract signed in September 2019. The slide puts the amount spent to date at $131,802.50 committed in the statement of work.
Summary drafted by a model from the document's text below and checked by script against that text before publication. It is a navigation aid, not a reading of what the document proves. Where AI is used
Cite this document
“OCIO IT Dashboard Activities: Timeline, April 2019 to January 2020.”
Archived at Pandemic Darlings, https://pandemicdarlings.com/source-documents/2020-01-14-a26222-d208671-derek-puckett-ited-200114-2ec80a24de/
, SHA-256 a6d2c8398197ca606650a59a12543cfbc2a8fa771727053b88b0c53c8fc430f8.Full text
OCIO IT Dashboard Activities - Timeline
April 2019 – Conference July-August 2019 - Onboarding October 2019-January 2020 –
Budget including Dashboard and training agencies and projects Dashboard build, design and
and oversight requirements on new oversight requirements, go live.
passed legislature draft RFQQ for dashboard support,
release RFQQ.
May-June 2019 – Process
development for project data September 2019 – Contract
gathering, dashboard proof of signed, vendor on-boarded,
concept with existing contract. vendor discovery phase
1
Amount spent to date: $131,802.50 committed in SOW.
Deliverables:
Deliverables Certified: Vendor discovery, backend build, front end design and
closeout documents.
Next steps: Prioritize product backlog and plan future development
activities.
2
File and source
- File
- 2020-01-14_a26222_d208671_derek-puckett-ited-200114.pdf
- Size
- 147,405 bytes
- SHA-256
- a6d2c8398197ca606650a59a12543cfbc2a8fa771727053b88b0c53c8fc430f8
- Original
- No public link identified.